Tata Power reports Rs 1,652 crore profit, Rs 25,000 crore plan
Key highlights
- Tata Power reported record Q2 FY27 PAT of Rs 1,652 crore, up 33% year on year from Rs 1,245 crore.
- Tata Power’s Q2 FY27 revenue rose nearly 26% to Rs 19,886 crore from Rs 15,769 crore.
- Tata Power had completed Rs 10,000 crore of capex and targets nearly Rs 25,000 crore for FY27.
- Tata Power approved a Rs 11,871 crore, 1,800 MW pumped-hydro project at Shirwata near Lonavala.
powered by IRIS

The Tata Power Company Limited reported record profit after tax of Rs 1,652 crore in Q2 FY27, up 33% year on year, and said it was on track for nearly Rs 25,000 crore of capital expenditure in FY27 after completing Rs 10,000 crore by its November 11, 2026 earnings call.
Know Tata Power Company inside out
Results, valuation, peers and who's buying, in one view.
How did Tata Power’s Q2 FY27 earnings change?
Tata Power’s Q2 FY27 profit after tax, or PAT, rose to Rs 1,652 crore from Rs 1,245 crore in the corresponding quarter a year earlier, making it the company’s highest-ever quarterly profit. Management attributed the 33% increase to performance across its businesses, while earnings before interest, tax, depreciation and amortisation, or EBITDA, increased 5% year on year.
Revenue reached Rs 19,886 crore in Q2 FY27, compared with Rs 15,769 crore a year earlier. Management said power demand grew nearly 10% to 11% in the quarter, citing weak monsoon conditions, higher agricultural consumption and increased cooling demand during heatwave and humid conditions.
For the half year ended September 30, 2026, Tata Power reported PAT of Rs 3,053 crore, up 22% year on year. Half-year EBITDA rose 7% to Rs 8,494 crore from Rs 7,961 crore, while revenue increased to Rs 38,784 crore from Rs 33,233 crore, showing growth in profit, operating earnings and revenue across both reported periods.
What is Tata Power’s FY27 capital-expenditure plan?
Tata Power said it had completed Rs 10,000 crore of capital expenditure, or capex, by the November 11 call and remained on track to complete nearly Rs 25,000 crore in FY27. Management said the programme would add capacity in renewables, transmission, distribution and other projects under implementation.
Management did not provide a numerical allocation of the nearly Rs 25,000 crore FY27 capex plan by business. Its presentation separates rooftop solar, utility-scale renewables and manufacturing within renewables, while distribution reporting distinguishes Odisha distribution companies from Delhi and Mumbai distribution companies.
Tata Power expects the second half, or H2, of FY27 to be better than H1 because projects and actions delayed by monsoon conditions or other factors can be completed later in the year. Management also expects benefits from projects under implementation to start accruing in H2, which is an expectation rather than a reported financial outcome at September 30, 2026.
Why is Tata Power adding the 1,800 MW Shirwata project?
Tata Power has approved a 1,800-megawatt, or MW, pumped-hydro project at Shirwata near Lonavala with an investment of Rs 11,871 crore. Management said the project would be funded with 75% debt and 25% equity, a financing mix disclosed for Shirwata rather than for the full FY27 capex programme.
The company intends to use the project to bid for pumped-storage capacity arrangements sought by state distribution companies. Tata Power also plans to combine storage with renewable projects for renewable-energy round-the-clock, or RE RTC, supply to distribution companies, industrial customers and data centres with which it said it was in discussions.
Management linked the storage decision to rising system demand, reporting nearly 12% year-on-year power-demand growth in October after growth of nearly 10% to 11% in the preceding quarter. It also said insufficient rainfall could constrain hydro generation in the following year, without quantifying any effect on Tata Power’s own hydro output.
Got a follow-up? Ask IRIS
What could affect Tata Power’s H2 FY27 performance?
Tata Power’s H2 FY27 performance will depend partly on project execution after the Rs 10,000 crore of capex completed by the November 11 call. Management said some projects were ready but had been delayed by evacuation-line availability, and it expected certain lines by December or January.
In renewables, Tata Power maintained its FY27 target of adding 2.5 gigawatts, or GW, of capacity after missing capacity-addition targets in the first and second quarters. Management said transmission evacuation delays had held back progress, but expected the annual addition target to be met as lines become available.
Renewable-generation curtailment rose to about 11% in Q2 from about 8.8% in Q1, according to management. The company expects planned connectivity to ease the constraint in subsequent quarters, although it did not provide a curtailment forecast for the remainder of FY27.
What is the status of Tata Power’s Singapore legal case?
Tata Power said its appeal in the Singapore International Commercial Court had been rejected and that it had approached the Court of Appeal, which management described as the Supreme Court of Singapore. The matter was listed for January 19, and management said it believed it had a case on merits and law.
Management said Kleros was seeking to enforce the order by attaching shares in two Singapore companies. Tata Power said it was taking legal action to prevent attachment, while noting that the shares were pledged with a consortium of lenders that would need to be approached and would also take suitable legal action.
The call did not disclose a financial provision, potential liability or a resolution timetable beyond the January 19 listing. That leaves the legal process separate from the Q2 FY27 PAT of Rs 1,652 crore and the nearly Rs 25,000 crore capex programme disclosed by management.
Conclusion
Tata Power combined record Q2 FY27 PAT of Rs 1,652 crore with a plan to complete nearly Rs 25,000 crore of capex during FY27. The figures show profit rose 33% year on year in the quarter and 22% in the first half, while the investment programme spans renewables, transmission, distribution and pumped storage.
The next disclosed milestones are execution of the remaining FY27 capex, the targeted 2.5 GW of renewable capacity additions and the availability of delayed evacuation lines expected by December or January. Investors will also watch progress on the Rs 11,871 crore Shirwata project and the Singapore appeal listed for January 19.