Insolation Energy targets Q4 FY27 first cell from 4.5 GW plant
Key highlights
- INA Solar targets first output from its 4.5 GW TOPCon cell line in Q4 FY27.
- Pre-engineered building erection and main civil work are complete, while machinery installation is ongoing.
- INA Solar says 200 engineers are deployed for two years and its planned workforce is 900 employees.
- H1 FY27 revenue rose 100.56% to Rs 1,582.09 crore, while profit after tax fell 21.22% to Rs 63.08 crore.
powered by IRIS

Insolation Energy targets the first solar cell from its 4.5 GW TOPCon G12R line in Q4 FY27, following completion of the pre-engineered building and main civil works at Nandaramapuram, Madhya Pradesh. Machinery installation remains under way, with commissioning, factory acceptance testing and trial production still scheduled before the target.
Know Insolation Energy inside out
Results, valuation, peers and who's buying, in one view.
What is INA Solar’s 4.5 GW TOPCon cell plan?
INA Solar plans 4.5 GW of TOPCon cell-manufacturing capacity at Nandaramapuram, Madhya Pradesh, under its INA 4 project. The presentation identifies the product as advanced N-type TOPCon G12R cell technology and places first cell output from the line in Q4 FY27.
The 4.5 GW cell facility is intended to add a manufacturing stage to INA Solar’s existing 5.5 GW module capacity. Management presents this as backward integration intended to provide greater supply-chain control and cost competitiveness, rather than a further module-capacity addition.
The company’s longer-term manufacturing model is described as a 1:1:1:1 capacity structure across module, cell, aluminium frame, and ingot and wafer operations. INA Solar says land within the existing campus is secured for future ingot and wafer facilities, although funding planning for that expansion remains under discussion.
How far has INA Solar progressed with the cell plant?
INA Solar reports that pre-engineered building erection, main-building civil work, major utility orders and the first funding tranche are complete for the 4.5 GW project. Machinery installation is ongoing, while commissioning and factory acceptance testing, abbreviated as FAT, are the next listed stages and are described as on time.
The stated sequence is machinery installation, commissioning and FAT, trial production, and then first cell output in Q4 FY27. INA Solar does not disclose a percentage completion for machinery installation, a specific date within Q4 FY27, or a production-ramp schedule after the first cell is made.
The presentation names Nandaramapuram in Madhya Pradesh as the cell-facility location. It separately identifies Sawarda in its incentive disclosures, where Phase 1 investment of Rs 179.12 crore has received an entitlement certificate under the Rajasthan Investment Promotion Scheme 2022, or RIPS-2022.
Who is executing INA Solar’s Q4 FY27 target?
INA Solar says 200 engineers, comprising 100 Chinese and 100 Indian personnel, are deployed at the site for two years. The project structure includes SC Solar as turnkey provider, FIRST as technical consultant, RCT as owner’s engineer, and INA Solar’s in-house hiring and operating team.
SC Solar’s contract covers plant design, equipment, process know-how and commissioning under one turnkey scope. INA Solar says SC Solar has deployed 150 engineers, including 50 Chinese specialists and 100 Indian engineers, and that payments under the two-year contract are tied to key performance indicators and delivery milestones.
FIRST has appointed 50 Chinese engineers to provide technical oversight across design, quality and site progress, as well as research and development improvements. RCT, described as a German-owned technical consultant, is responsible for reviewing technical documents for utilities, machinery and processes across cell, module, frame, and ingot and wafer operations.
INA Solar says more than 50 senior professionals have joined the site, recruitment drives were completed in Baddi and Surat, and more than 300 letters of intent were issued for joining expected in August. The planned workforce is 900 employees, including blue-collar personnel, indicating further staffing is expected during the installation and commissioning stages.
Got a follow-up? Ask IRIS
What infrastructure and incentives are disclosed for INA Solar’s manufacturing plans?
INA Solar says power availability is secured and bulk industrial water supply has been sanctioned for the cell project, whose processes include high-volume texturing and chemical processing. The company also says electricity is available at the lowest industrial tariff, while major utilities have already been ordered.
For the Sawarda facility, INA Solar says RIPS-2022 provides a 100% electricity-duty exemption for nine years. Management expects that exemption to generate annual savings of more than Rs 1 crore at current consumption levels, though the presentation does not quantify the current consumption level.
INA Solar also discloses a 1.98% turnover-linked incentive of up to Rs 224 crore over about nine years for Sawarda Phase 1. The entitlement certificate applies to the Rs 179.12 crore Phase 1 investment, and the presentation does not assign those Sawarda incentives to the Nandaramapuram cell plant.
How does the cell project compare with INA Solar’s recent financial performance?
INA Solar reported H1 FY27 revenue of Rs 1,582.09 crore, up 100.56% from Rs 788.85 crore in H1 FY26, while earnings growth did not match revenue growth. EBITDA increased 23.30% to Rs 140.31 crore, but profit after tax declined 21.22% to Rs 63.08 crore.
In Q2 FY27, revenue rose 96.45% year on year to Rs 836.69 crore, while EBITDA margin declined to 7.58% from 13.15% in Q2 FY26. Depreciation and amortisation rose 183.13% to Rs 17.72 crore, and finance cost increased 169.12% to Rs 12.78 crore in the same quarterly comparison.
INA Solar also reports about 2.5 GW of pipeline under internal evaluation across memorandums of understanding, partnerships and direct supply orders. Of an approximately 2.2 GW order book, it says 1.3 GW is scheduled for delivery by March 2027, with production slots allocated; the presentation does not state how much of the pipeline is contracted.
Conclusion
INA Solar’s Q4 FY27 first-cell target rests on completed civil and pre-engineered building work, utility orders, and a multi-party execution structure involving 200 engineers. The 4.5 GW cell line would extend the company beyond its reported 5.5 GW module capacity and is central to management’s stated backward-integration plan.
The next disclosed milestones are commissioning, FAT and trial production before first cell output in Q4 FY27. The presentation leaves machinery-installation completion, the production ramp after first output, and funding for future ingot and wafer capacity unresolved, while 1.3 GW of the reported order book is scheduled for delivery by March 2027.