KNR Plans ₹1,000 Crore Mine Capex With 5% Profit
Key highlights
- KNR envisages about ₹1,000 crore across Kusmunda and Banhardih, or about ₹500 crore per mine.
- Management expects 5% profit from KNR's mining projects.
- KNR spent ₹180 crore on mining assets within total six-month capital expenditure of ₹220 crore.
- KNR targets about ₹400 crore of FY28 turnover from Kusmunda, while Banhardih could add ₹300 crore if it starts in the first quarter.
powered by IRIS

KNR envisages about ₹1,000 crore of capital expenditure for the Kusmunda and Banhardih mines, or about ₹500 crore each, while management expects 5% profit from the mining projects. The investment programme depends on equipment deployment at Kusmunda and land handover, mobilisation and a start date for Banhardih.
Know KNR Constructions inside out
Results, valuation, peers and who's buying, in one view.
How much will KNR spend on its two mines?
KNR expects the two mines to require about ₹1,000 crore of investment, with management putting the requirement at about ₹500 crore for Kusmunda and another ₹500 crore for Banhardih. Management said the Banhardih investment would be needed if that mine starts, and linked the requirement to completing the work over five years.
Kusmunda had already absorbed about ₹370 crore to ₹380 crore of spending at the time of the call. Management said a further ₹60 crore to ₹70 crore could be needed there, alongside another ₹120 crore for items including electric vehicles, taking Kusmunda's investment close to ₹500 crore. Banhardih would require an additional ₹400 crore to ₹500 crore if operations begin.
Mining was already the principal use of near-term capital expenditure. KNR said ₹180 crore of the ₹220 crore spent in the six months related to mining assets, while ₹40 crore related to road and other assets. For the full year, management expects ₹300 crore to ₹320 crore of ₹400 crore total capital expenditure to go to mining, with the remaining amount for road assets.
What profit does KNR expect from the mining projects?
KNR expects 5% profit from the mining projects, according to management, which said the projects were bid in a competitive environment. Management added that development-stage bills would be effectively hand-to-mouth, indicating that the initial phase may have limited surplus despite the equipment investment.
The turnover goals are larger than the stated profit expectation. KNR wants Kusmunda to reach about ₹400 crore of turnover in FY28. Management said Banhardih could add another ₹300 crore if it starts in the first quarter of FY28, although the mine would initially need development and mobilisation. These conditional targets point to up to ₹700 crore of FY28 mining turnover.
Management gave two different descriptions of mining activity during the call. In one response, it said mining revenue had not yet been recorded in the balance sheet because the mining project had not started. In another response, it referred to turnover of about ₹17 crore in the preceding October and a ₹20 crore target for the current month, without giving a reconciled segmental revenue figure.
Got a follow-up? Ask IRIS
How could mine capex affect KNR's depreciation and funding?
KNR's growing mining equipment base is expected to raise depreciation, although management did not give a final depreciation forecast for the full ₹1,000 crore programme. An analyst said depreciation had risen from ₹10 crore in the first quarter to about ₹19 crore in the second quarter because of mining capital expenditure; management then discussed the useful life assumed for mine equipment.
Management said its bid calculations used a five-year depreciation assumption because mining equipment may run for nearly 20 hours a day. It described the five-year estimate as conservative in the context of the equipment's operating cycle, while another executive said a six- to seven-year assumption could be used. KNR did not confirm the accounting life it will ultimately apply to the assets.
Mine capital expenditure is not the only intended use of proceeds from asset monetisation. KNR said those proceeds would support mine spending as well as equity investment in hybrid annuity model, or HAM, projects. Separately, it reported ₹295 crore of withheld amounts on three monetised assets and said about ₹130 crore would be withheld on a fourth asset, whose accounting was expected in the third quarter.
When could KNR begin Banhardih and scale mining revenue?
KNR said Banhardih could start in four to five months, but management did not provide a firm commencement date. It said there was high-level follow-up and court importance around the start, while making clear that the timing remained uncertain. The mine's potential ₹400 crore to ₹500 crore capital requirement therefore remains conditional on commencement.
Land handover is central to the start timetable because KNR has not mobilised for Banhardih. Management said it did not want to keep equipment idle while waiting for land, and said manufacturers were taking considerable time to supply machinery because equipment was being made against orders. A delay could therefore affect both the planned capital deployment and the conditional ₹300 crore FY28 turnover target.
Mining is material within KNR's wider order book. The company cited an almost ₹16,000 crore order book, including at least ₹6,800 crore for mining, compared with almost ₹10,000 crore excluding mining. It also said ₹3,300 crore represented its portion of a mining project after royalty, while KNR would execute the entire work through a back-to-back arrangement with its joint-venture partner.
Conclusion
The disclosures show mining becoming a larger capital-allocation area for KNR, with ₹180 crore of the ₹220 crore spent in the six months directed to mining assets. The expected 5% project profit means the outcome will depend on meeting the turnover targets, controlling equipment and mobilisation costs, and converting the investment into operating activity.
The next disclosed milestones are a possible Banhardih start within four to five months, land handover before mobilisation, and progress toward Kusmunda's ₹400 crore FY28 turnover target. KNR also plans to use monetisation proceeds for both mine capital expenditure and HAM equity, while ₹295 crore remains withheld on three monetised assets and about ₹130 crore is expected to be withheld on a fourth.