Ansal Properties gets two CoCs with flexible CIRP plans
Key highlights
- Ansal Properties will have 2 separate CoCs for Uttar Pradesh and Rajasthan projects.
- The Uttar Pradesh RP must receive records, claims and project information within 4 weeks of the order.
- RPs must file affidavit-backed project assessments within 4 weeks after the Uttar Pradesh handover.
- The common supervisor will report every 90 days and receive Rs 2 lakh per month plus actual expenses.
powered by IRIS

Ansal Properties will run two Corporate Insolvency Resolution Process (CIRP) streams, with one Committee of Creditors for Uttar Pradesh projects and another for Rajasthan projects, while both bodies may consider composite, project-wise or group-wise resolution plans. The Uttar Pradesh records handover is due within 4 weeks, followed by affidavit-backed project assessments.
Know Ansal Properties & Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
How will Ansal Properties’ two CIRP processes be administered?
Ansal Properties will have 2 separate Committees of Creditors (CoCs), one for Uttar Pradesh projects and one for Rajasthan projects. Each Resolution Professional (RP) must verify and collate claims relating to projects and assets in its geographical jurisdiction, constitute the relevant CoC under the Insolvency and Bankruptcy Code and applicable CIRP Regulations, and conduct its process accordingly.
The tribunal retained Navneet Kumar Gupta as RP for Rajasthan and appointed Surendra Raj Gang as RP for Uttar Pradesh. Each RP must file consent in Form-2, a valid Authorisation for Assignment and a disclosure on disciplinary proceedings within 3 working days of the order’s pronouncement. Their duties include identifying, verifying and managing the assets and liabilities assigned to their respective regional scopes.
Mukul Singhal has been appointed common supervisor for the 2 processes. The supervisor is to monitor both RPs, facilitate coordination and promote administrative uniformity without interfering with their independent statutory functions. He must file a consolidated progress report before the tribunal every 90 days, while his consent is also due within 3 working days.
Can Ansal Properties consider composite and project-wise plans?
Yes, Ansal Properties’ RPs and CoCs may consider a composite plan or plans for individual projects or groups of projects under the Code, applicable CIRP Regulations and Regulation 36A. The order states that separate CoCs for Uttar Pradesh and Rajasthan do not prevent consideration of separate plans for individual projects or groups of projects within each state.
The 2-CoC structure therefore separates creditor claim collation and decision-making by geographical process, but does not impose a single route for resolution. The tribunal has not directed a state-wide sale, a sale of a particular project, or a combined transaction. It has instead allowed the RPs and CoCs to consider the permitted plan formats within the legal framework.
No bidder, resolution applicant or submitted plan is identified in the order. Before plan evaluation can advance, the RPs must complete a comprehensive project-wise assessment, including attribution of assets, liabilities and common costs. That assessment is due by affidavit within 4 weeks from the Uttar Pradesh transition and handover described in the order.
Which projects fall within each Ansal Properties CIRP?
Ansal Properties’ Uttar Pradesh CIRP includes Mother City, Mother City Extension and projects in Sushant Golf City, Lucknow, together with the assets and liabilities attributable to those projects. The first process is confined to this defined Uttar Pradesh scope and cannot extend to another project, asset or undertaking beyond the scope identified by the National Company Law Appellate Tribunal.
The Rajasthan CIRP includes projects in that state, including built-up properties at Ajmer, Jodhpur and Jaipur. These properties are listed at serial numbers 5, 6 and 7 of Schedule-B to the settlement agreement dated March 3, 2022. The second process is similarly limited to assets and liabilities falling within its Rajasthan geographical scope.
The existing RP must transfer the relevant Uttar Pradesh records, claims, financial information and project-specific particulars to the Uttar Pradesh RP within 4 weeks of the order’s pronouncement. This transfer is required to enable the incoming RP to verify creditor claims, identify the relevant assets and liabilities, and form the Uttar Pradesh CoC on the prescribed project scope.
Got a follow-up? Ask IRIS
How will Ansal Properties allocate common assets and liabilities?
Ansal Properties’ RPs must prepare a project-wise assessment of the assets, liabilities and financial affairs within their respective CIRPs. The assessment must cover movable and immovable assets, project-wise liabilities, admitted claims, receivables, loans and borrowings, securities and encumbrances, bank accounts and balances, funds received and utilised, inter-project transfers and common expenses.
Where an asset, liability, fund, receivable or expenditure relates to more than 1 project or cannot be directly assigned, the relevant RP must make a reasoned pro rata allocation. The affidavit must specify the basis and methodology used. The order does not permit an item to be transferred, appropriated or excluded merely because the CIRP has been divided geographically.
The RPs must separately identify common infrastructure, shared resources and cross-collateralisation, where applicable. They must distinguish such shared items from project-specific assets and liabilities, support the assessment with relevant records, and file it by affidavit within 4 weeks after the Uttar Pradesh transition and handover. If either RP finds an item potentially included or excluded wrongly, tribunal directions must be sought before consequential action.
What issues remain pending in Ansal Properties’ CIRP?
The question of a proposed take-over of Ansal Properties’ Lucknow projects remains pending in I.A. 4747/2026. The tribunal will consider that matter separately after hearing the Lucknow Development Authority, the RP and other concerned parties. It has stated that no final opinion has been formed on the merits at this stage.
A possible application by the Uttar Pradesh Awas Evam Vikas Parishad seeking exclusion of assets it claims from the CIRP is also reserved for separate consideration. The order provides no decision on that potential application and says it will be considered under National Company Law Appellate Tribunal directions and applicable law. These matters concern the eventual scope of assets in the relevant process.
The common supervisor’s remuneration is Rs 2 lakh a month, plus reimbursement of actual expenses, and the Uttar Pradesh CoC must bear that cost. Although the supervisor oversees both processes, the order preserves the RPs’ separate statutory responsibilities. Both RPs have also been directed to proceed expeditiously under applicable CIRP Regulations and directions of the Supreme Court and National Company Law Appellate Tribunal.
Conclusion
Ansal Properties’ CIRP arrangement creates 2 separate creditor processes based on Uttar Pradesh and Rajasthan project scopes, while retaining flexibility over the form of a resolution plan. Separate RPs, claim verification and CoCs will operate for each region, but project-wise, group-wise and composite options remain available under the Code and CIRP Regulations.
The next disclosed steps are the Uttar Pradesh records handover within 4 weeks of the order and the RPs’ affidavit-backed assessments within 4 weeks after that handover. Progress will also be tracked through the supervisor’s report every 90 days and the separate hearing in I.A. 4747/2026 on the Lucknow projects.