South West Pinnacle Exploration Limited targets FY 2028-29 coal output
Key highlights
- South West Pinnacle’s Jharkhand coal block covers 2.66 square kilometres and has estimated geological reserves of 84 million tonnes.
- South West Pinnacle targets commencement of coal production by FY 2028-29, with its mining plan under preparation.
- South West Pinnacle’s order book was Rs 767.1 crore as of 30 September 2026, up from Rs 581.2 crore in FY26.
- South West Pinnacle reported FY26 operating revenue of Rs 243 crore and an EBITDA margin of 23.99%.
powered by IRIS

South West Pinnacle targets commencement of coal production by FY 2028-29 from its Jharkhand block with 84 million tonnes of estimated geological reserves, after completing exploration and securing approval of its geological report (GR). The mining plan is under preparation, making it the immediate disclosed development milestone.
Know South West Pinnacle Exploration inside out
Results, valuation, peers and who's buying, in one view.
What is South West Pinnacle’s Jharkhand coal block?
South West Pinnacle’s Jharkhand asset is a commercial coal-mining block covering 2.66 square kilometres with estimated geological reserves of 84 million tonnes. The presentation places the award of this block in the company’s 2020-2023 journey, marking an expansion from its established work as an exploration and drilling service provider into a block awarded for commercial mining.
The company’s operating base includes coal and mineral exploration, coal bed methane (CBM) services, aquifer mapping, seismic work and underground drilling. It reports more than 3.3 million metres of cumulative drilling by H1-FY27, compared with 2,800 kilometres at the end of 2025. Its coal-block plan therefore uses capabilities already deployed in exploration, but commercial coal extraction is a separate development phase from drilling and geological assessment.
What approvals and work has South West Pinnacle completed?
South West Pinnacle says exploration at the coal block has been completed and its GR has been prepared and approved. The company was also notified as an accredited prospecting agency by the Ministry of Coal, Government of India, during the year for undertaking coal and lignite prospecting operations. The presentation links that accreditation with the completion of exploration work at its coal blocks.
The next disclosed activity is preparation of the mining plan, alongside other related development work. South West Pinnacle says these activities are progressing, but the presentation does not provide the mining-plan submission date, approval date, production capacity, capital expenditure, mine life or a sequence of further permits. The FY 2028-29 production date is consequently a company target contingent on the development work described being completed.
When does South West Pinnacle expect coal production to start?
South West Pinnacle targets starting coal production by FY 2028-29. This is a forward-looking timeline stated in the coal-block acquisition section, rather than reported production, because the mining plan is still being prepared and the presentation gives no tonnes mined, coal sales or coal revenue from the Jharkhand block to date.
The planned start sits after a multiyear progression already recorded by the company. The block was awarded in the 2020-2023 period, while the 2025-26 onwards section says exploration work was completed and the GR approved. The remaining transition is from a defined geological resource of 84 million tonnes to an operating mine, with the mining plan identified as the immediate formal workstream.
Got a follow-up? Ask IRIS
How does the coal block change South West Pinnacle’s business mix?
South West Pinnacle’s coal block introduces a potential mining operation alongside a business currently led by contract-based exploration and drilling services. Its H1-FY27 order book was Rs 767.1 crore, of which survey and exploration of mineral accounted for Rs 455.4 crore, CBM production Rs 222.1 crore, aquifer mapping Rs 59.5 crore, seismic and coal drilling Rs 23.8 crore, and geophysical survey Rs 6.4 crore.
The comparison shows that mineral survey and exploration represented the largest disclosed order-book segment, while seismic and coal drilling was a smaller Rs 23.8 crore segment. The 84-million-tonne block is not presented as part of that order book and no valuation or expected earnings contribution is disclosed. It instead represents an asset-development project whose commercial outcome will depend on the mining-plan and development stages.
At H1-FY27, South West Pinnacle listed 20 ongoing projects: 12 in survey and exploration of mineral, six in aquifer mapping, one in CBM production and one in seismic and coal drilling. The active project count describes service contracts, whereas the Jharkhand block is presented separately as a commercial-mining development.
South West Pinnacle’s contract portfolio has expanded before the proposed mine start. Its total order book rose from Rs 215.7 crore in FY24 to Rs 328.7 crore in FY25, Rs 581.2 crore in FY26 and Rs 767.1 crore in H1-FY27. Private customers represented 77% of the H1-FY27 order book, against 23% for government customers, indicating that the existing pipeline remains largely private-sector work while the company progresses its Jharkhand development.
What financial information does South West Pinnacle disclose for the development period?
South West Pinnacle reports a growing services revenue base but does not identify funding dedicated to the coal mine. Operating revenue reached Rs 243 crore in FY26, up Rs 109.6 crore from Rs 133.4 crore in FY24, while earnings before interest, tax, depreciation and amortisation (EBITDA) margin increased to 23.99% from 18.52%. H1-FY27 operating revenue was Rs 119.4 crore and EBITDA margin was 19.43%, a partial-year result that should not be treated as a full-year comparison.
The company also reported debt-to-equity of 0.27 and an order book of Rs 767.1 crore as of 30 September 2026. These figures describe the existing services business, not funding dedicated to the coal mine. South West Pinnacle does not disclose a mine-development budget, funding structure or projected coal realisation in the presentation, so the financial contribution of the block cannot be quantified from the material provided.
Conclusion
South West Pinnacle has moved its Jharkhand coal block beyond exploration, reporting completed field work and an approved GR for 84 million tonnes of estimated geological reserves across 2.66 square kilometres. That creates a defined path toward a commercial mining asset alongside its service operations, whose order book had risen to Rs 767.1 crore in H1-FY27 and whose FY26 operating revenue was Rs 243 crore.
The next item to watch is the mining plan now under preparation and the related development activities required to support management’s FY 2028-29 production target. The presentation does not set out an approved mining-plan date, production capacity, capital requirement or coal-revenue forecast, leaving those disclosures and progress toward the stated start date as the principal unresolved milestones.