PSP Projects Limited H1 revenue rises 61% as backlog grows
Key highlights
- PSP Projects reported record H1 FY27 revenue of Rs 1,967 crore, up 61% year on year.
- PSP Projects' order book was Rs 12,872 crore on September 30, 2026, up 30% year on year.
- Group projects accounted for approximately Rs 9,229 crore, or 72%, of PSP Projects' work on hand.
- PSP Projects secured approximately Rs 1,305 crore of orders in H1 FY27, including Rs 675 crore in Q2 FY27.
powered by IRIS

PSP Projects Limited reported record H1 FY27 revenue of Rs 1,967 crore, up 61% year on year for the half year ended September 30, 2026, while its order book reached Rs 12,872 crore. Group projects accounted for approximately Rs 9,229 crore, or 72%, of work on hand, linking the revenue increase to a multiyear, group-weighted execution pipeline.
Know PSP Projects inside out
Results, valuation, peers and who's buying, in one view.
How fast did PSP Projects' revenue and profit grow in H1 FY27?
PSP Projects increased H1 FY27 revenue from operations by 61% year on year to Rs 1,967 crore, its highest half-yearly revenue, while earnings before interest, tax, depreciation and amortisation, or EBITDA, rose 66% to Rs 124 crore. Profit after tax increased 193% to Rs 48 crore, and management attributed the six-month result to project execution and improved availability of labour and other execution resources.
Q2 FY27 accounted for more than half of first-half revenue. Revenue was Rs 1,113 crore in Q2 FY27, up 58% from Rs 703 crore in Q2 FY26; EBITDA rose 38% to Rs 69 crore from Rs 50 crore, while profit after tax increased 87% to Rs 30 crore from Rs 16 crore.
Margins did not move in line with the revenue growth rate. H1 FY27 EBITDA margin was 6.30%, compared with 6.12% in H1 FY26, but Q2 FY27 EBITDA margin was 6.21%, below 7.10% a year earlier; employee costs increased to Rs 50 crore from Rs 33 crore, which management attributed to annual increments and a larger workforce.
What does PSP Projects' Rs 12,872 crore order book contain?
PSP Projects had work on hand of Rs 12,872 crore as of September 30, 2026, up 30% year on year. Group projects contributed approximately Rs 9,229 crore, or 72%, while external projects made up the remaining 28%, making group projects the larger source of future execution in the reported backlog.
The current order book is more concentrated in group projects than the active bidding pipeline. Management said the bid pipeline exceeded Rs 7,800 crore, comprising 52% group projects and 48% external projects, compared with the 72%-28% group-external split in work on hand.
Management said no project in the existing order book had a maximum timeline beyond 36 months. It estimated that the Rs 12,872 crore backlog could be executed in around 2.5 years and, at most, three years, setting an indicated period for converting work on hand into revenue.
Order inflow during H1 FY27 was approximately Rs 1,305 crore, including Rs 675 crore in Q2 FY27. The second-quarter additions covered healthcare, airport infrastructure, office buildings, refurbishment and steel-accommodation projects from Adani Group, according to management.
Got a follow-up? Ask IRIS
Which contracts are driving PSP Projects' current execution?
PSP Projects identified the Rs 931 crore Shree Ambaji Mata Temple project as its largest disclosed outstanding contract. General development, cutting and filling, foundations, plinth work and building work were under way at different stages, while the Rs 613 crore SMC high-rise project had completed reinforced cement concrete, or RCC, work.
At the SMC high-rise, mechanical, electrical and plumbing, or MEP, work had been completed through the 15th floor; interior work was under way from the first to fifth floors and facade work from the fifth to 10th floors. Other named contracts included the Rs 251 crore Fintech Building at GIFT City and the Rs 238 crore Human and Biological Science Gallery at Science City.
The company also disclosed a Rs 187 crore residential project in GIFT City, where RCC work had been completed up to the ground floor and work continued at the first, second and third levels across blocks A to D. Its other named contracts included the Rs 171 crore Dharoi Dam region development and Rs 155 crore Sabarmati Riverfront Development Phase 2, spanning tourism-related development, buildings and urban infrastructure.
How is PSP Projects managing capacity, project delivery and costs?
PSP Projects completed 17 projects during Q2 FY27, including Project Ninety, where it completed the RCC structure for three basement levels, a ground floor and 18 upper floors in 121 days. Management described the Gujarat project as one of the fastest precast high-rise projects executed in the state and cited its precast capability as supporting speed and labour deployment.
The company also completed its new corporate house adjacent to Project Ninety in 240 days, including MEP and interior fit-out work, and said it would begin operations there on November 4, 2026. Management said it was progressing with capacity enhancement at its precast facility in response to demand across building and infrastructure projects.
For the Rail Vikas Nigam Limited, or RVNL, project, management said it had handed over two of three buildings, identified as the lab and lab building. Flooring, MEP, interior and facade work remained under way at the hostel building, showing that the quarter included both handovers and unfinished execution stages.
Management said its Adani Group work operates on a cost-plus percentage basis, with material-cost differences reimbursed by the group. It also said approximately 75% of bills for group projects were cleared within seven to 10 days and the remaining 25% generally in the following month; for the Ambaji project, management said cement and steel escalation was covered through the Reserve Bank of India index rather than direct pass-through.
Conclusion
The H1 FY27 result combined higher execution with a larger project base: revenue rose 61% to Rs 1,967 crore, EBITDA rose 66% to Rs 124 crore and work on hand increased 30% year on year to Rs 12,872 crore. The order book provides an indicated 2.5- to three-year execution window, although its approximately 72% group-project share means the composition of that customer category remains central to delivery.
Next, investors can watch progress on the Rs 931 crore Ambaji and Rs 613 crore SMC contracts, along with the planned precast-facility capacity enhancement. Management also indicated an order-inflow range of approximately Rs 4,000 crore to Rs 5,000 crore and said the bid pipeline exceeded Rs 7,800 crore, while describing its EBITDA-margin outlook as within the H1 range with potential movement of plus or minus 1%.