Globe Civil H1 FY27 cash flow negative as collections lengthen
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Globe Civil reported Rs 11.97 crore negative operating cash flow in H1 FY27 despite Rs 27 crore operating profit before working-capital changes.
- Newer project payments can take about 2.5 to three months after work execution, management said.
- Globe Civil said retention money is 7.5% on some newer projects.
- An analyst cited standalone inventory of approximately Rs 176.26 crore at September 2026 after early material procurement.
powered by IRIS

Globe Civil Projects Limited reported Rs 11.97 crore of negative net cash from operating activities in the first half of fiscal year 2027, or H1 FY27, despite Rs 27 crore of operating profit before working-capital changes, as newer projects required early material purchases, took up to three months for collections and carried 7.5% retention deductions.
Know Globe Civil Projects inside out
Results, valuation, peers and who's buying, in one view.
Why was Globe Civil’s operating cash flow negative in H1 FY27?
Globe Civil’s H1 FY27 operating cash flow was negative because trade receivables, security deposits and defect-liability deposits rose on newer projects, management said. Net cash generated from operating activities was negative Rs 11.97 crore, despite operating profit before working-capital changes of Rs 27 crore during the first six months of FY27.
The Rs 38.97 crore difference between those two measures reflects the cash absorbed by working-capital movements. Management distinguished this timing issue from operating profitability, saying Globe Civil’s earlier Central Public Works Department, or CPWD, projects had shorter billing cycles than newer work for NBCC, the Haryana Cricket Association Stadium and Unitech.
For FY26, management also linked negative operating cash flow to higher debtors despite positive operating profit before working-capital changes. It said the company had to invest initial public offering proceeds in working capital, while the H1 FY27 cash outflow was principally associated with the newer project mix and related deposits.
How long does Globe Civil take to collect newer project bills?
Globe Civil said payment on the Haryana Cricket Association stadium project can arrive about 2.5 to three months after work execution. Management said bill preparation itself takes around 1.5 months, followed by client checking and payment after 40 days under that contract.
The company cited a September example to illustrate the delay. Management said it expected in the following week a payment for work billed in the first week of September, showing that billed work can remain unpaid while client certification and payment procedures continue.
Management did not disclose the value of completed but unbilled work as of September 2026. It did say the stadium project billed around Rs 30 crore to Rs 40 crore in H1 FY27, while the Bathinda project billed about Rs 7 crore a month, or around Rs 40 crore to Rs 45 crore for the half year.
How do retentions and subcontractor payments increase Globe Civil’s funding need?
Globe Civil said retention money is 7.5% on some newer projects, leaving part of billed value unavailable until contract conditions are met. Management also identified increased security deposits and defect-liability deposits for clients including NBCC as contributors to higher working-capital needs.
Globe Civil generally funds subcontractor payments independently of client collections. Management said subcontractors may not wait 2.5 months, three months or longer for customer payments, requiring the company to pay labour and subcontracting costs before it receives project cash.
Management used the Narela project as an example of final-bill timing. The project was completed in March 2026, and most subcontractors and contractors had been paid by April, May or June, but the final bill remained with the department and Globe Civil expected the security deposit and other money by December or January.
Got a follow-up? Ask IRIS
Why did Globe Civil increase inventory while collections slowed?
Globe Civil increased inventory to secure materials early amid price volatility, management said. An analyst cited standalone inventory of approximately Rs 176.26 crore as of September 2026, and management said inventory had risen because the company procured steel and other major materials earlier.
In engineering, procurement and construction, or EPC, contracts, major materials may be required early even when installation takes longer. Management cited tiles as an example of materials that may be bought for an entire project before they are installed, extending the period between purchase and revenue collection.
Management said it had tried to reduce receivables but remained keen to purchase major materials as early as possible. It also said project costs and profitability estimates are reassessed every quarter because material prices change and the economics of individual contracts can vary by project stage.
What does Globe Civil’s contract mix mean for cash conversion?
Globe Civil said about Rs 200 crore of its approximately Rs 600 crore order book comprised fixed-price contracts. Management identified the Haryana Cricket Association project as a major fixed-price contract, while noting that steel is supplied free of cost by the client and is therefore outside Globe Civil’s cost scope.
Most of the remaining order book has price-escalation clauses or client-supplied-steel arrangements, according to management. It said escalation is determined broadly through the government-issued Wholesale Price Index, meaning recovery reflects an overall index rather than movements in individual material prices.
Management said variation claims on ongoing projects operate on a three-month cycle, which can delay recovery after input costs rise. It described the Rs 600 crore order book as sufficient for roughly 1.5 years based on annual execution of around Rs 400 crore, while saying two or three new projects were needed in the next four to five months for next-year revenue.
Conclusion
Globe Civil’s H1 FY27 cash-flow position reflects the timing of project funding rather than a negative operating-profit measure. The Rs 38.97 crore gap between Rs 27 crore of operating profit before working-capital changes and negative Rs 11.97 crore of operating cash flow was associated with longer collections, 7.5% retentions, deposits, independently funded subcontractors and early material procurement.
The next issue is whether Globe Civil converts billed and retained amounts into cash as management expects, including the Narela recovery expected by December or January. Management is also seeking two or three projects within four to five months and has targeted 10% to 15% year-on-year revenue growth while aiming to maintain margins amid volatile material prices.