Ansal Properties CIRP split into two state resolution processes
Key highlights
- Ansal Properties’ CIRP has been separated into 2 state-level processes for Uttar Pradesh and Rajasthan.
- The restricted CIRP commencement date remains 25 February 2025.
- The Uttar Pradesh resolution professional must receive relevant records within 4 weeks of the order.
- A common supervisor must file a consolidated NCLT progress report every 90 days and will receive Rs 2 lakh a month.
powered by IRIS

Ansal Properties’ restricted corporate insolvency resolution process (CIRP) will run as two state-level processes after the National Company Law Tribunal (NCLT) ordered separate Uttar Pradesh and Rajasthan tracks, separate resolution professionals and separate committees of creditors for the two geographical regions.
Know Ansal Properties & Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
What did the NCLT decide for Ansal Properties’ CIRP?
The NCLT decided that Ansal Properties’ Uttar Pradesh projects and Rajasthan assets must be handled through 2 separate resolution processes. The ruling concerns the operating structure of the CIRP after the National Company Law Appellate Tribunal (NCLAT) had upheld Ansal Properties’ admission to insolvency and confined the process to specified assets rather than the company as a whole.
The tribunal said the issue was not whether the CIRP should continue, because the NCLAT had upheld the admission order and the Supreme Court had declined to interfere. Instead, it considered how to implement the restricted CIRP, whose commencement date remains 25 February 2025. The NCLAT’s judgment of 7 January 2026 and its clarification of 25 May 2026 defined the projects and assets within scope.
The order does not establish a separate CIRP for every project. Homebuyers had sought separate project-level CIRPs and committees of creditors (CoCs) in I.A. 5159/ND/2026, but the NCLT chose a state-wise arrangement with 2 CoCs. It said a project-by-project approach could create multiple processes and difficulties involving common assets, liabilities, infrastructure and inter-project transactions.
Which Ansal Properties assets fall into each resolution process?
The Uttar Pradesh process covers Ansal Properties’ Mother City, Mother City Extension and projects in Sushant Golf City, Lucknow, together with the assets and liabilities attributable to those projects. The Rajasthan process covers specified Rajasthan assets, including built-up properties in Ajmer, Jodhpur and Jaipur listed at serial numbers 5, 6 and 7 of Schedule-B to the settlement agreement dated 3 March 2022.
Neither of the 2 processes can extend to any other Ansal Properties project, asset or undertaking beyond the NCLAT-defined scope. This restriction matters because the appellate ruling put named Uttar Pradesh developments and specified Rajasthan assets into CIRP, rather than bringing Ansal Properties’ entire business or portfolio into the process.
The regional split separates the administration of claims, liabilities and project funds. The Uttar Pradesh asset pool contains the 3 named project groupings in and around Lucknow, while the Rajasthan pool contains assets in 3 cities. Each resolution professional must identify, verify and manage the assets and liabilities within the relevant geographical scope under the Insolvency and Bankruptcy Code and applicable regulations.
Why did the NCLT use two state processes instead of one CIRP?
The NCLT found that one CIRP administered by a common resolution professional could create practical difficulties in identifying and segregating project-specific assets and liabilities across 2 geographical regions. It also cited the need to determine region-specific claims, manage project funds, maintain financial records and coordinate with the relevant local authorities.
A common CoC could complicate voting shares and assessment of resolution proposals where stakeholders’ interests are confined to different projects or regions, the order said. The tribunal considered this especially relevant because the CIRP is limited to specified projects and assets rather than the entire Ansal Properties corporate debtor. Separate CoCs for Uttar Pradesh and Rajasthan are intended to align creditor decision-making with each geographical asset pool.
The state-level arrangement retains flexibility for proposals within each region. The NCLT said the 2-process structure does not prevent project-wise or group-wise resolution plans from being considered in either Uttar Pradesh or Rajasthan, subject to the Code and CIRP regulations. The state split therefore sets the administrative boundary without requiring every project to have its own separate insolvency process.
Got a follow-up? Ask IRIS
Who will manage Ansal Properties’ Uttar Pradesh and Rajasthan processes?
Mr. Surendra Raj Gang will be the resolution professional for Ansal Properties’ Uttar Pradesh process, while the existing resolution professional, Mr. Navneet Kumar Gupta, will continue for Rajasthan. Mr. Gang’s registration number is IBBI/IPA-001/IP-P01066/2017-2018/11773, and Mr. Gupta’s is IBBI/IPA-001/IP-P00001/2016-2017/10009.
The appointed resolution professional must submit Form-2 consent, a valid AFA and a disclosure that no disciplinary proceedings have been initiated against him within 3 working days of the order’s pronouncement. The requirement applies before the appointed professional performs the statutory functions assigned to the Uttar Pradesh or Rajasthan process.
Mr. Gupta must transfer records, claims, financial information and project-specific particulars relating to Uttar Pradesh to Mr. Gang within 4 weeks of the order’s pronouncement. That transition separates the information needed for the Uttar Pradesh process while Mr. Gupta continues to administer the Rajasthan assets.
How will Ansal Properties’ two CIRPs be coordinated?
The NCLT has provided for 1 common supervisor for both Ansal Properties processes to support coordination, monitoring and uniformity without taking over either resolution professional’s independent statutory functions. The supervisor will monitor the progress of both processes and facilitate coordination where required, while each professional remains responsible for the assets and liabilities in the assigned region.
The supervisor must file a consolidated progress report before the NCLT every 90 days. The order sets remuneration at Rs 2 lakh a month, plus reimbursement of actual expenses, and assigns that cost to the CoC constituted for the Uttar Pradesh projects. Both resolution professionals must cooperate with the supervisor.
The arrangement separates the two regional processes but leaves a reporting link between them. The 90-day consolidated report is the mechanism disclosed by the NCLT for monitoring progress across the Uttar Pradesh projects and Rajasthan assets, while the separate resolution professionals maintain responsibility for region-specific claims, records and resolution steps.
Conclusion
The order converts Ansal Properties’ restricted CIRP into 2 geographically defined processes: one for the Uttar Pradesh project cluster and another for identified Rajasthan assets. The NCLT based the structure on the need to separate assets, liabilities, claims, funds and creditor voting where one common process could complicate administration across the 2 regions.
Next, the appointed professional must provide the required consent and disclosures within 3 working days, and Uttar Pradesh records must be transferred within 4 weeks. Stakeholders can watch the consolidated supervisor reports due every 90 days, the operation of the 2 CoCs and any project-wise or group-wise resolution plans considered within either state process.