ACME Solar Holdings Limited raises FY27 BESS goal above 12 GWh
Key highlights
- ACME Solar Holdings Limited commissioned about 5.2 GWh of BESS by H1 FY27 and raised its FY27 goal to more than 12 GWh.
- ACME Solar doubled its 2030 BESS target from 25 GWh to 50 GWh and raised its renewable target to 15 GW.
- Q2 FY27 revenue was Rs 10.07 arab, up 67.5% year on year, while EBITDA was Rs 8.74 arab, up 63.6%.
- ACME Solar had contracted about 19 GWh of BESS equipment and disclosed more than Rs 16 hundred crore of partial FY27 BESS revenue.
powered by IRIS

ACME Solar Holdings Limited raised its FY27 battery energy storage system, or BESS, commissioning guidance from 10 gigawatt-hours (GWh) to more than 12 GWh after commissioning about 5.2 GWh by H1 FY27. The company also doubled its 2030 BESS ambition from 25 GWh to 50 GWh while lifting its renewable-capacity target to 15 gigawatts (GW).
Know ACME Solar Holdings inside out
Results, valuation, peers and who's buying, in one view.
Why did ACME Solar raise its FY27 BESS commissioning target?
ACME Solar raised the FY27 target because it had commissioned about 5.2 GWh of BESS by H1 FY27, exceeding the 5 GWh annual target cited on its previous earnings call. Management said early deployment and execution momentum supported guidance of more than 12 GWh, compared with the earlier 10 GWh objective.
The faster rollout coincided with Q2 FY27 revenue of Rs 10.07 arab, up 67.5% year on year, and earnings before interest, tax, depreciation and amortisation (EBITDA) of Rs 8.74 arab, up 63.6%. Management attributed the increases primarily to short-term peak-power BESS operations and renewable-capacity additions, while profit after tax rose 133.5% to Rs 2.69 arab.
BESS operations generated a 78.3% EBITDA margin in Q2 FY27, below the 90.8% reported for renewable generation, producing a blended margin of 86.7%. Management said BESS operating expenses include the cost of power purchased to charge batteries, a distinction from the renewable-generation segment.
What is ACME Solar's 2030 storage roadmap?
ACME Solar now targets 15 GW of renewable capacity and 50 GWh of BESS by 2030, replacing its previous objective of 10 GW with 25 GWh of storage. The new plan adds 5 GW of renewable capacity and 25 GWh of batteries, doubling the storage component of the earlier roadmap.
Management cited more than 20 GW of upcoming tenders across solar-plus-BESS, firm and dispatchable renewable energy (FDRE), contracts for difference and pumped hydro storage projects. It also cited 50 GWh of peak-power builds rolled out through September 27, another 200 GWh to 250 GWh of short-term peak-power contracts expected in the near to medium term, and 20 GWh of medium-term peak-only tenders expected shortly.
A specific opportunity cited on the October 29, 2026 call was a Solar Energy Corporation of India auction for 4 GW and 16 GWh of four-hour assured peak power. Management said this auction requires commissioning within 12 months and carries viability-gap funding of Rs 15 lakh per megawatt-hour; it described the tender market, not an award to ACME Solar.
What equipment and connectivity support ACME Solar's plan?
ACME Solar said it had contracted about 19 GWh of BESS equipment from CATL, Hithium, Ganfeng, Trina and CLOU. It also reported more than 5 GW of BESS connectivity already granted and about 10 GW of renewable-energy connectivity inventory secured or applied for beyond its existing portfolio.
The company had partially commissioned 1.9 GW of contracted projects through solar and BESS additions by Q2 FY27. It had delivered 1.7 GW of modules to project sites, installed 1.1 GW, and charged 200 megawatt-peak of that installed capacity; management expected the remaining installed modules to be charged in November and December 2026.
ACME Solar signed 430 megawatts (MW) of FDRE power-purchase agreements (PPAs) during Q2 FY27 and another 400 MW FDRE PPA with NTPC the day before the call. These agreements took signed PPAs to 92% of its 8,370 MW contracted portfolio, and management identified NTPC as the offtaker for the additional 400 MW agreement.
Got a follow-up? Ask IRIS
How is ACME Solar earning from BESS before full grid access?
ACME Solar is commissioning solar and storage elements in stages so BESS can operate before full general network access (GNA) is available. Management said this model enabled the 1.9 GW of partial commissioning already reported and could support 2.5 GW to 3 GW of partial commissioning in FY27, even as complete FDRE and hybrid-plant commissioning remains dependent on GNA timing.
Management said it hoped to fully commission about 1.5 GW in FY27, though that outcome could move by a quarter depending on GNA commissioning. It expects 1.5 GW to 2 GW of generation capacity, measured in megawatt-peak installed, before March from Fatehgarh-II, Neemuch, Bikaner-III and Ananthapur, subject to transmission availability.
At Bikaner-III, management said ACME Solar supplies NTPC when GNA is available and routes remaining solar output to BESS. It also cited a regulatory provision allowing curtailed solar under a PPA to charge BESS for merchant sale where GNA is delayed, which management said could monetise energy that would otherwise be curtailed.
What revenue and capital-spending plans has ACME Solar disclosed?
ACME Solar had locked in more than Rs 16 hundred crore of revenue from partial sales of FY27 BESS capacity and more than Rs 15 hundred crore from partial sales of FY28 capacity. Management said the remaining capacity would be tied up through future bids, so the disclosed figures do not cover all storage capacity in either financial year.
The company sold 324 million units through short-term peak-power BESS contracts in Q2 FY27, alongside total power generation of 1,840 million units. Its capacity utilisation factor improved to 27.8% from 24.1% a year earlier, while the Q2 FY27 profit-after-tax margin was 26.7%.
Management gave differing descriptions of FY27 spending to date during the call, first referring to about Rs 1 kharab of capital expenditure and later describing about Rs 60 hundred crore of spending. It said Rs 35 hundred crore had been capitalised and Rs 30 hundred crore was capital work in progress, before referring to Rs 65 hundred crore completed; these statements cannot be reconciled from the transcript. Management's stated plan was to capitalise the full 12 GWh of BESS during FY27.
Conclusion
ACME Solar's revised targets place BESS at the centre of its stated growth strategy rather than treating storage as an addition to solar capacity. Its 5.2 GWh commissioned by H1 FY27, 19 GWh of contracted equipment and more than Rs 16 hundred crore of disclosed partial FY27 BESS revenue provide the operating and procurement context for the 50 GWh 2030 ambition.
The next markers are management's plan to capitalise 12 GWh of BESS in FY27, the expected November-to-December 2026 charging of installed solar modules, and GNA commissioning at Fatehgarh-II, Neemuch and Bikaner-III. Management's expectation of about 1.5 GW of full FY27 commissioning remains conditional on those transmission timelines.