Lodha gains 5 GW approval, targets BTS signing this year
Key highlights
- Lodha has approvals for 5 GW of data-centre input power, up from 3 GW.
- Lodha expects definitive documents for a multi-hundred-megawatt BTS deal in FY ’27.
- Lodha targets BTS sign-ups of 1 GW by FY ’30 and delivery by FY ’32.
- Lodha expects a Q4 FY ’27 data-centre land transaction worth about Rs 1,500 crore.
powered by IRIS

Lodha Developers Limited has received approvals for 5 gigawatts (GW) of input power at its data-centre park, up from 3 GW, and expects to sign definitive documents for a multi-hundred-megawatt build-to-suit (BTS) deal in FY ’27. Management said the expanded power availability uses the transmission ecosystem around the site and requires no significant network upgrade.
Know Lodha Developers inside out
Results, valuation, peers and who's buying, in one view.
Why did Lodha receive approval for 5 GW at its data-centre park?
Lodha received the 5 GW approval from the concerned authorities based on transmission capacity available in and around the site. The approved input-power availability has risen by 2 GW from the earlier 3 GW level, while management said this scale does not require a significant upgrade to the existing transmission network.
Lodha is building substations at its own cost to tap into that transmission network, and said work is under way. Management estimated that 5 GW of input power would translate into a little more than 4 GW of information-technology output, after allowing for the infrastructure required to operate the campus.
The approval expands the potential scale of the campus, but it is not itself a change to Lodha’s disclosed rental guidance. Management said it would provide a clearer view of the larger land-sale and BTS opportunity after the first BTS agreement is signed.
When will Lodha sign its first BTS data-centre deal?
Lodha expects definitive documents for its first BTS transaction to be signed in FY ’27, with construction beginning in the same fiscal year. Management plans to deliver the buildings in FY ’29, when rent would commence, and described the transaction as a multi-hundred-megawatt project without disclosing a precise size because it remains confidential.
A BTS arrangement would involve Lodha constructing facilities for a customer rather than only selling a plot within the park. Management reaffirmed its target to sign up 1 GW of input power under BTS arrangements by FY ’30 and deliver that capacity by FY ’32, while saying it remains positive on achieving, and potentially exceeding, that goal.
The campus already has three companies building facilities: AWS, STT and Digital Edge. Management said those occupiers are seeing demand from large corporates, are seeking additional land, and are joined by other companies that are considering land purchases in the park.
What rental guidance has Lodha given for BTS capacity?
Lodha has kept its guidance unchanged at annual BTS rentals of Rs 2,000 crore to Rs 2,300 crore for 1 GW of input power. Management said that range remains applicable despite the increase in approved campus power from 3 GW to 5 GW.
Management described the Rs 2,000 crore annual-rental estimate as conservative and said it expects the figure to rise over time, but did not change the guidance. The current estimate applies to the 1 GW BTS target, not to the entire 5 GW campus approval, which includes capacity that could also support land sales.
The distinction is material because the 5 GW approval increases the potential infrastructure envelope, while commercial conversion depends on BTS contracts, tenant construction and land transactions. Lodha said it would articulate the full-scale opportunity after executing its first BTS agreement rather than setting a revised long-term rental target now.
Got a follow-up? Ask IRIS
What data-centre land sale does Lodha expect next?
Lodha expects at least one data-centre land transaction in the fourth quarter of FY ’27, valued at about Rs 1,500 crore. Management said it then aims to complete one land transaction every six months, making such sales a recurring and more predictable part of its overall sales mix.
The expected next transaction is likely to be priced in the high-Rs 50 crore-per-acre range. That would be above the Rs 42 crore per acre achieved in the prior transaction, although it would remain below Lodha’s earlier view that fair market value could reach around Rs 65 crore per acre over an 18-month period.
The comparison shows management expects a step-up from the earlier Rs 42 crore-per-acre deal. However, the Rs 65 crore-per-acre figure remains management’s fair-market-value view rather than an achieved sale price, and the Q4 FY ’27 transaction remains subject to completion.
How will Lodha manage water and renewable-power use?
Lodha said its data centres are designed to use almost entirely recycled water, resulting in almost no fresh-water use. Management said Mumbai generates about 4,000 million litres per day of wastewater, much of which has historically been discharged into the sea, and that this recycled water is intended to meet the park’s water requirement.
Lodha has also undertaken that at least 51% of the power used at the data-centre park will be renewable. Management said it hopes the renewable share will increase as renewable generation, battery storage and pumped storage expand, but it did not give a date or a target above 51%.
Management acknowledged concerns about water, sound and other environmental effects associated with data centres. Its stated response is to communicate the use of recycled water, the renewable-power commitment, job creation and the site’s economic role, while recognising that public discussion may include inaccurate claims or competing interests.
Conclusion
Lodha’s approval for 5 GW of input power raises the potential scale of its data-centre park by 2 GW from the earlier 3 GW position. The strategy now combines three existing occupiers, a planned multi-hundred-megawatt BTS facility, annual BTS-rental guidance of Rs 2,000 crore to Rs 2,300 crore for 1 GW, and an expected Rs 1,500 crore land transaction in Q4 FY ’27.
The next disclosed milestones are definitive BTS documents and construction in FY ’27, delivery and rent commencement in FY ’29, and the target to sign up 1 GW of BTS input power by FY ’30. Investors will also watch whether the expected Q4 FY ’27 land sale closes in the high-Rs 50 crore-per-acre range and whether management updates its broader 5 GW commercial outlook after the first BTS deal is signed.