Surya Roshni targets 2 million tonnes with greenfield plant
Key highlights
- Surya plans Rs 250 crore to Rs 300 crore of greenfield capital expenditure for 3.5 lakh tonnes of pipe capacity.
- Surya’s pipe capacity is about 14.5 lakh tonnes, with planned investments aimed at 20 lakh tonnes or slightly more.
- Surya targets more than 11 lakh tonnes of pipe volume in FY27 and about 14 lakh tonnes in FY28.
- Surya reported zero debt and a Rs 75 crore cash surplus as of September 30, 2026.
powered by IRIS

In its Q2FY27 call, Surya Roshni said its Rs 250-300 crore greenfield project would add 3.5 lakh tonnes of annual pipe capacity, helping lift total capacity from about 14.5 lakh tonnes to 20 lakh tonnes or slightly more over two years. Management said the project cost includes land and all other elements.
Know Surya Roshni inside out
Results, valuation, peers and who's buying, in one view.
What is Surya's greenfield pipe expansion plan?
Surya has outlined a Rs 250-300 crore greenfield investment that management said would add 3 lakh to 3.5 lakh tonnes of pipe capacity, later specifying 3.5 lakh tonnes. The stated project cost includes land and all other elements, rather than only machinery or mill equipment. Management said the greenfield plan was “almost complete” at the time of the call.
Surya had not selected the final site when it spoke to investors. Management said it was evaluating Vizag and Maharashtra, had identified land in Maharashtra, and expected to decide the precise location within two to three months. The company’s stated condition is that the plant should be near a port to provide access to imported material.
The greenfield project is separate from additions planned at existing locations in FY27. Surya said it planned total capital expenditure of Rs 150 crore to Rs 155 crore for the year, including a mill commissioned at Bhuj, mills coming up at Bahadurgarh and Gwalior, and an adjacent-land expansion at Hindupur expected to be commissioned by March of FY27.
How much pipe capacity will Surya add and when?
Surya’s current pipe capacity is about 14.5 lakh tonnes, and management said the full investment programme would take it to 20 lakh tonnes or slightly above. The 3.5 lakh-tonne greenfield plant is therefore a major part of the route to the 20 lakh-tonne level, alongside FY27 additions and the Rs 75 crore Hindupur Phase 2 investment planned for next year.
Management said greenfield spending would extend over two years, with some activity occurring at the end of next year and more in the subsequent year. It did not disclose a formal commissioning date, a plant-by-plant capacity schedule or an annual utilisation target. The two-to-three-month timeframe applies to selecting the location, not to finishing construction.
The capacity plan sits alongside higher volume targets for the steel pipes and strips business. Surya targets more than 11 lakh tonnes in FY27 after selling 4.96 lakh tonnes in H1FY27, and it targets about 14 lakh tonnes in FY28. Management also set a longer-term volume target of about 20 lakh tonnes by FY2030, broadly matching the planned capacity scale.
The near-term volume outlook follows a record 2.67 lakh tonnes in Q2FY27, up 23% year on year and 17% sequentially. Management expects about 6 lakh tonnes in H2FY27 after delivering about 5 lakh tonnes in H1FY27. That outlook would take annual volume beyond the earlier 11 lakh-tonne target, according to management, but it does not establish the future utilisation of the proposed greenfield unit.
Got a follow-up? Ask IRIS
How will Surya finance its pipe expansion?
Surya reported zero debt and a Rs 75 crore cash surplus as of September 30, 2026, but management did not specify the funding source for the Rs 250-300 crore greenfield project. The call did not state whether the project would be financed from internal cash generation, existing cash balances, borrowings or another source.
Management said Rs 50 crore of FY27 capital expenditure had occurred by October, including the commissioned mill at Bhuj. It put investment in mills at Bahadurgarh and Gwalior at around Rs 55 crore, while the adjacent-land expansion at Hindupur was estimated at Rs 50 crore to Rs 55 crore and was expected to be completed by March of FY27.
The company reported a 63-day net working-capital cycle in Q2FY27, return on capital employed of 15.74%, and return on equity of 11.35%. H1FY27 revenue was Rs 4,495 crore, up 30% from Rs 3,450 crore in H1FY26, while EBITDA, or earnings before interest, tax, depreciation and amortisation, rose 18% to Rs 263 crore from Rs 223 crore.
What product mix and demand will support the added capacity?
Surya said the proposed greenfield capacity would retain its existing product balance, with value-added products accounting for about 48% to 50% of volume and sections and GP pipes making up the remainder. Management said value-added products carry EBITDA above Rs 7,000 per tonne, but it did not disclose a product-level volume split or profitability forecast for the new plant.
Value-added products represented about 48% of total steel-pipe volume in Q2FY27, while hollow-section volume grew 35%. Management said section-pipe demand was growing 18% to 20% across India, linked to construction activity, but put section-pipe EBITDA at Rs 2,500 to Rs 2,600 per tonne amid pricing pressure.
API pipes are another component of the mix. Surya said its domestic API order book had reached about 20,000 tonnes after domestic oil-and-gas tendering revived, while export orders included about 80,000 tonnes of API pipes for execution in Q3 and Q4. Management said API-pipe EBITDA had declined from an earlier average of Rs 10,000 per tonne to about Rs 8,000 because of coating-material costs.
Steel pipes and strips revenue rose 38% year on year to Rs 1,941 crore in Q2FY27, while segment EBITDA was Rs 103 crore. EBITDA per tonne was Rs 4,105, below Rs 5,013 in Q2FY26 but above Rs 4,006 in Q1FY27. Management expects Rs 4,800 to Rs 4,900 per tonne in Q3FY27 and more than Rs 5,000 per tonne in Q4FY27, partly reflecting price increases flowing through fixed-price export and API business.
Conclusion
Surya’s programme combines existing-site additions, a Rs 75 crore Hindupur Phase 2 investment and a Rs 250-300 crore greenfield project to move pipe capacity from about 14.5 lakh tonnes to 20 lakh tonnes or slightly more. Management intends to preserve a 48% to 50% share of value-added products rather than shift the mix toward sections and GP pipes.
The next disclosed milestones are a greenfield site decision between Vizag and Maharashtra within two to three months, Hindupur commissioning by March of FY27, and the start of greenfield activity at the end of next year. Management’s H2FY27 targets of about 6 lakh tonnes of volume and EBITDA of Rs 4,800 to Rs 4,900 per tonne in Q3FY27 are also relevant near-term measures of execution.