Atlanta Electricals says Gujarat rains deferred Rs 180 crore
Key highlights
- Atlanta Electricals said Gujarat rains deferred completed transformer deliveries worth Rs 180 crore in Q2 FY27.
- About 70% of Atlanta Electricals' deferred orders had been dispatched by October 2026.
- Atlanta Electricals inventory rose to Rs 632.9 crore on September 30, 2026, from Rs 364.1 crore on March 31, 2026.
- Atlanta Electricals reported a Q2 FY27 EBITDA margin of 15.3%, down from 17.3% a year earlier.
powered by IRIS

Atlanta Electricals Limited said Gujarat rainfall deferred completed transformer deliveries worth Rs 180 crore in Q2 FY27 because customer sites could not accept equipment; about 70% had been dispatched by October. Atlanta Electricals expects the remaining deliveries in Q3 FY27, subject to customer-site readiness.
Know Atlanta Electricals inside out
Results, valuation, peers and who's buying, in one view.
Why were Atlanta Electricals deliveries deferred in Q2 FY27?
Atlanta Electricals said unusually heavy rainfall and waterlogging in Gujarat disrupted manufacturing, transportation and customer delivery schedules in Q2 FY27. Its manufacturing facilities took precautionary shutdowns on two occasions, but management identified customer project sites being unable to accept completed transformers as the more significant reason for Rs 180 crore of deferred deliveries.
The company said these orders were deferred rather than cancelled and remained in the order book. Operations were normal after the monsoon withdrew, according to management, and customer-site activities had resumed by the November 2, 2026 earnings call. Approximately 70% of the deferred orders had already been dispatched, while the remaining deliveries depend on site readiness during Q3 FY27.
Q2 revenue still increased 23.1% year on year to Rs 390.1 crore from Rs 317 crore in Q2 FY26. The weather interruption nevertheless delayed the execution and acceptance of a meaningful amount of completed equipment, creating a timing difference between manufacturing completion and delivery during the quarter.
How did the delivery backlog affect Atlanta Electricals inventory?
Atlanta Electricals reported inventory of Rs 632.9 crore as of September 30, 2026, compared with Rs 364.1 crore on March 31, 2026. Management said the increase partly reflected finished transformers awaiting dispatch and customer acceptance after the weather disruption, alongside raw-material procurement needed for ongoing manufacturing operations.
The Rs 268.8 crore increase over six months was larger than the Rs 180 crore of deferred completed orders. That comparison indicates the delivery backlog was only one contributor to the inventory movement; Atlanta Electricals also cited procurement requirements for its expanding operations. Management expects the related finished-goods inventory to move progressively as remaining deferred orders are executed.
Outstanding orders stood at Rs 3,196.97 crore on September 30, 2026, up from Rs 3,116.63 crore on June 26 and about Rs 2,069 crore a year earlier. Atlanta Electricals booked approximately Rs 421 crore of new orders during Q2 FY27, although it said commodity-price volatility delayed finalisation of certain tenders where it had emerged as L1, or lowest bidder.
Did the disruption reduce Atlanta Electricals profitability?
Atlanta Electricals reported lower gross and EBITDA margins in Q2 FY27, with elevated input costs the main stated cause and temporary execution disruption also affecting operating leverage. Earnings before interest, tax, depreciation and amortisation, or EBITDA, rose 8.8% year on year to Rs 59.6 crore from Rs 54.8 crore, but its margin declined to 15.3% from 17.3%, a fall of about 201 basis points.
Gross profit increased 6.1% to Rs 103.6 crore from Rs 97.8 crore, while gross margin fell to 26.6% from 30.9%. Management attributed the gross-margin change primarily to higher transformer oil, copper and steel prices. It also said that the disruption to execution reduced operating leverage during the quarter.
Firm-price contracts added to the input-cost effect. Orders booked in the previous year without the same price-adjustment flexibility represented about 15% of Q2 FY27 revenue, according to management. Most orders include price-variation clauses, but Atlanta Electricals said it expects the smaller remaining firm-price orders to be substantially completed in Q3 FY27.
Profit after tax, or PAT, rose 28% to Rs 32.1 crore from Rs 25.1 crore, and PAT margin improved to 8.2% from 7.9%. Atlanta Electricals attributed part of that outcome to finance costs declining to Rs 8.5 crore from Rs 13.2 crore a year earlier. Basic and diluted earnings per share increased to Rs 4.18 from Rs 3.50.
Got a follow-up? Ask IRIS
What did H1 FY27 results show for Atlanta Electricals?
Atlanta Electricals reported revenue growth through H1 FY27 despite the Q2 disruption, with revenue from operations rising 35.5% to Rs 856.4 crore from Rs 632.1 crore in H1 FY26. EBITDA increased 32% to Rs 136.7 crore from Rs 103.6 crore, although the H1 EBITDA margin edged down to 16.0% from 16.4%.
PAT for H1 FY27 rose 40.4% year on year to Rs 79 crore from Rs 56.2 crore, while PAT margin increased to 9.2% from 8.9%. The half-year figures show that revenue, EBITDA and PAT remained higher than the prior-year period even as Q2 gross margin and EBITDA margin were below their Q2 FY26 levels.
Depreciation and amortisation expense increased to Rs 20.1 crore in H1 FY27 from Rs 7.9 crore in H1 FY26 after new manufacturing capacities were commissioned. Management said it expects better absorption of the operating cost base as utilisation improves, while continuing to manage commodity volatility, working capital and delivery execution.
What is Atlanta Electricals planning for the second half?
Atlanta Electricals plans to accelerate deferred deliveries, improve capacity utilisation and commission its dedicated inverter duty transformer, or IDT, facility before the end of Q3 FY27. Civil construction at the facility was complete and machinery installation was under way. The project is planned to add about 5,000 megavolt-amperes of capacity with capital expenditure of Rs 65 crore.
The IDT facility is intended to shift 33 kilovolt IDT manufacturing from Unit 2, releasing that unit for 66 kilovolt and 132 kilovolt products. Separately, Atlanta Electricals began manufacturing its first 315 megavolt-ampere, 400 kilovolt-class transformer on October 26 after delays in receiving critical components. Management is targeting manufacturing completion and short-circuit testing in Q3 FY27, with commercial contribution expected in Q4 FY27 subject to testing and approvals.
Atlanta Electricals also has a tank and radiator backward-integration project through AE Components, with planned capital expenditure of approximately Rs 193 crore and a commissioning target of October 2027. Management said the project is intended to improve supply-chain reliability and manufacturing efficiency. These initiatives do not alter the condition attached to the remaining weather-deferred deliveries, which is customer-site acceptance.
Conclusion
The Q2 FY27 interruption at Atlanta Electricals was an execution and acceptance delay rather than an order cancellation, based on management's description of Rs 180 crore of completed transformers remaining in the order book. Rain-related plant shutdowns and customer-site disruption coincided with inventory reaching Rs 632.9 crore and EBITDA margin declining by about 201 basis points, while Q2 and H1 revenue and PAT still increased year on year.
The next disclosed milestone is completion of the remaining deferred deliveries in Q3 FY27, subject to customer-site readiness, after around 70% had been dispatched by October. Management's other stated markers are commissioning the 5,000 megavolt-ampere IDT facility before the end of Q3 FY27, substantial completion of firm-price orders in Q3 FY27, and testing of the first 315 megavolt-ampere, 400 kilovolt-class transformer.