HUDCO expects Dharavi to start PPP lending this quarter
Key highlights
- HUDCO sanctioned Rs 9,000 crore of PPP projects across redevelopment, roads, HAM and energy.
- Dharavi redevelopment could become HUDCO's first PPP disbursement during the quarter discussed on November 6, 2026.
- HUDCO said no PPP disbursement had begun despite the Rs 9,000 crore of approved projects.
- HUDCO reported a broader sanctioned pipeline of about Rs 3 lakh crore to Rs 4 lakh crore with three-to-five-year gestation periods.
powered by IRIS

Housing and Urban Development Corporation Limited expects the Dharavi redevelopment to become its first public-private partnership, or PPP, loan disbursement in the quarter discussed on November 6, 2026, after sanctioning Rs 9,000 crore of PPP projects. Management said Dharavi documentation was at an advanced stage, while no PPP project had yet received a disbursement.
Know Housing & Urban Development Corporation inside out
Results, valuation, peers and who's buying, in one view.
What has HUDCO sanctioned under PPP lending?
HUDCO has sanctioned Rs 9,000 crore of PPP projects covering the Dharavi redevelopment, road projects including hybrid annuity model, or HAM, projects, and one energy-sector project. Management described the activity as recently started private or non-sovereign lending, rather than a portfolio with an established disbursement history. The Rs 9,000 crore is sanctioned exposure and does not represent money already released to borrowers.
HUDCO did not disclose the individual sanction amount, loan tenor, borrower, pricing or first-drawdown size for the Dharavi project. Management said its lending is released according to project progress, meaning documentation and implementation milestones determine when a sanctioned amount becomes a disbursement. That leaves the scale of any initial Dharavi release unspecified.
The PPP sanctions sit within a wider project pipeline. HUDCO said it had been sanctioning about Rs 1 lakh crore every half year and had a broader sanctioned pipeline of about Rs 3 lakh crore to Rs 4 lakh crore. Management said projects in that pipeline have gestation periods of three to five years, so sanction figures do not immediately translate into loans outstanding or cash releases.
Why is Dharavi expected to be HUDCO's first PPP disbursement?
Dharavi is expected to be HUDCO's first PPP disbursement because its documentation is in an advanced stage and management said it was hopeful of starting the release during the quarter. At the November 6, 2026 call, management said no other sanctioned PPP project had begun receiving funds, including the road, HAM and energy projects within the Rs 9,000 crore total.
The timing is an expectation rather than a fixed closing date. Management later said it was trying to start a disbursement in the quarter, which indicates that further documentation steps remained. HUDCO provided no rupee amount for the initial release, so the transcript does not show what portion of the Rs 9,000 crore sanction book could be drawn in that period.
The expected Dharavi release would add a new lending category while HUDCO pursues an internal annual disbursement target of Rs 65,000 crore. It had already disbursed more than Rs 35,000 crore in the first half and estimated another Rs 30,000 crore for the remaining period. Management said the annual total could rise if project execution accelerated, but it did not assign a separate PPP disbursement target.
Got a follow-up? Ask IRIS
How will HUDCO control risk in non-sovereign lending?
HUDCO said it will fund PPP projects only where the borrower is investment grade and the project has a strong concession agreement. Management said it would not compromise on asset quality as it expands non-sovereign lending, and cited strong appraisal and monitoring as prerequisites for credit approval.
The stated protections include third-party due diligence and appraisal, a project management arrangement, or PMA, and a trust and retention account, or TRA. Management named CRISIL and ICRA as examples of agencies that could provide third-party appraisal. The transcript does not say whether all these steps had been completed for Dharavi, but management presented them as risk-mitigation conditions for PPP lending.
HUDCO also said it would assess regulatory arrangements where relevant, citing the power sector as an example. Management said the risk premium on PPP lending would be higher than for state-government lending, although it acknowledged the market is competitive. It did not disclose a target lending rate, credit-cost assumption, exposure cap or expected margin for the Rs 9,000 crore of PPP sanctions.
The safeguards are relevant because management discussed recoveries and resolutions in legacy private-sector loans. It reported recoveries of Rs 32 crore and resolutions of about Rs 359 crore in H1 2027, compared with recoveries of about Rs 403 crore and resolutions of about Rs 660 crore in 2025-2026. Management said around 95% of the loans being discussed in that recovery context were to private-sector entities.
How does PPP lending fit HUDCO's wider lending plan?
HUDCO said its broader objective is a Rs 3 lakh crore loan book by 2030, but management explicitly said there was no separate target for PPP funding. The company said it would lend selectively as suitable entities and projects emerge, supported by concession agreements or regulatory arrangements. The Rs 9,000 crore PPP sanction book is therefore a specific approved portfolio, not management guidance for a future lending volume.
Management said the reported spread was 1.96% and net interest margin, or NIM, was 2.93% at the time of the call, while its targets were about 2% for spread and at least 3% for NIM. It attributed the reported figures partly to a Rs 20,000 crore Government of India loan carrying a 40-basis-point spread. One basis point is one-hundredth of a percentage point.
HUDCO said the Rs 20,000 crore Government of India exposure is expected to run off in FY 2028-2029. Excluding that exposure, management said its spread was around 2% and NIM was around 3%. It also reported a loan book of Rs 1.86 lakh crore and borrowings of about Rs 1.65 lakh crore, placing the Rs 9,000 crore PPP sanctions within a substantially larger lending and funding base.
On pricing, HUDCO said it increased its marginal cost of funds-based lending rate, or MCLR, by 15 basis points after a two-year gap. Loans are generally reset annually on a tranche-by-tranche basis, and management expected about Rs 20,000 crore of loans to reset during the half year. It also said it was discussing quarterly resets in some cases to transmit higher funding costs more quickly.
Conclusion
HUDCO has moved from setting guidelines for non-sovereign lending to sanctioning Rs 9,000 crore of PPP projects across redevelopment, roads, HAM and energy. Dharavi is the near-term operational test because it could become the first project to draw funds, while investment-grade borrowers, concession agreements, third-party appraisal, PMA structures and TRAs are the protections management said will govern PPP credit.
The next point to watch is whether Dharavi documentation is completed and a disbursement begins in the quarter cited on the November 6, 2026 call. Management's stated Rs 65,000 crore annual disbursement target, the Rs 3 lakh crore to Rs 4 lakh crore wider sanction pipeline and three-to-five-year project gestation periods will also determine how quickly approved projects become funded loans.