Jindal Supreme targets Raipur production start by March 2028
Key highlights
- Jindal Supreme targets March 2028 production at its Raipur greenfield facility.
- Raipur phase 1 is planned at about Rs 150 crore for 150,000 tonnes of annual capacity.
- Management expects to acquire roughly 75 to 80 acres in Raipur, compared with 16 acres at Hisar.
- Jindal Supreme said Raipur could serve about 11 to 12 states and phase two would follow 50% utilisation.
powered by IRIS

Jindal Supreme (India) Limited is targeting production from a Raipur greenfield plant by March 2028, with about Rs 150 crore allocated to a first phase designed for 150,000 tonnes of annual capacity. Management said the Chhattisgarh project would add a second manufacturing location beyond Hisar and introduce larger pipe sizes.
Know Jindal Supreme (India) inside out
Results, valuation, peers and who's buying, in one view.
When will Jindal Supreme's Raipur plant begin production?
Jindal Supreme is targeting commercial production at Raipur by March 2028. Management said it was in advanced stages of acquiring roughly 75 to 80 acres in Chhattisgarh, with due diligence under way and the land transaction expected to close in quarter 4. It also said a facility of this type takes about one year to set up, making the March 2028 date a management target rather than a completed milestone.
The planned Raipur site is substantially larger than Jindal Supreme's Hisar location. Management compared the proposed 75-to-80-acre Raipur plot with 16 acres at Hisar and said the full site could be almost four times larger. It described the location as Raipur, Chhattisgarh, after initially referring to land acquisition in eastern India.
Management did not provide a schedule for the complete Rs 600 crore potential build-out or disclose its eventual capacity. The first phase, however, has a specified 150,000-tonne annual capacity, which creates a separate manufacturing platform rather than another line within the existing Hisar plant.
How will Jindal Supreme fund the Raipur expansion?
Jindal Supreme expects to finance the roughly Rs 150 crore first phase through internal accruals and debt. Management indicated that the mix could be approximately 50-50 and said it had no plans for further equity dilution at the time of the call. This funding outline was stated for phase 1, not for the entire Rs 600 crore site potential.
The company had already deployed about Rs 72 crore of its initial public offering proceeds towards debt repayment, out of proceeds management described as about Rs 100 crore. Management nevertheless said Raipur would require some new debt alongside internal cash generation. The transcript does not disclose proposed lenders, interest rates, repayment terms or the amount of borrowing for later phases.
Working capital remains relevant to the internal-accrual component of the plan. Management said inventory was increased to benefit from higher steel prices and receivables rose to Rs 42 crore from Rs 33 crore a year earlier, which it identified as reasons for negative first-half operating cash flow of about Rs 6 crore to Rs 7 crore. It said the target for net working-capital days was 45 to 50 days, against 64 days raised by an analyst.
What capacity and products will Jindal Supreme add at Raipur?
Jindal Supreme plans 150,000 tonnes per annum of phase-one capacity at Raipur. Management said about half the product range would resemble products made at Hisar, while the other half would comprise pipes with different sizes and thicknesses, including larger diameters not currently produced there. It did not identify individual product categories or give a capacity split by pipe type.
The Raipur proposal follows capacity work at Hisar. Management put Hisar capacity at 171,000 tonnes at the time of the call and said new additions would take it to about 200,000 tonnes by the end of financial year 2027. It also said the company expects output of about 170,000 to 180,000 tonnes in the next financial year, based on monthly production of 15,000 to 16,000 tonnes.
Hisar's additions include a fifth galvanising line with 24,000 tonnes of annual capacity, expected in quarter 2 of the next financial year after roughly nine months of implementation. A separate 18,000-tonne annual galvanising line for crash barriers started commercial production at the end of October and was expected to provide additional quantities by December. Management also expects nut-and-bolt manufacturing to begin in quarter 4 of the current financial year, although it said this product has lower tonnage and higher value addition.
Got a follow-up? Ask IRIS
How could Raipur change Jindal Supreme's market reach?
Jindal Supreme said Raipur could serve about 11 to 12 states, compared with the mainly northern reach of Hisar. The Hisar facility supplies Delhi National Capital Region, Rajasthan, Punjab, Himachal Pradesh, and Jammu and Kashmir, while some crash barriers and galvanised iron pipes reach Maharashtra, Gujarat and Madhya Pradesh. Management said Raipur would have a lower inbound freight component for steel and lower outward freight than Hisar.
The company did not quantify freight savings per tonne, forecast Raipur revenue by state, or disclose customer commitments for the new facility. Its assertion about serving 11 to 12 states is therefore a management view based on the proposed location. Commercial outcomes will depend on land acquisition, construction, commissioning, product acceptance and the pace at which the plant is utilised after March 2028.
Jindal Supreme's current channels combine dealers and direct customers. Management said dealers account for about 20% of revenue, while the remainder includes engineering, procurement and construction companies, crash-barrier contractors and other pipe customers. Crash barriers are sold on 100% advance payment, poles sold to engineering, procurement and construction companies are backed by letters of credit, and management put debtor days at about 12 to 13 days.
What will trigger Jindal Supreme's second Raipur phase?
Jindal Supreme plans to begin a second Raipur phase when the first phase reaches about 50% capacity utilisation. Management said the later expansion would add capacity for different products because the pipe industry encompasses a wide range of specifications. It did not specify the capital amount, capacity addition or timing that would follow the 50% trigger.
That threshold differs from management's utilisation expectations for the existing business. Overall utilisation was about 65% at the time of the call, and management expected about 70% in quarter 3, 75% in quarter 4 and about 80% in quarter 1, which it described as the industry’s optimum level. These expectations relate to the current operations and do not establish how quickly the Raipur facility will reach 50% utilisation.
Management also described financial year 2027 sales as seasonally weighted towards the second half, with a 40% first-half and 60% second-half split. It guided for full-year revenue of about Rs 850 crore to Rs 900 crore and earnings before interest, tax, depreciation and amortisation of about Rs 60 crore. The nearer-term outlook rests on Hisar capacity additions, whereas Raipur is scheduled to start production in March 2028.
Conclusion
Jindal Supreme has outlined a defined Raipur expansion: about Rs 150 crore for 150,000 tonnes of first-phase annual capacity, funded through internal accruals and debt and targeted for production by March 2028. The 75-to-80-acre site would move manufacturing beyond the 16-acre Hisar facility, while adding a mix of existing pipe products and larger or different specifications.
The next disclosed event is the expected quarter-4 close of the Raipur land acquisition. Management’s subsequent execution markers include the December ramp-up of the 18,000-tonne crash-barrier galvanising line, quarter-4 nut-and-bolt commissioning, and a second Raipur phase only after the first phase reaches about 50% utilisation.