Patil Automation plans Rs 60 crore expansion, Rs 580 crore capacity
Key highlights
- Patil Automation plans about Rs 60 crore of construction and machinery spending for a new 2 lakh square foot facility.
- Management expects annual revenue capacity to rise from about Rs 280 crore to about Rs 580 crore by May 2027.
- Patil Automation has planned FY28 revenue of more than Rs 380 crore, below the about Rs 580 crore post-expansion capacity.
- Standalone H1 FY27 total income rose about 41% year on year to about Rs 104 crore.
powered by IRIS

Patil Automation Limited plans a Rs 60 crore facility that management expects to be ready by May 2027, lifting annual revenue capacity from about Rs 280 crore to about Rs 580 crore. Management said the added capacity is intended to support its planned FY28 revenue of more than Rs 380 crore without another facility currently being required.
Know Patil Automation inside out
Results, valuation, peers and who's buying, in one view.
What will Patil Automation's Rs 60 crore expansion add?
Patil Automation plans to spend about Rs 60 crore on construction and machinery for a new facility that management expects to add about Rs 300 crore of annual revenue capacity. Management put current capacity at around Rs 280 crore, implying combined old and new capacity of around Rs 580 crore once the new site is operational.
The new facility is planned to include a 2 lakh square foot shed on about 10 acres of land. Management said the land had been finalised and the agreement was planned as a 30-year lease, while construction was expected to start in December 2026. The Rs 60 crore figure covers the proposed construction and machinery, rather than a reported completed capital expenditure.
The expansion represents a material increase from the current Rs 280 crore capacity base. Management's FY28 revenue plan of more than Rs 380 crore would remain below the planned Rs 580 crore combined capacity, while its FY27 revenue target is Rs 250 crore to Rs 260 crore. Capacity is management's estimate of potential revenue throughput, not a forecast of booked sales.
When will Patil Automation's new facility start operating?
Patil Automation expects the facility to be ready by May 2027, after construction begins in December 2026 and is tentatively completed by the end of April 2027. Management said actual work could start at the plant in May, allowing the company to use both existing capacity and the additional site during FY28.
The May 2027 target follows an earlier addition to Patil Automation's footprint. During the H1 FY27 call on November 12, 2026, management said a Faridabad facility had already been commissioned alongside three plants at Chakan. The planned new site would provide another 2 lakh square feet as the company seeks larger automation projects.
Management said its normal project-execution cycle is around three to four months. That timing means the May 2027 facility start falls after the end of FY27 and within FY28, the period in which management has planned more than Rs 380 crore of revenue. The call did not disclose further construction milestones, contractor details or a phased commissioning plan.
Can Patil Automation support its FY28 revenue plan with this capacity?
Patil Automation said the planned new facility and existing sites should be sufficient for its FY28 revenue plan of more than Rs 380 crore, and management said no further facility is currently required. The FY28 plan is more than Rs 120 crore above the upper end of the Rs 250 crore to Rs 260 crore FY27 target, while remaining about Rs 200 crore below planned capacity of Rs 580 crore.
The capacity plan follows growth in H1 FY27. On a standalone basis, total income rose about 41% year on year to about Rs 104 crore, earnings before interest, tax, depreciation and amortisation (EBITDA) rose about 39% to about Rs 18 crore, and net profit rose about 38% to about Rs 10.4 crore. Consolidated total income increased about 36% year on year to about Rs 100 crore.
Management said it expects EBITDA margin to remain in a 17% to 19% range and profit after tax margin to be about 10.5% in FY27 and FY28. Standalone EBITDA margin in H1 FY27 was about 17%, broadly in line with H1 FY26, while consolidated EBITDA margin was about 19.4%, up around 180 basis points year on year. A basis point is one-hundredth of a percentage point.
Got a follow-up? Ask IRIS
What orders and business mix are expected to use the added capacity?
Patil Automation reported an order book of more than Rs 130 crore and an order pipeline of about Rs 800 crore in November 2026, with management planning about Rs 200 crore of business in hand by the end of March for the next financial year's first quarter. Management also said it expected to close about Rs 50 crore of additional business by the end of November.
Management's stated order-book strategy allocates 60% to automotive and electric vehicles, 20% to defence, and 20% to data centres and heavy equipment automation. It said the more than Rs 130 crore order book broadly followed that 60:20:20 mix. This is a planned portfolio mix, rather than a disclosed revenue split for H1 FY27.
Patil Automation is also seeking larger assignments. Management said individual order sizes currently range from Rs 1 crore to Rs 13 crore, but it has set a minimum order value of Rs 2 crore and described major projects as being around Rs 10 crore. The larger facility is intended to accommodate this move toward higher-value projects as the company pursues FY28 revenue above Rs 380 crore.
In defence, management said its subsidiary Mii Robotics had orders from five customers worth more than Rs 30 crore for artillery-shell manufacturing lines, including assembly, machining and welding equipment. It also cited automated bullet-manufacturing lines and Magnetic Particle Inspection, or MPI, projects. In renewable energy, management said PAL Green Energy was planned to generate around Rs 20 crore of business by the end of FY27 from solar-tracking and related work.
What execution issues could affect the expansion plan?
Patil Automation said working-capital timing varies by project size, with some projects taking 90 to 110 days and larger assignments reaching about 150 days. Management said the first line developed for a customer generally takes longer, while later lines should require less time. This matters as the company seeks larger Rs 10 crore-scale projects and adds capacity for FY28.
Management also said some large defence projects were ready but had not been dispatched because customer payments were pending. It said cash flow from operations and inventory should improve once those projects are dispatched and cash is realised. The call did not quantify the payment amount, expected collection date or the share of the Rs 60 crore project cost already committed.
Conclusion
Patil Automation's proposed Rs 60 crore facility would more than double management's stated revenue capacity from about Rs 280 crore to about Rs 580 crore by May 2027. The planned capacity is larger than the more than Rs 380 crore FY28 revenue objective, while the 60:20:20 order strategy points to automotive and electric vehicles, defence, and data centres or heavy equipment as the intended demand base.
The next disclosed milestones are the planned December 2026 construction start, tentative end-April 2027 completion and May 2027 operating start. Management's FY27 target remains Rs 250 crore to Rs 260 crore, and it plans about Rs 200 crore of business in hand by March; progress on those targets, plus dispatches and payment collection on ready defence projects, will show how the expansion is being supported.