Power Mech targets Rs 500 crore mining revenue in FY27
Key highlights
- Power Mech targets more than Rs 500 crore of combined mining revenue in FY27.
- KBP generated Rs 119 crore in the first half of FY27 against a Rs 350 crore full-year target.
- KBP washery construction was 85% complete, with completion targeted by end-January 2027.
- Tasra generated almost Rs 50 crore in the first half and is expected to reach 2 million tonnes in FY28.
powered by IRIS

Power Mech targets more than Rs 500 crore of FY27 revenue from its two mines, led by a Rs 350 crore goal at KBP, where washery construction was 85% complete. Management plans to finish the washery by end-January 2027, begin February trials and record one month of washed-coal revenue in March.
Know Power Mech Projects inside out
Results, valuation, peers and who's buying, in one view.
What is Power Mech's FY27 mining revenue target?
Power Mech is targeting more than Rs 500 crore of FY27 revenue from its combined mining operations, with the KBP mine projected to deliver Rs 350 crore. Management said it was confident of crossing the Rs 500 crore mark as KBP production increases in the next two quarters and new machinery raises output. This is management's target, rather than revenue already reported.
KBP generated Rs 119 crore in the first half of FY27 after producing about 7 lakh tonnes, leaving Rs 231 crore to reach its Rs 350 crore annual revenue projection. Management attributed the first-half production level to the rainy season and the start of new seams in the first quarter. It said the production shortfall would be recovered during the third and fourth quarters.
The second-half requirement is substantially higher than the reported first-half outcome. KBP needs Rs 231 crore of revenue in the second half, compared with Rs 119 crore in the first half, while its annual production target is about 3 million tonnes. Management said its revenue projection is based on 2.5 million tonnes, rather than the higher production target.
How far has Power Mech progressed on the KBP washery?
Power Mech had completed 85% of KBP washery construction and is targeting completion by the end of January 2027. Management plans trial runs in February 2027 and expects the washery to operate by March. That timetable would allow for one month of washed-coal revenue in FY27.
The washery is part of infrastructure that also includes a coal handling plant and railway siding, for which management estimated total capital expenditure of around Rs 900 crore. At KBP, project capital expenditure is expected to be around Rs 300 crore to Rs 330 crore because heavy equipment is hired rather than owned. Management said around Rs 150 crore had already been spent at the mine.
Management said it had postponed the balance of around Rs 150 crore of KBP project expenditure because of a client-side delay in the washery. It also said KBP would not require significant additional capital expenditure over the next two years. The commissioning schedule is therefore relevant both to the final-quarter revenue plan and to the timing of the remaining infrastructure spend.
Got a follow-up? Ask IRIS
What is Power Mech's production plan for Tasra?
Power Mech reported Tasra output of 50,000 to 60,000 tonnes a month and almost Rs 50 crore of revenue in the first half of FY27. Revenue was Rs 26 crore in the first quarter and Rs 24 crore in the second quarter. Management confirmed an analyst's assumption that Tasra output is expected to reach 2 million tonnes in FY28.
Tasra's first-half revenue was below KBP's Rs 119 crore, although both mines underpin the target of more than Rs 500 crore of FY27 mining revenue. With KBP projected to contribute Rs 350 crore, the combined plan implies more than Rs 150 crore from Tasra and any other mining contribution beyond that KBP target. Management did not provide a separate FY27 revenue target for Tasra.
Tasra remains in a more capital-intensive phase than KBP. Management said it had incurred around Rs 600 crore of capital expenditure at Tasra and expected another Rs 300 crore by March. By comparison, KBP had incurred around Rs 150 crore against a stated project requirement of Rs 300 crore to Rs 330 crore.
How does mining fit into Power Mech's FY27 outlook?
Power Mech reiterated its earlier FY27 and FY28 guidance, including a minimum FY27 operating margin of 11.6% without other income. Management said lower mining volumes during the rainy season affected the first half, and that higher volume in the second half should support margin recovery. It did not revise its guidance after setting the washery completion target.
Mining is one part of management's plan to increase the contribution from operations and maintenance, or O&M, and mine development and operation, or MDO, work. Management said new O&M orders are expected to add Rs 400 crore to Rs 500 crore of incremental revenue. It projected overall O&M revenue of around Rs 2,100 crore in the current year and around Rs 2,600 crore by FY28.
Management expects the orders received in the first two quarters to contribute to revenue and profitability from FY28 after mobilisation expenses, recruitment and overheads. It said operating margin could improve by 0.25% to 0.5% over FY27 levels as those projects stabilise. For mining, its FY27 confidence rests on KBP's volume recovery, additional machinery and the planned March start of washed-coal revenue.
Conclusion
Power Mech's mining plan is weighted heavily toward the second half of FY27. KBP had generated Rs 119 crore in the first half against its Rs 350 crore full-year target, while Tasra generated almost Rs 50 crore and was producing 50,000 to 60,000 tonnes monthly. Achieving more than Rs 500 crore of combined mining revenue depends primarily on KBP's production ramp and the washery schedule.
The next disclosed milestones are KBP washery construction completion by end-January 2027, trial runs in February and planned operations in March. Management also expects Tasra to reach 2 million tonnes of output in FY28, while another Rs 300 crore of Tasra capital expenditure is expected by March and the remaining KBP expenditure has been deferred following the client-side washery delay.