Orient Green Power ruling supports Rs 12.98 crore recovery
Key highlights
- APTEL’s November 17, 2026 order supports Orient Green Power’s estimated Rs 12.98 crore receivable through its material subsidiary.
- The Rs 12.98 crore estimate includes Rs 5.93 crore of principal and Rs 7.05 crore of interest.
- The ruling covers a 50.4 MW Andhra Pradesh wind project and a 23% CUF payment dispute.
- APERC had set a Rs 0.50-per-unit rate above 23% CUF, versus the Rs 4.70-per-unit PPA tariff.
powered by IRIS

Orient Green Power Company Limited said the November 17, 2026 Appellate Tribunal for Electricity ruling supports a Rs 12.98 crore estimated receivable, including interest, for its material subsidiary’s 50.4 megawatt wind project in Andhra Pradesh. The amount remains subject to implementation of the order and collection from the power purchaser.
Know Orient Green Power Company inside out
Results, valuation, peers and who's buying, in one view.
What did the APTEL order decide for Orient Green Power?
The Appellate Tribunal for Electricity, or APTEL, held on November 17, 2026 that the 23% normative capacity utilisation factor, or CUF, was a tariff-determination benchmark rather than a ceiling on payment for electricity supplied under the power purchase agreement, or PPA. Orient Green Power announced the ruling on November 19, 2026 after APTEL set aside the restrictive Andhra Pradesh Electricity Regulatory Commission, or APERC, order.
The order concerns Beta Wind Farm Private Limited, Orient Green Power’s material subsidiary, and its 50.4 megawatt, or MW, wind project in Andhra Pradesh. APTEL directed Southern Power Distribution Company of Andhra Pradesh Limited, or APSPDCL, to release withheld payments with interest in accordance with the PPA, as stated in the company’s November 2026 disclosure.
APTEL also rejected APERC’s cumulative-CUF computation and the Rs 0.50-per-unit rate applied to generation above the 23% benchmark. Orient Green Power said energy delivered under the PPA is payable at the applicable PPA tariff even where annual generation exceeds 23% CUF, which is the stated basis for the subsidiary’s Rs 12.98 crore receivable estimate.
How is Orient Green Power’s Rs 12.98 crore receivable calculated?
Orient Green Power estimates the subsidiary’s receivable at Rs 12.98 crore, comprising Rs 5.93 crore of withheld principal and Rs 7.05 crore of interest. The interest figure consists of Rs 3.09 crore claimed up to March 2022 and Rs 3.96 crore for April 2022 to October 2026.
The Rs 5.93 crore principal relates to 1,26,17,939 units supplied between July 27, 2016 and July 27, 2017. APSPDCL withheld the payment on the basis that these units were generated beyond the 23% CUF benchmark, while the subsidiary maintained that the PPA tariff applied to the supply.
The disclosed interest increased from Rs 3.09 crore through March 2022 to a further Rs 3.96 crore for April 2022 to October 2026. Orient Green Power described Rs 12.98 crore as its own estimated receivable, while saying APTEL directed release of the withheld amount with interest in accordance with the PPA.
What was the tariff dispute at the Andhra Pradesh project?
The dispute arose under a 25-year PPA dated May 29, 2013 between the subsidiary and APSPDCL for the 50.4 MW Andhra Pradesh wind project. The project was commissioned on July 27, 2013, and its APERC-determined tariff was Rs 4.70 per unit, according to Orient Green Power’s November 2026 investor update.
APERC’s September 26, 2022 order limited the Rs 4.70-per-unit tariff to generation up to a cumulative CUF of 23%. It provided Rs 0.50 per unit for generation beyond that level, a Rs 4.20-per-unit difference from the PPA tariff cited in the announcement.
The subsidiary appealed the September 2022 APERC order to APTEL, while APSPDCL filed a cross-appeal. Orient Green Power said the matters were heard together with related appeals before APTEL’s November 17, 2026 order set aside APERC’s payment restriction.
Got a follow-up? Ask IRIS
What could the ruling mean for Orient Green Power’s cash flow?
Orient Green Power said collection of the Rs 12.98 crore estimated receivable would support the subsidiary’s cash flows, but it did not describe the amount as cash received. Its November 19, 2026 announcement states that the timing and realisation depend on implementation of APTEL’s order and actual receipt of dues from APSPDCL.
The recovery relates to the subsidiary, which operates 241.6 MW of wind projects across Tamil Nadu, Andhra Pradesh, Gujarat and Karnataka. Orient Green Power separately reported approximately 381.7 MW of Indian wind capacity, a 10.5 MW wind farm in Croatia and a 24.6 MW solar power plant in Tamil Nadu.
For the FY26 period disclosed in the release, Orient Green Power reported consolidated total income of Rs 315.57 crore, earnings before interest, taxes, depreciation and amortisation of Rs 205.45 crore, and net profit of Rs 71.57 crore. The company did not quantify how the Rs 12.98 crore collection would affect those reported FY26 figures or future financial results.
What happens next after the APTEL ruling?
Orient Green Power management said it remains focused on implementing APTEL’s November 17, 2026 order and recovering approximately Rs 12.98 crore. Managing Director and Chief Executive Officer T. Shivaraman said the ruling reaffirmed the agreed tariff for electricity supplied under the PPA irrespective of generation exceeding the 23% normative CUF.
The immediate unresolved matter is collection from APSPDCL, rather than APTEL’s finding that the 23% CUF was not a payment ceiling. Orient Green Power’s safe-harbour statement says expected recoveries and cash-flow effects are forward-looking and subject to risks, uncertainties and assumptions.
Orient Green Power did not disclose a payment deadline for APSPDCL, an enforcement timetable, or an updated interest calculation beyond October 2026. The disclosed Rs 3.96 crore interest component covers April 2022 to October 2026, so the final cash amount and timing depend on implementation under the 25-year PPA.
Conclusion
APTEL’s November 17, 2026 order removes the APERC approach that paid Rs 0.50 per unit for generation above the 23% CUF benchmark at the 50.4 MW project. For Orient Green Power, the ruling supports the PPA tariff of Rs 4.70 per unit and underpins its estimated Rs 12.98 crore receivable, including Rs 5.93 crore of principal and Rs 7.05 crore of interest.
The next item to watch is implementation by APSPDCL and actual receipt of the dues, as Orient Green Power has not disclosed a collection date. Management’s disclosed plan is to pursue implementation and recovery, while the current interest estimate only runs through October 2026.