KNR completes Rs 1,557.4 crore four-SPV sale to Indus Infra
Key highlights
- KNR completed divestment of four SPVs to Indus Infra Trust for Rs 1,557.4 crore on 5 October 2026.
- The four sold SPVs had Rs 566.1 crore of total equity to be invested, with listed consideration multiples of 2.4 to 4.6 times.
- Marripudi to Somvarappadu was 93.9% complete, while Mysore to Kushalnagara Packages V and IV were 24.6% and 28.8% complete.
- KNR's order book stood at Rs 11,708.8 crore on 30 September 2026, with HAM roads accounting for 9%.
powered by IRIS

KNR completed the divestment of four special purpose vehicles, or SPVs, to Indus Infra Trust for Rs 1,557.4 crore by 5 October 2026, against Rs 566.1 crore of total equity to be invested. The four transfers were accounted across Q1FY27 to Q3FY27, while KNR retained four hybrid annuity model, or HAM, projects at differing construction and funding stages.
Know KNR Constructions inside out
Results, valuation, peers and who's buying, in one view.
What did KNR sell to Indus Infra Trust?
KNR sold four SPVs under share purchase agreements executed with Indus Infra Trust on 24 December 2025. The agreements covered the proposed sale of KNR's 100% shareholding, including subordinated debt, in KNR Palani Infra Pvt Ltd, KNR Ramagiri Infra Pvt Ltd, KNR Guruvayur Infra Pvt Ltd and KNR Ramanattukara Infra Pvt Ltd.
The presentation states that divestment of all four assets was completed on 5 October 2026. Total consideration was Rs 1,557.4 crore against Rs 566.1 crore of total equity to be invested, while the listed consideration multiples ranged from 2.4 times to 4.6 times across the individual SPVs.
The total consideration equates to about 2.75 times the stated total equity amount, based on the Rs 1,557.4 crore and Rs 566.1 crore figures disclosed by KNR. This is a calculation from the presentation figures, rather than a transaction multiple stated by management.
When did KNR account for the sale consideration?
KNR accounted for Rs 522.4 crore of consideration in Q1FY27 from the first two SPV transfers. KNR Palani Infra Pvt Ltd transferred on 29 May 2026 for Rs 295 crore, followed by KNR Ramagiri Infra Pvt Ltd on 11 June 2026 for Rs 227.4 crore.
KNR accounted for Rs 485.9 crore from KNR Guruvayur Infra Pvt Ltd in Q2FY27 after its 17 September 2026 transfer. The final transfer, KNR Ramanattukara Infra Pvt Ltd, occurred on 5 October 2026 and contributed Rs 549.1 crore accounted in Q3FY27.
The Q3FY27 transfer was the largest of the four by consideration, at Rs 549.1 crore, but carried the lowest listed multiple at 2.4 times equity. In contrast, the Q1FY27 Palani transaction carried the highest multiple, 4.6 times, despite its Rs 295 crore consideration being the second-smallest amount among the four SPVs.
How did the four KNR SPV transaction terms differ?
KNR Palani Infra Pvt Ltd had Rs 64.4 crore of total equity to be invested and Rs 295 crore of consideration at a stated 4.6 times multiple. KNR also says Rs 90 crore of cash surplus from this SPV was upstreamed to KNR as engineering, procurement and construction, or EPC, claims.
KNR Ramagiri Infra Pvt Ltd had Rs 82.7 crore of equity to be invested, Rs 227.4 crore of consideration and a 2.7 times listed multiple. KNR Guruvayur Infra Pvt Ltd had a larger Rs 193.3 crore equity amount and Rs 485.9 crore consideration at 2.5 times, placing it between Ramagiri and Ramanattukara on the disclosed multiple scale.
KNR Ramanattukara Infra Pvt Ltd had the largest stated equity amount, Rs 225.7 crore, and the largest consideration, Rs 549.1 crore. Its 2.4 times listed multiple was 2.2 times lower than Palani's 4.6 times, showing that consideration size and the reported consideration-to-equity multiple did not move together across the four transfers.
Got a follow-up? Ask IRIS
Which HAM projects remain in KNR's portfolio?
KNR's HAM portfolio lists four 100%-owned SPVs: KNR Somwarpet Infra Pvt. Ltd., KNR Ramatheertham Infra Pvt. Ltd., KNR Sriranganatha Infra Pvt. Ltd. and KNR Kaveri Infra Pvt. Ltd. Their projects are in Karnataka and Andhra Pradesh, with total project costs from Rs 738.73 crore for Mysore to Kushalnagara Package IV to Rs 1,127.6 crore for Magadi-Somwarpet.
Magadi-Somwarpet, a 166-kilometre Karnataka project for Karnataka State Highway Improvement Project, or KSHIP, was 91.5% physically complete and had a provisional commercial operation date, or PCOD, of 27 June 2023. It reported Rs 123.26 crore of equity invested, Rs 748.5 crore of grant received and Rs 218.7 crore of debt drawn.
Marripudi to Somvarappadu in Andhra Pradesh was 93.9% physically complete, exceeding Magadi-Somwarpet's 91.5% by 2.4 percentage points. The 29.1-kilometre National Highways Authority of India, or NHAI, project had an appointed date of 10 February 2024, Rs 69.28 crore of equity invested, Rs 297.24 crore of grant received and Rs 219.5 crore of debt already drawn; its PCOD or commercial operation date field was blank.
How far advanced are KNR's Mysore HAM projects?
KNR Sriranganatha Infra Pvt. Ltd.'s Mysore to Kushalnagara Package V was 24.6% physically complete, with an appointed date of 7 April 2025. The 83.4-kilometre NHAI project had estimated equity of Rs 89.5 crore and estimated debt of Rs 357.99 crore, but reported Rs 0.1 crore of equity invested and no debt drawn.
KNR Kaveri Infra Pvt. Ltd.'s Package IV was 28.8% complete, 4.2 percentage points ahead of Package V, and had an appointed date of 30 April 2025. The 26.6-kilometre NHAI project reported estimated equity of Rs 81.72 crore and estimated debt of Rs 326.85 crore, with Rs 0.1 crore of equity invested and nil debt already drawn.
The two Mysore projects were also part of KNR's order book as of 30 September 2026. Package V had Rs 473 crore of order-book value and Package IV had Rs 409.7 crore, together representing Rs 882.7 crore of KNR's Rs 11,708.8 crore total order book; the presentation assigns 9% of that order book to HAM roads and 59% to mining.
Conclusion
KNR's four-SPV monetisation was completed through transfers from May to October 2026, producing Rs 1,557.4 crore of disclosed consideration against Rs 566.1 crore of total equity to be invested. Its retained HAM portfolio is at sharply different stages, from 91.5% and 93.9% physical progress for Magadi-Somwarpet and Marripudi to Somvarappadu to 24.6% and 28.8% for the two Mysore packages.
The next disclosed matters to watch are construction progress, funding drawdowns and PCOD or commercial operation dates for the three projects whose PCOD or commercial operation date fields remain blank. KNR provides no target completion dates for those projects, while its 30 September 2026 order book includes Rs 882.7 crore for the two Mysore HAM packages.