Vikram Solar targets March 2027 COD for 9 GW cell plant
Key highlights
- Vikram Solar expects first-cell output from its 9 GW facility in December 2026 and COD in March 2027.
- Management said captive cells could almost double current DCR-module margins based on procured cells.
- Vikram Solar estimated its 9 GW cell project cost at about Rs 4,500 crore.
- Q2 FY27 EBITDA per watt peak rose 37% sequentially to Rs 1.71, while distribution volume rose about 80% to 259 MW.
powered by IRIS

Vikram Solar Limited expects its 9 GW TOPCon Plus cell facility to reach commercial operation date, or COD, in March 2027 after first-cell output in December, and management said captive domestic-content-requirement cells could almost double margins compared with DCR modules using procured cells.
Know Vikram Solar inside out
Results, valuation, peers and who's buying, in one view.
When will Vikram Solar commission its 9 GW cell plant?
Vikram Solar expects first cells from its 9 GW TOPCon Plus facility in December, followed by sequential commissioning of lines over three months and project COD in March 2027. Management said on the November 16, 2026 Q2 FY27 earnings call that the project remained on schedule, without providing a separate date for full commercial-volume ramp-up after COD.
The company has added an extra layer of technical supervision and moved senior leadership to the project site to reduce ramp-up risk. The facility is intended to supply Vikram Solar’s own DCR cells for module production, replacing purchased cells in part of its output once commercial production begins.
Vikram Solar described its longer-term integration objective as spanning ingot to module. Its board-approved next step is a 9 GW wafer-and-ingot project at the same site, where the Bhoomi Puja was completed in August; management said commissioning will occur in phases based on policy mandates and demand.
How could captive cells change Vikram Solar’s margins?
Vikram Solar said margins could almost double from current DCR-module margins earned using procured cells once its captive cells are available. The chief financial officer made this point in response to an analyst question but declined to quantify the benefit in rupees per watt or as an EBITDA margin target.
Management expects the margin change to come from both lower reliance on purchased DCR cells and a higher-value product mix. It said TOPCon Plus cells used in Vikram Solar modules could create an efficiency offering that few manufacturers can match at scale, with the stated aim of gaining share in segments that value that efficiency.
The company said a significant share of FY28 volume could shift to the higher-margin DCR segment after the 9 GW facility is commissioned. This is a forward-looking management expectation, rather than a reported result, and will depend on the plant’s commissioning and production ramp.
Current unit economics improved before captive-cell production began. In Q2 FY27, EBITDA per watt peak rose 37% sequentially to Rs 1.71 from Rs 1.25 in Q1 FY27, while EBITDA margin was 9.4% on Rs 1,077 crore of revenue from operations. Management attributed the improvement to distribution mix, DCR growth, high-efficiency products and cost optimisation.
What changed in Vikram Solar’s Q2 FY27 profitability?
Vikram Solar’s improved per-watt economics did not offset lower volume, as EBITDA fell to Rs 101 crore in Q2 FY27 from Rs 126 crore in Q1 FY27. Volume declined about 40% sequentially to 591 megawatts, or MW, as independent power producer customers deferred offtake amid land and power-evacuation constraints, with monsoon conditions also affecting installations.
Distribution was the principal mix change during the quarter. Distribution volume rose about 80% to 259 MW from 145 MW in Q1 FY27, while its share of total volume reached 44%. DCR volume within distribution grew 71% sequentially, supporting higher realisations, according to management.
For H1 FY27, revenue rose 18% year on year to Rs 2,641 crore while volume increased 3% to 1,596 MW. Management said the gap reflected average realisation per watt rising about 15% from H1 FY26 because of a richer channel mix and higher DCR share; however, H1 EBITDA fell to Rs 227 crore from Rs 477 crore in H1 FY26 amid industry price competition.
Got a follow-up? Ask IRIS
How is Vikram Solar funding the cell project?
Vikram Solar estimated the cost of its 9 GW cell project at about Rs 4,500 crore, or within about Rs 500 crore per GW. Management also said the larger Gangaikondan project, comprising 6 GW of modules and 9 GW of cells, has a cost of Rs 5,800 crore and is funded roughly one-third by equity and two-thirds by debt.
By the end of Q2 FY27, Vikram Solar had spent about Rs 1,700 crore on the Gangaikondan project, mainly to complete the module plant and advance the cell facility. It planned another Rs 3,800 crore of infusion in H2 FY27, mostly for the cell project, while gross debt stood at Rs 632 crore and net debt at Rs 547 crore.
The company reported net debt to equity of 0.17 at the end of Q2 FY27. Management said wafer-and-ingot and battery energy storage system spending would be paced so that capital and management attention remain focused primarily on the cell project during FY27.
The 9 GW wafer-and-ingot project has a current estimated cost of about Rs 5,600 crore, or about Rs 620 crore per GW. Management said serious investment in that project would begin in the next fiscal year to align with timelines stipulated for ALMM List-III, while it retains provision at the site for a further 3 GW across cell, wafer and ingot capacity.
How much demand can Vikram Solar convert before the cell ramp?
Vikram Solar closed Q2 FY27 with an 8.2 GW order book after removing 1 GW of US export orders that it said were no longer viable. Management expects 60% to 70% of the remaining order book to be executed over the next 12 to 18 months, although it described the book as primarily non-DCR.
The removed export orders were affected by the US Section 232 circular of August 6, which management said introduced a minimum import price and an additional 15% ad valorem duty, with an enforcement deadline of December 4. The 8.2 GW closing book therefore reflects the removal of those orders rather than an increase in export demand.
New orders in Q2 FY27 totalled 1.7 GW, more than double the preceding quarter. Key accounts contributed 1.3 GW and the mid-market segment added 400 MW, while the 10 largest orders represented 1.1 GW of the new order flow.
Management said IPP offtake was normalising after Q2 delays and called an approximately 1 GW quarterly-volume estimate fair in response to an analyst. It expects H2 FY27 volumes to be substantially higher than H1 as the order book converts, while expecting EBITDA per watt peak to hold around current levels.
Conclusion
Vikram Solar’s cell project is central to its planned shift from mix-led margin improvement to backward integration. Q2 FY27 demonstrated the near-term effect of distribution and DCR mix, with EBITDA per watt peak rising to Rs 1.71 even as lower 591 MW volume reduced quarterly EBITDA to Rs 101 crore; captive cells are management’s proposed next structural lever.
The next disclosed milestones are first-cell output in December and COD in March 2027, followed by the execution of 60% to 70% of the 8.2 GW order book over 12 to 18 months. Management’s H2 FY27 outlook also depends on deferred IPP and commercial-and-industrial offtake normalising, while wafer-and-ingot investment is planned to be phased around policy mandates and demand.