South West Pinnacle Exploration Limited Keeps FY27 15%-20% Target
Key highlights
- South West Pinnacle's order book reached approximately Rs 757 crore on September 30, 2026.
- H1 FY27 operating revenue rose 16.3% year on year to approximately Rs 119 crore.
- Q2 FY27 EBITDA margin was 14.38%, compared with 19.43% for H1 FY27.
- Management plans to add four to five rigs during Q3 and Q4 FY27.
powered by IRIS

South West Pinnacle Exploration Limited retained its financial year 2027 (FY27) target of 15%-20% top-line growth after second-quarter (Q2 FY27) disruption, supported by a record Rs 757 crore order book at September 30, 2026. South West Pinnacle reported Q2 operating revenue of about Rs 58 crore and expects incoming rigs to raise second-half execution.
Know South West Pinnacle Exploration inside out
Results, valuation, peers and who's buying, in one view.
Why does South West Pinnacle retain its FY27 target?
South West Pinnacle retains its 15%-20% FY27 top-line growth target because management expects its Rs 757 crore order book and additional equipment to support stronger second-half execution. In the first half of FY27 (H1 FY27), consolidated operating revenue rose 16.3% year on year to about Rs 119 crore. Earnings before interest, tax, depreciation and amortisation (EBITDA) increased 14.3% to about Rs 23 crore, while profit after tax (PAT) increased about 23% to Rs 13 crore.
The H1 outcome included a slower Q2, when operating revenue was about Rs 58 crore, EBITDA was about Rs 8 crore and PAT was about Rs 4 crore. Q2 EBITDA margin was 14.38%, compared with 19.43% for H1 FY27, reflecting the disruption and cost pressures that management identified during the quarter.
What disrupted South West Pinnacle's Q2 FY27 execution?
South West Pinnacle said unusually heavy monsoon conditions at certain sites and scheduled maintenance of rigs and major equipment reduced availability, utilisation and project execution in Q2 FY27. Higher diesel prices and other input costs also pressured profitability during the Rs 58 crore revenue quarter. Management described these factors as near-term operational issues rather than a change in the underlying business opportunity.
The company executed 20 projects across eight Indian states during H1 FY27 and reported zero lost-time injuries, but management said the monsoon period from around mid-June to before Diwali is typically more subdued. It also said a Central Ground Water Board contract that supported rainy-season activity in the prior year had ended. Some contracts include fuel-escalation provisions and others do not, so diesel-price movements are not passed through uniformly across the Rs 757 crore backlog.
How will additional rigs support South West Pinnacle in H2 FY27?
South West Pinnacle expects rigs and associated equipment arriving in Q3 FY27 to increase capacity, help mobilise pending work and improve utilisation in the second half. Management said funding arrangements for the capital expenditure programme had been completed, and stated that its H2 FY27 priorities were faster execution, better equipment utilisation and improved operating efficiency as monsoon effects eased.
Management planned FY27 capital expenditure of Rs 50 crore to Rs 60 crore, with almost Rs 10 crore of assets already deployed and working at sites. It said another roughly Rs 50 crore of equipment would arrive in Q3 and be deployed at the end of Q3 or the beginning of Q4. The company plans to add four to five rigs during Q3 and Q4, against an order book comprising about 77% private-sector work and 23% government-sector work.
Got a follow-up? Ask IRIS
How long could South West Pinnacle's order book take to execute?
South West Pinnacle's Rs 757 crore order book has varying execution periods, so it will not convert into revenue over one common timetable. Management cited contracts lasting six months, one year and four years. It said the Hindustan Zinc contract has a four-year term, while work for Reliance was in its third phase and could receive further client extensions.
The September 30, 2026 backlog was the company's all-time high, but its conversion depends on mobilisation, equipment deployment and individual contract schedules. Management said it expects the order book to increase further over the next two to three months, although it did not provide a period-by-period revenue split for the existing Rs 757 crore balance.
What longer-term projects could affect South West Pinnacle?
South West Pinnacle is targeting coal production from its Jharkhand block in FY28-29, subject to approvals and mine development. Exploration has been completed at the 2.66-square-kilometre block, and the geological report has been submitted, vetted and approved by the Ministry of Coal. Management said the mining plan was at an advanced stage and was expected to be submitted shortly.
The chief financial officer said the coal block's initial investment is about Rs 200 crore, including around Rs 75 crore of non-fund-based limits for performance bank guarantees. Management expects Rs 100 crore to Rs 125 crore to be funded through internal accruals, offtake agreements and bank loans, followed by a second phase of about Rs 150 crore to Rs 180 crore funded through internal accruals. In Oman, Alara Resources LLC, a joint venture, reported PAT of Omani rial 352,000, equivalent to about Rs 8.67 crore, for the year ended June 30, 2026, up 603% year on year.
What should South West Pinnacle report next?
South West Pinnacle should next report whether the Q3 FY27 equipment shipments were received and deployed by the end of Q3 or the beginning of Q4. That timing is central to management's plan for higher H2 utilisation after Q2 EBITDA margin fell to 14.38%. The company also said it expects monsoon-related disruption to be largely behind it, subject to normal project conditions.
For the Jharkhand project, the next disclosed step is mining-plan submission, followed by environmental, forest and state-level clearances before the FY28-29 production target can be assessed further. In Oman, the second joint venture had identified 12 prospective copper-gold targets over an airborne geophysical survey exceeding 1,400 square kilometres. Management expected surface geophysics to be completed around February-March FY27 before selecting drilling targets.
Conclusion
South West Pinnacle's FY27 outlook relies on a Rs 757 crore record order book, H1 revenue growth of 16.3% to about Rs 119 crore and a plan to add four to five rigs during Q3 and Q4. The contrast between Q2's Rs 58 crore revenue and 14.38% EBITDA margin and H1's 19.43% margin shows the material effect of weather, maintenance and fuel costs on quarterly execution.
The next test is whether Q3 equipment deliveries are deployed on schedule and enable the H2 execution needed for management's 15%-20% FY27 growth target. Beyond FY27, the mining-plan submission and subsequent clearances for the 2.66-square-kilometre Jharkhand coal block, plus Oman surface geophysics expected around February-March FY27, are the stated milestones to watch.