Tata Power sets Bhivpuri 2029, Shirwata 2031 commissioning
Key highlights
- Tata Power expects Bhivpuri to become operational in the first half of calendar year 2029.
- Tata Power expects the 1,800 MW Shirwata pumped-storage project to be commissioned in calendar year 2031.
- Shirwata has a disclosed gross capital cost of Rs 11,871 crore before probable incentives and grants.
- Tata Power reported renewable curtailment of about 11% in the second quarter, compared with about 8.8% in the first quarter.
powered by IRIS

Tata Power expects its Bhivpuri pumped-storage project to become operational in the first half of calendar year 2029 and its 1,800 MW Shirwata project to be commissioned in calendar year 2031. Management said Shirwata has been approved at a gross capital cost of Rs 11,871 crore, before probable incentives and grants.
Know Tata Power Company inside out
Results, valuation, peers and who's buying, in one view.
When will Tata Power commission Bhivpuri and Shirwata?
Tata Power expects Bhivpuri to become operational in the first half of calendar year 2029 and Shirwata to be commissioned in calendar year 2031. Managing Director and Chief Executive Officer Praveer Sinha gave the two milestones in response to an analyst asking when the projects could begin producing cash flows.
The timetable places Bhivpuri ahead of Shirwata by roughly two years based on the disclosed calendar-year targets. Tata Power did not provide a specific month for Bhivpuri, a quarter for Shirwata, or annual cash-flow estimates for either project during the call.
Tata Power also said work is under way on its first 1,000 MW pumped-storage project. The transcript does not explicitly identify that 1,000 MW project as Bhivpuri in the same exchange, so the call does not establish Bhivpuri's capacity.
Shirwata is the later and specifically identified 1,800 MW project approved by the board. Tata Power said it may return with further pumped-storage proposals at other reservoirs, but gave no additional capacity, cost or commissioning date beyond the 1,000 MW work under way and the 1,800 MW approval.
What is Tata Power spending on Shirwata?
Tata Power has disclosed a gross capital cost of Rs 11,871 crore for the 1,800 MW Shirwata project. Chief Financial Officer Sanjeev Churiwala said this was the figure in the company's press release and Securities and Exchange Board of India filing.
Management rejected the analyst's premise that the project cost had increased from an earlier estimate of Rs 8,000 crore or Rs 7,850 crore. Churiwala said there was confusion around those numbers and that Shirwata had always been in this broad cost range, meaning the call does not confirm a cost increase from a prior company estimate.
Tata Power said it normally announces capital expenditure on a gross basis, without deducting probable incentives or grants. Churiwala contrasted this approach with companies that may state project costs after incentives and grants, so the Rs 11,871 crore amount is not a net-of-support cost estimate.
The company did not disclose the likely value of incentives or grants, a funding structure, debt requirement or equity contribution for the Rs 11,871 crore project. It also did not provide an equivalent cost figure for Bhivpuri, preventing a like-for-like cost comparison between the two projects.
Got a follow-up? Ask IRIS
Why does Shirwata use one existing reservoir?
Tata Power said Shirwata is being assessed as a one-reservoir pumped-storage project because one reservoir already exists and the company plans to create one additional settling reservoir. Sinha said the number of reservoirs that must be built changes both a project's cost and its timeline.
Projects that require construction of both reservoirs have different costs and schedules from a project using an existing reservoir, according to management. The analyst sought a greenfield pumped-storage cost benchmark, but Tata Power did not disclose a per-megawatt cost, total cost or standard timeline for a two-reservoir project.
Management said it considers pumped storage over an operating period not limited to 40 years, but potentially longer. This long operating-life view was part of Sinha's explanation for pursuing pumped storage alongside the physical design of the 1,800 MW Shirwata project.
Tata Power did not disclose Shirwata's storage duration, expected electricity generation, construction start date or offtake arrangement. Therefore, the call establishes the 2031 commissioning goal and Rs 11,871 crore gross cost, but not the commercial terms that would underpin project cash flows.
How does pumped storage fit Tata Power's storage plans?
Tata Power said it is going “big time” into pumped storage, with work under way on a first 1,000 MW project and board approval for the additional 1,800 MW Shirwata project. The company described pumped storage as a long-term storage solution and said it could bring more proposals involving other reservoirs.
That potential expansion is a management plan rather than a disclosed target. Tata Power provided no capacity total, investment total or approval schedule for projects beyond the first 1,000 MW work and the 1,800 MW Shirwata project scheduled for calendar year 2031.
Storage was also discussed in connection with renewable-energy curtailment. Tata Power reported curtailment of about 8.8% in the first quarter and about 11% in the second quarter, an increase of about 2.2 percentage points between the two periods.
Management said it was working on connectivity and expected improvement in subsequent quarters. It also said battery energy storage system, or BESS, installations coming through would help reduce curtailment, but did not disclose BESS capacity, commissioning dates or the portion of the 11% second-quarter curtailment that storage could address.
Pumped storage and BESS were discussed as separate technologies in the call. The first-half 2029 Bhivpuri and calendar-year 2031 Shirwata timelines apply to pumped storage, while the BESS comments were made in the context of reducing renewable curtailment that reached about 11% in the second quarter.
Conclusion
Tata Power has set out a phased pumped-storage schedule, with Bhivpuri expected to operate in the first half of calendar year 2029 and the larger 1,800 MW Shirwata project targeted for commissioning in calendar year 2031. Shirwata's Rs 11,871 crore figure is a gross capital-cost disclosure, and management links the project assessment to its use of one existing reservoir and a potential operating life beyond 40 years.
The next disclosed milestones are execution toward Bhivpuri's first-half 2029 operating target and Shirwata's 2031 commissioning target. Investors can also watch for any further reservoir proposals, while funding, potential incentives or grants, storage duration and commercial arrangements for the Rs 11,871 crore Shirwata project remain undisclosed in the call.