Skipper Limited cites Rs 7.9 lakh crore grid plan by 2035-36
Key highlights
- India’s transmission plan targets integration of more than 900 GW by 2035-36, with an estimated Rs 7.9 lakh crore opportunity.
- The planned build-out includes 1,37,500 circuit km of transmission lines and 8,27,600 MVA of substation capacity.
- Renewable capacity is projected to rise to 596 GW in FY32E from 191 GW in FY24, lifting its share of total capacity to about 66%.
- India’s transmission network is projected to expand to 6.48 lakh circuit km and 2,342 GVA of transformation capacity by FY32.
powered by IRIS

Skipper Limited says India’s transmission plan is designed to integrate more than 900 GW of capacity by 2035-36, with an estimated Rs 7.9 lakh crore opportunity covering 1,37,500 circuit km of lines and 8,27,600 megavolt-amperes of substations. The plan is being prepared ahead of renewable-generation additions because transmission projects have longer gestation periods.
Know Skipper inside out
Results, valuation, peers and who's buying, in one view.
How large is India’s transmission plan through 2035-36?
India’s transmission build-out is planned to support more than 900 GW of capacity integration by 2035-36, according to Skipper’s presentation citing the Central Electricity Authority. The stated scope comprises 1,37,500 circuit km of transmission lines, 8,27,600 megavolt-amperes, or MVA, of substation capacity and an estimated Rs 7.9 lakh crore investment opportunity.
The more-than-900-GW network measure differs from the projected non-fossil generation base of about 786 GW by 2035-36, compared with about 275 GW currently. Solar and wind are projected to account for about 664 GW, while peak electricity demand is expected to reach about 459 GW. Skipper therefore presents the network plan as accommodating generation, related grid needs and capacity flows beyond the stated non-fossil total.
What change in power capacity is driving transmission demand?
Renewable capacity is projected to account for most of India’s power-capacity increase through FY32, rising to 596 GW from 191 GW in FY24. Over that period, total capacity is projected to rise to 900 GW from 442 GW, while thermal capacity increases to 284 GW from 243 GW and nuclear capacity to 20 GW from 8 GW.
Renewables would rise to about 66% of the FY32E total from about 43% in FY24, based on Skipper’s figures. Skipper identifies Rajasthan, with about 260 GW of renewable-energy potential, and Gujarat, with about 136 GW, as major hubs, alongside southern states, Ladakh solar and storage projects, and offshore wind in Gujarat and Tamil Nadu.
How much will India’s high-voltage network expand by FY32?
India’s transmission network is projected to increase 33% to 6.48 lakh circuit km in FY32 from 4.85 lakh circuit km in 2024. Transformation capacity is projected to increase 87% to 2,342 gigavolt-amperes, or GVA, from 1,251 GVA, showing that the plan covers substations as well as line length.
The mix of additions shifts towards higher-voltage systems. The 765 kilovolt, or kV, network is projected to increase to 1.15 lakh circuit km in FY32E from 0.55 lakh circuit km in FY24, while 500 kV high-voltage direct-current, or HVDC, lines rise to 0.35 lakh circuit km from 0.10 lakh circuit km. By comparison, 220 kV lines increase to 2.49 lakh circuit km from 2.07 lakh circuit km.
The Government of India’s combined National Electricity Plan and state programme is expected to add 1.15 lakh circuit km during FY22-27 and 0.77 lakh circuit km during FY27-32. Skipper also cites 33 GW of HVDC bipole links in planning and an increase in interregional transmission capacity to 168 GW by 2032 from 119 GW.
Got a follow-up? Ask IRIS
Why is transmission being planned before renewable generation?
Transmission is being planned ahead of renewable generation because grid projects have longer gestation periods, according to Skipper. The presentation links that sequence to an annual renewable-addition target of 40-45 GW, requiring transmission assets to be tendered and completed before new generation can be evacuated.
Skipper cites more than 500 GW-equivalent of transmission as commissioned or under implementation, with a further approximately 334 GW in planning. The figures distinguish projects already operating or being built from planned work, while Green Energy Corridor phases II and III, Renewable Energy Zones, offshore wind and hybrid projects are listed as continuing sources of transmission demand.
The presentation also cites remote renewable-resource locations, intermittent output and rising power flows as operating reasons for new lines. It says upgraded networks can support bidirectional flows for rooftop solar and other local sources, but does not quantify the effect on losses, reliability or utilisation.
What does the programme mean for transmission suppliers?
The programme increases the relevance of technically complex equipment and execution capabilities, according to Skipper. It identifies HVDC systems, 1,150 kV ultra-high-voltage corridors, battery energy storage systems and pumped-storage plants as factors raising engineering requirements within the planned grid expansion.
Skipper says its positioning includes tower manufacturing scale, cost leadership and engineering, procurement and construction capability for renewable-energy evacuation and national transmission projects. The company also disclosed the commissioning of two independent transmission-tower test beds at one location in its October 2026 presentation, allowing simultaneous full-scale testing of lattice towers and monopoles.
The presentation separately cites Rs 9.2 lakh crore of National Electricity Plan capital expenditure for high-voltage networks above 220 kV during FY22-32. It shows Power Grid Corporation of India capital expenditure at Rs 11,200 crore in FY24 and Rs 25,000 crore in FY26E, with Rs 2.075 lakh crore disclosed for FY25-32E.
Conclusion
Skipper’s presentation describes a transmission programme whose scale is tied to a more renewable-heavy power system and a planned network capable of integrating more than 900 GW by 2035-36. The Rs 7.9 lakh crore opportunity, 1,37,500 circuit km target and projected rise in renewable capacity from 191 GW in FY24 to 596 GW in FY32E place grid construction alongside generation growth.
The next milestones are the 40-45 GW annual renewable-addition target, movement of the approximately 334-GW planning pipeline into implementation, and progress on 33 GW of planned HVDC bipole links. FY32 targets of 6.48 lakh circuit km of network and 2,342 GVA of transformation capacity provide the disclosed measures for tracking execution.