Scoda Tubes shifts welded revenue start to January 2027
Key highlights
- Scoda Tubes expects welded-line revenue to begin in January 2027 after a two-to-three-month construction delay.
- Scoda Tubes budgeted Rs 45 crore for an additional 8,000-metric-tonne annual welded expansion in FY28.
- Aggregate welded capacity is planned to reach 21,150 metric tonnes per annum after H1 FY28 commissioning.
- Q2 FY27 EBITDA was Rs 15.8 crore, down from Rs 22.3 crore in Q2 FY26.
powered by IRIS

Scoda Tubes Limited expects revenue from its delayed welded-pipe facility to start in January 2027, after March and April 2026 construction disruption caused a two-to-three-month setback, while a further 8,000-metric-tonne annual line is targeted for H1 FY28 with a Rs 45 crore budget.
Know Scoda Tubes inside out
Results, valuation, peers and who's buying, in one view.
Why did Scoda Tubes delay welded-line revenue to January?
Scoda Tubes delayed welded-line revenue to January 2027 because construction was held up for two to three months. Management said gas-related disruption in March and April 2026 affected civil contractors and labour, preventing the construction schedule from progressing as planned. At the November 13, 2026 earnings call, it said commissioning and trial runs were under way.
The revised commercial start is in Q4 FY27, replacing an earlier H1 FY27 expectation referenced by an analyst on the call. Management continued to describe trial production as on track for Q4 FY27, but said production contributing revenue would begin in January. The timing gives the facility only the final quarter of FY27 to contribute to the company's 20% to 25% full-year revenue-growth guidance.
The expanded facility will manufacture welded pipes of up to 16 inches in diameter. Scoda Tubes said the larger size range would allow it to pursue broader turnkey packages, including projects linked to cooling infrastructure, industrial water treatment and desalination. It did not disclose firm orders from these end markets as of November 13, 2026.
What is Scoda Tubes planning after the January launch?
Scoda Tubes plans a separate brownfield welded expansion with annual capacity of 8,000 metric tonnes, targeted for commissioning in H1 FY28. Management specified a likely start between April and June 2027, with civil construction under way and procurement of long-lead equipment progressing. The new line would take aggregate welded manufacturing capacity to 21,150 metric tonnes per annum.
The chief financial officer said the total budgeted capital expenditure for the additional 8,000-tonne project is Rs 45 crore, with the remaining investment to be used during FY28. This was more specific than the approximately Rs 40 crore cited in prepared remarks. Management said financing would combine internal accruals and long-term borrowings.
The capacity plan is linked to higher borrowings and solar investment. Gross borrowings stood at Rs 229.2 crore on September 30, 2026, and management expects peak debt of Rs 250 crore, with no immediate repayment plan. It attributed the debt increase to the 8,000-tonne welded project and about 9 megawatts of ground-mounted solar capacity, while saying future free cash flow could be used to reduce debt.
Can the January start support Scoda Tubes' FY27 growth target?
Scoda Tubes maintained FY27 revenue-growth guidance of 20% to 25%, although Q2 FY27 revenue rose 2.5% year on year to Rs 148.9 crore. H1 FY27 revenue increased 12.6% to Rs 273.3 crore from Rs 242.7 crore in H1 FY26. Management said the second half should benefit from improved operating conditions, higher sales volume and the Q4 launch of welded products.
The short January-to-March operating period limits the disclosed evidence on how much welded output can affect FY27 revenue. Scoda Tubes did not give a revenue, utilisation or profit forecast for the new line. Its order book was about Rs 185 crore, entirely for seamless products, with expected execution over four to five months and roughly 40% related to exports.
Seamless utilisation is expected to be about 70% for FY27, below management's stated optimum finished-goods range of 80% to 85%. The company reported higher inventory because it maintained production in anticipation of sales that converted more slowly amid private-player competition. Management expects better alignment of production and demand to help normalise inventory during H2 FY27.
Got a follow-up? Ask IRIS
Which applications and cost changes matter for Scoda Tubes?
Scoda Tubes is pursuing data-centre cooling demand by supplying welded pipes to spool manufacturers and heating, ventilation and air-conditioning manufacturers. Management said it does not intend to produce spools itself. Its sales team was meeting potential data-centre customers, and management said it expected orders before welded production begins, but no signed data-centre order was disclosed.
The new welded activity may alter working-capital timing because management estimates a welded operating cycle of about 130 to 140 days, compared with 180 to 185 days for seamless products. That difference is relevant after inventory days increased in FY27. Management expects the shorter welded cycle, alongside improved sales conversion, to lower overall inventory holding over time.
Margin conditions remain unresolved. Q2 FY27 earnings before interest, tax, depreciation and amortisation, or EBITDA, were Rs 15.8 crore, down from Rs 22.3 crore in Q2 FY26, while the EBITDA margin fell 479 basis points to 10.6% from 15.38%. Management attributed the decline to power and fuel costs rising to 4.9% of revenue from 3.0%, freight rising to 2.9% from 1.4%, and limits on passing costs through amid competition.
Solar generation is intended to reduce electricity costs, rather than gas costs. Scoda Tubes commissioned and synchronised a 4.99-megawatt direct-current solar phase for seamless operations in August 2026. It said dedicated solar capacity for welded operations had already received capital expenditure and would be used when January production starts, without quantifying savings.
Conclusion
The January 2027 start delays Scoda Tubes' welded revenue contribution but does not change management's FY27 growth target of 20% to 25%. The 16-inch welded-pipe capability is intended to broaden access to cooling, water-treatment and desalination applications, while the 8,000-tonne FY28 project would increase aggregate welded capacity to 21,150 metric tonnes annually.
The next disclosed markers are January 2027 commercial production and the planned April-to-June 2027 commissioning of the additional 8,000-tonne line. Management will also need to execute its Rs 45 crore FY28 project budget while gross borrowings move toward its stated Rs 250 crore peak-debt expectation and while it seeks to normalise inventory in H2 FY27.