ESDS funds Rs 1,336 crore Sharon AI deposit from advance
Key highlights
- ESDS said its Rs 1,336 crore Sharon AI deposit in May 2026 was fully funded by a matching customer advance.
- ESDS said no additional letter of credit or bank guarantee is required alongside the Rs 1,336 crore cash deposit.
- The Rs 1,336 crore deposit will be adjusted against service fees and is recorded as an advance to vendor.
- ESDS expects Sydney AI factory handover in mid-December 2026 and billing from January 2027.
powered by IRIS

ESDS Software Solution Limited said its Rs 1,336 crore security deposit placed with Sharon AI in May 2026 was funded entirely by an equal customer advance, without using its own cash. ESDS said the deposit replaces additional letters of credit or bank guarantees and will be adjusted against service fees during the contract term.
Know ESDS Software Solution inside out
Results, valuation, peers and who's buying, in one view.
How did ESDS fund the Sharon AI security deposit?
ESDS funded the Rs 1,336 crore Sharon AI security deposit from a customer advance of the same amount. The company said it placed the deposit in May 2026 as an agreed alternative to letters of credit, and explicitly stated that the payment did not draw on ESDS's own cash.
The deposit relates to the Sydney AI factory, where all 8,208 NVIDIA B300 graphics processing units, or GPUs, had been installed as of ESDS's November 21, 2026 clarification. ESDS said customers committed funds before a single GPU went live, while customer names remain confidential under the contracts.
ESDS said no letter of credit or bank guarantee is outstanding or required in addition to the Rs 1,336 crore cash deposit. The stated arrangement therefore substitutes a customer-funded cash deposit for the further bank-backed security instruments that might otherwise have been required under the Sharon AI agreement.
How will ESDS account for the Rs 1,336 crore deposit?
ESDS will adjust the Rs 1,336 crore deposit against service fees over the contract term, and therefore records it as an advance to vendor. This treatment means the amount is not described in the filing as an immediate operating cost of the Sydney AI factory.
The filing also states that the deposit is refundable if Sharon AI does not deliver according to the contract. ESDS did not disclose the timing or process for a refund, but said monthly charges payable to Sharon AI begin only after the cluster is accepted.
Customer payments are also due to begin after cluster acceptance, according to ESDS's November 21 disclosure. The company said this alignment means the revised handover schedule does not add to its costs, because payments by ESDS and payments to ESDS start together.
What customer advances did ESDS report at September 30, 2026?
ESDS said customer advances in its balance sheet at September 30, 2026 included the Rs 1,336 crore advance used for the Sharon AI deposit and advances received before March 31, 2026. The filing does not disclose the aggregate customer-advance balance at September 30, 2026.
Advances received before March 31, 2026, which ESDS had disclosed in its prospectus, remained unutilised in the group's bank accounts at September 30, 2026. This separates the earlier balances from the May 2026 advance that was used to fund the Sharon AI security deposit.
ESDS said no major advances were received in the quarter ended September 30, 2026. Its clarification followed a November 19, 2026 article that questioned the economics of the Sharon AI arrangement, customer contracts and ESDS's role in the Sydney project.
Got a follow-up? Ask IRIS
How do ESDS customer contracts match its Sharon AI commitment?
ESDS said the entire Sydney AI factory capacity is contracted with customers on a take-or-pay basis, requiring customers to pay for full capacity whether they use it or not. The company also said customer contract terms and exit provisions mirror its agreement with Sharon AI.
ESDS's contractual commitment to Sharon AI is approximately Rs 14,285.71 crore over 60 months, based on the company's disclosed US$1.26 billion commitment and its stated approximate annual equivalent of Rs 2,400 crore. This equates to about Rs 200 crore a month at the same approximate conversion basis, under a fixed per-GPU-per-hour rate for the full term.
Management expects customers to pay about Rs 285.71 crore a month, against approximately Rs 200 crore a month payable to Sharon AI, using the same approximate conversion basis from the filing. That leaves about Rs 85.71 crore a month before operating costs and tax; the company did not separately quantify those costs in the clarification.
The filing says both customer receipts and Sharon AI payments are denominated in US dollars. ESDS cautioned that currency movements will alter reported rupee revenue, costs and profit, although it said such movements would not change the margin earned in US dollars.
When will ESDS start billing for the Sydney AI factory?
ESDS expects handover of the Sydney AI factory in mid-December 2026 and expects billing to start in January 2027. As of November 21, 2026, the company said all 8,208 NVIDIA B300 GPUs were installed and the cluster was in final testing.
The delivery timeline was revised by mutual agreement with Sharon AI, according to ESDS. The company said customers had been kept informed and that it chose to complete full testing before taking handover; it also said the revised schedule matched Sharon AI's timeline published with quarterly results on November 16, 2026.
The Sydney factory is ESDS's first facility outside India. Sharon AI owns the hardware and data-centre capacity, while ESDS supplies cluster operations, a 24x7 network and security operations centre, model training, and GPU-as-a-Service under one customer contract.
ESDS currently estimates monthly profit after tax from the project at approximately Rs 38.10 crore to Rs 47.62 crore, using the filing's approximate dollar-to-rupee conversion basis. Management said this equals an expected 14% to 17% margin on revenue, and cautioned that the estimate is an expectation rather than a guarantee.
Conclusion
ESDS's November 21, 2026 clarification states that its Rs 1,336 crore Sharon AI deposit was wholly financed by a matching customer advance rather than its own cash. The deposit requires no additional letter of credit or bank guarantee, will be offset against future service fees, and sits alongside customer contracts that ESDS says mirror its Sharon AI obligations.
The next disclosed milestone is handover in mid-December 2026, followed by expected billing in January 2027. ESDS said it will notify the stock exchanges when the Sydney AI factory goes live; investors will also need to watch delivery, customer payments, operating costs, tax and US dollar-rupee movements affecting reported figures.