Powerica targets 1 GW after projects lift wind to 638 MW
Key highlights
- Powerica said wind capacity could rise from 330 MW to 638 MW within two and a half years.
- The first expansion phase includes 250 MW of auction awards and 50 MW already under construction.
- Management plans annual renewable additions of 100 MW to 150 MW across wind, hybrid and battery projects.
- Powerica said it expects to use 70% debt financing for the capacity-doubling project phase.
powered by IRIS

Powerica said in its earnings call that it is targeting a 1 gigawatt (GW) renewable portfolio after secured projects are expected to lift wind capacity to 638 megawatts (MW) within two and a half years. Management outlined a first phase built on 330 MW in operation, 50 MW under construction and 250 MW of auction awards.
Know Powerica inside out
Results, valuation, peers and who's buying, in one view.
How will Powerica reach 638 MW of wind capacity?
Powerica said its first renewable expansion phase will take wind capacity from 330 MW to 638 MW within two and a half years. The plan combines the existing operational portfolio with 50 MW under construction and 250 MW of projects won through reverse-bidding auctions.
Management also described the 330 MW base, 50 MW under construction and 250 MW of awards as taking capacity to “630 MW, something like that.” The later strategic roadmap specified 638 MW, and the call did not disclose project-level figures that reconcile the difference between the rounded calculation and the stated target.
The 250 MW awards comprise one Gujarat Urja Vikas Nigam Limited (GUVNL) project of more than 100 MW, another GUVNL project of more than 50 MW, and a 100 MW Solar Energy Corporation of India (SECI) project. Management said both GUVNL projects have 25-year power purchase agreements (PPAs), while the SECI award is from the central-government entity.
What is the construction status of Powerica's new wind projects?
Powerica said work has started on the 250 MW portfolio, with machines already arriving for the 100 MW GUVNL project. Land procurement was under way for the other projects, described during the call as 50 MW and 100 MW GUVNL and SECI developments, after which management said construction would begin.
Management said wind tenders generally allow 24 months from PPA signing for project execution. It also said Powerica has historically executed projects before the contractual deadline, but it gave no individual commissioning date for the 50 MW under construction or for the three auction awards.
The two-and-a-half-year timeline to 638 MW covers projects at different stages, including equipment delivery for 100 MW and land procurement for the remaining 150 MW. That means the portfolio target is broader than a single construction milestone and remains dependent on progress in land development and execution.
What is Powerica's renewable strategy after 638 MW?
Powerica plans to add 100 MW to 150 MW of renewable capacity each year after the first phase, according to management. The planned additions span wind, wind-solar hybrid projects and batteries, with the stated ambition of building a portfolio of up to 1 GW in the renewable sector.
At the stated 638 MW first-phase level, Powerica would need another 362 MW to reach 1 GW. Management did not provide a target year for that objective, so the timing depends on future project additions, bid wins, land procurement and the pace of execution.
Powerica also plans to continue engineering, procurement and construction (EPC) work for third-party renewable customers. Management said it had completed 450 MW of third-party EPC work and had about 600 MW in hand, describing the combination of independent power producer (IPP) assets and EPC work as a way to develop larger renewable parks.
Got a follow-up? Ask IRIS
How does Powerica plan to finance renewable growth?
Powerica said its existing 330 MW wind business was practically debt-free after its initial public offering. For the next phase that is intended to take capacity to 638 MW, management said it expects to use 70% debt financing at the project level.
Management did not disclose the capital cost, interest rate, repayment terms or equity contribution for the 250 MW of new awards and the 50 MW under construction. The 70% figure therefore sets out the intended debt share, but not the absolute borrowing requirement or effect on consolidated debt.
Powerica also said it has signed a joint-venture agreement with GE Vernova for joint project development. Management said discussions were ongoing and that an announcement on GE-related projects would come soon, but it disclosed no capacity, investment amount, location or timetable for those developments.
What margins does Powerica expect from its renewable business?
Powerica said its blended earnings before interest, tax, depreciation and amortisation (EBITDA) margin across old and new wind projects was 62% to 65%. Management said new projects carry EBITDA margins of about 82% to 85%, though it did not provide tariff, revenue, operating-cost or generation data behind those ranges.
Management expects the addition of newer capacity could raise the blended wind margin to about 72% to 73%. This is a management expectation rather than a reported target for a specified financial year, and it depends on the company continuing to add renewable projects beyond the 638 MW phase.
The call showed a different margin profile across Powerica's businesses. Management put normal-scenario consolidated genset margin at about 9%, EPC margin at about 10%, and the blended wind IPP margin at an average of 62%, linking the renewable capacity build-out to a larger share of recurring generation assets.
Conclusion
Powerica has set out a renewable expansion sequence that starts with moving from 330 MW of operational wind capacity to a stated 638 MW within two and a half years. The first phase combines 50 MW under construction with 250 MW of awards, while the longer plan calls for annual additions of 100 MW to 150 MW across wind, hybrid and battery projects toward 1 GW.
The next developments to watch are machine deliveries and construction at the 100 MW GUVNL project, land procurement for the other 150 MW of awards, and progress on the 50 MW already under construction. Management's 70% debt-financing plan, the general 24-month PPA execution period and any announced projects with GE Vernova will provide further detail on the route to 1 GW.