Saatvik Green Energy Limited begins Odisha output at 1.3 GW
Key highlights
- Saatvik began commercial production from approximately 1.3 GW of Odisha module capacity on 2 November 2026.
- Saatvik expects its Phase 1 Odisha module line to reach 4 GW by December 2026.
- Saatvik's 2.4 GW Odisha cell line is in trial runs, with production ramp-up targeted for December 2026.
- Saatvik reported a 6.68 GW confirmed order book at the end of H1 FY27, including 1.76 GW of new orders.
powered by IRIS

Saatvik Green Energy Limited began commercial production from approximately 1.3 GW of module capacity at Gopalpur, Odisha, on 2 November 2026, and expects its Phase 1 module line to reach 4 GW by December 2026. The 57-acre Phase 1 campus also contains a 2.4 GW cell line that has entered trial runs.
Know Saatvik Green Energy inside out
Results, valuation, peers and who's buying, in one view.
What has Saatvik commissioned at the Odisha campus?
Saatvik has commissioned approximately 1.3 GW of commercial module capacity at its Gopalpur facility, effective 2 November 2026. The company identifies this as the operational first portion of a 4 GW Phase 1 module line, separating it from the site’s cell operation, which remains in the trial-run stage.
The Phase 1 campus spans 57 acres and is designed to combine 4 GW of module capacity with 2.4 GW of cell capacity. The presentation calls the Odisha location a next-generation integrated hub, while describing the Ambala, Haryana location as its established manufacturing base. Odisha is shown with modules, cells, ingots and wafers, and encapsulant, whereas Ambala is shown with modules, encapsulant, transformers, inverters, batteries and ancillaries.
Commercial production at 1.3 GW means the Odisha facility has moved beyond construction for part of its module line, but the disclosed Phase 1 capacity remains partly under ramp-up. Management said the commencement marked an important milestone in the company’s manufacturing plan, while the project-status page specifies further testing and validation steps before the line reaches 4 GW.
When will Saatvik's Odisha module line reach 4 GW?
Saatvik expects the full 4 GW Phase 1 Odisha module line to be available by December 2026. The remaining work listed by the company includes tool and utility testing, validation, trial runs, performance verification, process optimisation and stabilisation after the 1.3 GW commercial start.
The planned increase from 1.3 GW operational capacity to 4 GW represents approximately 2.7 GW of further module capacity. Separately, Saatvik’s overall capacity outlook lists 6.1 GW of live module capacity, an additional 2.7 GW by December 2026 and total module capacity of 8.8 GW. The source does not explain how the 4 GW Odisha Phase 1 line and the group-level 2.7 GW module addition are reconciled.
The December 2026 target is also important because the company’s broader manufacturing table describes modules as established, with 6.1 GW live and a further 2.7 GW planned by that month. This compares with cells, which are described as under construction, showing that module capacity is scheduled to become operational before the company’s planned cell manufacturing base is fully ramped up.
What is the status of Saatvik's Odisha cell lines?
Saatvik has started trial runs on the 2.4 GW Phase 1 Odisha cell line and targets production ramp-up by December 2026. Management said production activities are in progress, but the presentation does not state that commercial cell production has commenced, unlike its explicit statement that 1.3 GW of module capacity has entered commercial production.
An inspection for the Approved List of Models and Manufacturers, List-II, or ALMM List-II, is planned for November 2026 for the 2.4 GW cell line. The presentation’s capacity table also gives Q3 FY27 as the production timing for cells, consistent with the December 2026 ramp-up target disclosed for the Odisha Phase 1 line.
Saatvik has also commenced structural and civil works for Phase 2 at Odisha. That project covers 27 acres and is planned to add 3.6 GW of cell capacity. The group capacity outlook places the 3.6 GW Phase 2 addition by the start of FY28, taking planned cell capacity to 6 GW when combined with the 2.4 GW Phase 1 line.
Got a follow-up? Ask IRIS
How far does Saatvik's integration plan extend?
Saatvik’s manufacturing plan extends from modules into cells, encapsulant, and eventually ingots and wafers. Its capacity outlook shows 6 GW of planned ingot and wafer capacity in Phase III, 6 GW of cell capacity across the two Odisha phases, 5 GW of encapsulant capacity, and 8.8 GW of total module capacity.
The stages are at different points of execution. Saatvik lists 2 GW of encapsulant capacity as commissioned and targets another 3 GW by FY28; it lists the 2.4 GW cell line in trial runs and the 3.6 GW Phase 2 line in civil and structural works. Ingot and wafer capacity remains planned, rather than commissioned or under construction, according to the presentation.
This sequencing means the Odisha project is not yet an operating end-to-end manufacturing campus despite its integrated design. As of 2 November 2026, the company had commercialised 1.3 GW of module capacity, had started cell-line trials at 2.4 GW, and had begun groundwork for a further 3.6 GW of cells. No separate commercial-production date is provided for the Phase 2 cell line beyond the target of the start of FY28 in the capacity outlook.
What operating and order-book data accompany the expansion?
Saatvik reported a confirmed order book of 6.68 GW at the end of H1 FY27, including 1.76 GW of new orders added during the half-year. Management said the order book was about 110% of installed module capacity, linking the expansion plan to a disclosed volume of pending execution.
Revenue from operations was Rs 902.6 crore in Q2 FY27, up 77% quarter on quarter, while earnings before interest, tax, depreciation and amortisation, or EBITDA, were Rs 69.6 crore. Profit after tax reached Rs 20.2 crore in Q2 FY27, compared with Rs 5.4 crore in Q1 FY27. For H1 FY27, revenue from operations was Rs 1,413.6 crore, EBITDA was Rs 112.1 crore and profit after tax was Rs 25.6 crore.
Module production was 658 MW in Q2 FY27 and 1,066 MW in H1 FY27, while module sales were 640 MW and 973 MW, respectively. Production exceeded sales by 18 MW in Q2 and by 93 MW in H1, based on the reported figures. The presentation provides no explanation for the differences between reported output and sales in either period.
Conclusion
Saatvik has started commercial module manufacturing at Odisha with 1.3 GW operational from 2 November 2026, while pursuing a 4 GW Phase 1 module line, a 2.4 GW cell line in trials and a further 3.6 GW Phase 2 cell project. Its 6.68 GW confirmed order book and Rs 902.6 crore of Q2 FY27 revenue provide the reported operating context for that manufacturing expansion.
The next disclosed milestones are the November 2026 ALMM List-II inspection for the 2.4 GW cell line and the December 2026 targets for full 4 GW module capacity and cell-line production ramp-up. Progress on the 3.6 GW Phase 2 cell project by the start of FY28, and clarification of the 4 GW Odisha target against the 2.7 GW group-level module addition, remain matters to watch.