Safety Controls has a ₹590.77 crore order book led by NTPC
Key highlights
- Safety Controls states total order-book contract value of ₹590.77 crore.
- Three disclosed contracts for NTPC Limited and NTPC Renewable Energy Ltd total ₹344.56 crore.
- The eight listed order-book projects total ₹566.67 crore, ₹24.10 crore below the stated total.
- Safety Controls reported FY26 commissioning disclosures for facilities at Jewar and Sector-62, Noida.
powered by IRIS

Safety Controls reported a ₹590.77 crore order book, including three contracts for NTPC Limited and NTPC Renewable Energy Ltd worth ₹344.56 crore. SAFETY CONTROLS & DEVICES LTD. lists the ₹137.43 crore, 945 megavolt ampere (MVA) Bikaner substation package for NTPC Renewable Energy Ltd as its largest disclosed assignment, although its eight displayed contract rows total ₹566.67 crore.
Know Safety Controls & Devices inside out
Results, valuation, peers and who's buying, in one view.
What does Safety Controls' ₹590.77 crore order book contain?
Safety Controls states that the total contract value of its projects is ₹590.77 crore and identifies eight individual contracts valued between ₹22.94 crore and ₹137.43 crore. The largest listed project is a 945 MVA substation package at Bikaner, Rajasthan, for NTPC Renewable Energy Ltd, worth ₹137.43 crore.
The next-largest disclosed contract is a ₹112.18 crore substation package under development of 630 megawatt (MW) capacity at Barethi, Madhya Pradesh, also for NTPC Renewable Energy Ltd. The ₹94.95 crore third-largest project is development of a 20 MW power photovoltaic, or PV, plant at NTPC Rihand Super Thermal Power Station in Sonbhadra, Uttar Pradesh.
The eight listed rows do not fully reconcile with the stated ₹590.77 crore total. Their combined value is ₹566.67 crore, leaving a ₹24.10 crore difference; the presentation does not disclose an additional contract, adjustment or explanation for that gap.
How much of Safety Controls' disclosed work is tied to NTPC?
Safety Controls lists ₹344.56 crore of contracts for NTPC Limited and NTPC Renewable Energy Ltd, representing 58.32% of the stated ₹590.77 crore order-book total. This amount comprises the ₹137.43 crore Bikaner package, the ₹112.18 crore Barethi package and the ₹94.95 crore Rihand PV plant.
The two NTPC Renewable Energy Ltd substation packages total ₹249.61 crore, compared with ₹94.95 crore for the NTPC Limited solar project. The disclosed NTPC workload is therefore concentrated in the two substation assignments by contract value, although the presentation provides no execution timeline, completion percentage or revenue-recognition detail for any of the three projects.
Safety Controls' strategy page says it is executing NTPC projects in Rajasthan and Madhya Pradesh. The Bikaner and Barethi contracts correspond to those two states and together account for ₹249.61 crore, while the Rihand project adds a third NTPC contract in Uttar Pradesh.
Which non-NTPC projects are in Safety Controls' listed order book?
Safety Controls' five non-NTPC project rows total ₹222.11 crore, based on the eight disclosed contracts, led by an ₹82.83 crore assignment for TUSCO Ltd. That project covers a 220 kilovolt (kV) air-insulated substation, or AIS, package for pooling substations PSS1 and PSS2 and related transmission lines at Mau, Chitrakoot, Uttar Pradesh.
Rail Vikas Nigam Limited, or RVNL, has a ₹55.65 crore contract for design, supply, erection, testing and commissioning of traction substations on the Phaphamau-Janghai section in the Prayagraj region. Uttar Pradesh Power Transmission Corporation Limited, or UPPTCL, has two listed contracts worth ₹60.69 crore combined: a ₹33.46 crore 220/132 kV hybrid substation at Jewar and a ₹27.23 crore supervisory control and data acquisition, or SCADA, based 220 kV gas-insulated substation, or GIS, at Sector-62, Noida.
Power Grid Corporation of India Limited, or PGCIL, has the smallest listed contract, valued at ₹22.94 crore. Its scope is a 765 kV AIS substation extension at Bhadla-II, Rajasthan, and an upgrade at Hisar, Haryana, extending the disclosed project locations beyond Uttar Pradesh, Madhya Pradesh and Rajasthan.
Got a follow-up? Ask IRIS
How does Safety Controls' order book compare with its completed projects?
Safety Controls' stated ₹590.77 crore order book is ₹290.15 crore higher than the ₹300.62 crore combined value of the five completed projects displayed in its presentation. The completed-project list is led by a ₹124.87 crore 400/132 kV AIS substation at Masauli, Prayagraj, followed by a ₹73.32 crore 220/33 kV substation at Nadarganj, Kanpur Road.
This is a comparison of disclosed contract values, not of revenue, profit or cash generation. The completed-project table lists work valued at ₹124.87 crore, ₹73.32 crore, ₹36.02 crore, ₹35.18 crore and ₹31.23 crore, but does not provide completion dates, costs, margins or revenue-recognition data.
The mix of work has also broadened in the order-book list. The five completed entries are AIS or grid-substation projects in Uttar Pradesh and Bihar, including ₹31.23 crore of 132/33 kV grid substations at Hathua, Maharajganj, Narkatiyaganj and Areraj, whereas the current list includes a 20 MW PV plant, railway traction substations, a 765 kV extension and GIS or hybrid-substation work.
Have Safety Controls projects at Jewar and Noida been commissioned?
Safety Controls says it commissioned a 220 kV GIS substation for Noida International Airport at Jewar and a 220 kV GIS substation at Sector-62, Noida, in FY26. The order-book page separately lists a ₹33.46 crore 220/132 kV hybrid substation at Jewar and a ₹27.23 crore SCADA-based 220 kV GIS substation at Sector-62.
The Jewar and Sector-62 locations overlap across the FY26 operating highlights and order-book table, but the presentation does not expressly identify the commissioned facilities as the same contracts. It also does not say whether the ₹60.69 crore combined value of the two listed location-based projects remains included in the ₹590.77 crore total after commissioning.
Safety Controls lists end-to-end extra-high-voltage engineering, procurement and construction, or EPC, execution, protection and automation, SCADA and remote terminal unit integration, GIS and AIS substations, high-voltage testing and grid synchronisation among its FY26 capabilities. Those capabilities align with the listed Sector-62 GIS work, the Mau AIS and transmission package, and the Jewar hybrid-substation contract.
Conclusion
Safety Controls' disclosed project portfolio is led by ₹344.56 crore of NTPC Limited and NTPC Renewable Energy Ltd work, including the ₹137.43 crore Bikaner package. Its other listed contracts span ₹82.83 crore of TUSCO substation and transmission work, ₹55.65 crore for RVNL traction substations, ₹60.69 crore for UPPTCL projects and ₹22.94 crore for PGCIL.
The key unresolved point is the ₹24.10 crore difference between the stated ₹590.77 crore total and the ₹566.67 crore sum of eight listed rows, as well as the status of projects at Jewar and Sector-62 after FY26 commissioning disclosures. Management's stated plan to expand its clean-energy portfolio into wind, hydrogen and battery storage, while executing work in Rajasthan, Madhya Pradesh and Haryana, provides the framework for assessing future project updates.