Globe Civil FY26 order book rises to Rs 730 crore after wins
Key highlights
- Globe Civil reported a FY26 order book of Rs 730 crore, up Rs 60.90 crore from FY25.
- Four major FY26 contracts had a combined stated value of Rs 564.96 crore.
- The Rs 222.20 crore Jhajjar cricket stadium contract was Globe Civil's largest disclosed FY26 order.
- Globe Civil reported standalone FY26 revenue of Rs 376.529 crore, versus Rs 325.992 crore in FY25.
powered by IRIS

Globe Civil Projects Ltd. (Globe Civil) closed FY26 with a Rs 730 crore order book, up Rs 60.90 crore from FY25, after disclosing four major contracts worth Rs 564.96 crore. The contracts cover a Punjab university campus, a Jhajjar cricket stadium and projects at IIT Kanpur and IIT Delhi.
Know Globe Civil Projects inside out
Results, valuation, peers and who's buying, in one view.
Which major contracts did Globe Civil disclose in FY26?
Globe Civil disclosed four major FY26 orders with stated values totalling Rs 564.96 crore, led by the Rs 222.20 crore International Cricket Stadium project in Jhajjar for the Haryana Cricket Association. The Central University of Punjab Campus contract for NBCC (India) Ltd was the second-largest, at Rs 172.99 crore.
The contract timelines range from 16 months to 24 months. The Rs 98.85 crore IIT Delhi project has an 18-month schedule, while the Rs 70.92 crore Kotak School of Sustainability project at IIT Kanpur has a 16-month schedule and carries an L1 designation in the presentation.
The Rs 564.96 crore combined value of the four orders equals about 77% of the Rs 730 crore FY26 order book. That comparison does not mean the contracts were wholly unexecuted at FY26-end, because the presentation does not disclose their execution status or say how much of each project was included in the closing order-book balance.
How did Globe Civil's order book change through FY26?
Globe Civil's order book rose to Rs 730 crore in FY26 from Rs 669.10 crore in FY25, reversing part of the decline from Rs 980.85 crore in FY24. The FY26 increase was Rs 60.90 crore, while the closing balance was still Rs 250.85 crore below the FY24 level.
The order book fell Rs 311.75 crore between FY24 and FY25 before increasing Rs 60.90 crore in FY26. The presentation establishes the change in year-end balances, but does not provide order inflow, project execution, cancellation or retention data to explain the movement in each period.
Management said the FY26 order book offered visibility for the next two to three years and cited repeat business from marquee clients. This is management's outlook, rather than a quantified revenue forecast, as the presentation does not allocate annual revenue, margin or cash-flow contributions to the Rs 730 crore balance.
What does Globe Civil's order book indicate about project mix?
Globe Civil reported that government projects accounted for Rs 433.272 crore, or 64.75%, of its order book as of March 31, 2025. This portfolio disclosure relates to the FY25 period, not the Rs 730 crore order book reported at the end of FY26.
The company identifies government infrastructure, particularly education and healthcare construction, as a priority. Its FY26 list includes the Central University of Punjab Campus and the IIT Kanpur and IIT Delhi projects, worth a combined Rs 342.76 crore, but the presentation does not identify the government-funded share of these contracts or of the FY26 closing book.
Globe Civil said it was operating in 11 states and planned to expand into West Bengal and Odisha while building its existing-market presence. It also reported six joint ventures as of March 31, 2026, which management said could combine expertise, share risks and support bids for larger opportunities.
Got a follow-up? Ask IRIS
What execution capacity and bidding plans has Globe Civil set out?
Globe Civil said it had completed 37 projects and was managing 13 ongoing projects, alongside the four FY26 orders carrying schedules of up to 24 months. The company cites its in-house engineering and design team as an execution capability, but provides no project-level completion rates, delay data or cost performance for the 13 ongoing assignments.
Management plans to invest Rs 14.255 crore in new machinery, strengthen its workforce and use advanced project-management tools. The presentation links these measures to efficiency, timely delivery, quality and safety, but does not provide an implementation timetable, asset deployment plan or expected financial return.
Globe Civil said its Class I Super Contractor status allows it to bid independently for projects worth up to Rs 650 crore. Management also said it aims to increase bid capacity and pre-qualification eligibility, using joint ventures where necessary, although the presentation gives no target bid limit or deadline for that plan.
How did FY26 financial performance compare with the order-book trend?
Globe Civil reported standalone revenue from operations of Rs 376.529 crore in FY26, compared with Rs 325.992 crore in FY25 and Rs 294.905 crore in FY24. The company stated that revenue grew at a compound annual growth rate of 10.52% from fiscal 2024 to 2026, while its order book first declined in FY25 and then increased in FY26.
Standalone profit before tax was Rs 31.234 crore in FY26, down from Rs 33.237 crore in FY25 but above Rs 20.669 crore in FY24. Profit after tax was Rs 23.308 crore in FY26 versus Rs 24.051 crore in FY25, while the presentation reported a fiscal 2024-to-2026 profit-before-tax compound annual growth rate of 22.13%.
On a consolidated basis, revenue from operations reached Rs 405.715 crore in FY26, compared with Rs 378.576 crore in FY25. Consolidated net profit was Rs 23.299 crore in FY26, against Rs 24.051 crore a year earlier, meaning the higher FY26 order book coincided with increased consolidated revenue but lower consolidated net profit.
Conclusion
Globe Civil's FY26 disclosures show a recovery in the closing order-book balance after the FY25 decline, with four named contracts spanning education and sports infrastructure. The Rs 564.96 crore aggregate value of these disclosed orders provides identified project activity alongside FY26 standalone revenue of Rs 376.529 crore and consolidated revenue of Rs 405.715 crore.
The next points to watch are the delivery of contracts scheduled for 16 to 24 months, the planned Rs 14.255 crore machinery investment, and the intended expansion into West Bengal and Odisha. Management also plans to improve pre-qualification and bidding capacity beyond its stated Rs 650 crore independent bidding limit, but has not disclosed a target or timetable.