NLC India Incorporates 50:50 NALCO 1,080 MW Captive Power JV
Key highlights
- NLC India and NALCO incorporated NLC NALCO Power Private Limited on November 23, 2026.
- NLC India and NALCO will each hold a 50% stake in the joint venture.
- The venture is planned to develop a 1,080 MW thermal plant comprising four 270 MW units.
- The proposed plant is intended to support NALCO's 0.5 MTPA aluminium smelter expansion at Angul.
powered by IRIS

NLC India Limited has incorporated NLC NALCO Power Private Limited, a 50:50 joint venture with National Aluminium Company Limited, to develop a 1,080 MW thermal captive power plant at Angul, Odisha. The project vehicle will develop four 270 MW units to support NALCO's additional captive power requirement for its planned aluminium smelter expansion.
Know NLC India inside out
Results, valuation, peers and who's buying, in one view.
What did NLC India incorporate with NALCO?
NLC India incorporated NLC NALCO Power Private Limited with NALCO as an equal equity partner for the proposed thermal captive power project in Angul. The company was incorporated on November 23, 2026, when the Registrar of Companies issued its Certificate of Incorporation.
The new entity formalises the project structure for a plant with total planned capacity of 1,080 MW. The plant is proposed to comprise four generating units of 270 MW each and is intended to be developed in phases. NALCO and NLC India will each hold a 50% stake in the joint venture.
NALCO subscribed to 25,000 equity shares in the new company at a face value of Rs. 10 per share for its 50% holding. The available disclosures state that the two public sector companies will have equal ownership and representation in the project company.
The incorporation follows the joint venture agreement signed by NALCO and NLC India on July 8, 2026. NLC India's board subsequently approved the formation of the 50:50 venture in September 2026 after the Ministry of Coal conveyed approval for the proposal from the Department of Investment and Public Asset Management.
Why is the Angul power plant being planned?
The Angul power plant is being planned to meet NALCO's additional captive electricity requirement for its proposed 0.5 million tonnes per annum aluminium smelter expansion. Aluminium smelting requires large and continuous electricity supplies, making captive power availability an important operating requirement for a smelter expansion.
The 1,080 MW proposed capacity is close to the approximately 1,100 MW additional power requirement previously indicated for the expansion. The project is planned within NALCO's existing captive power complex at Angul, according to the available project details.
NALCO is expected to receive 100% of the electricity generated by the project through a proposed 25-year power purchase agreement. The power purchase arrangement remains proposed, and the project is subject to statutory, administrative and other applicable approvals.
Got a follow-up? Ask IRIS
How did the joint venture proposal progress?
The proposal progressed from an initial non-binding memorandum of understanding to a signed joint venture agreement and then to incorporation of the project company. NALCO and NLC India signed the joint venture-cum-shareholders' agreement on July 8, 2026.
NLC India's board considered and approved incorporation of the joint venture at its September 29, 2026 meeting. Its disclosure said the venture would develop the 1,080 MW thermal captive power plant in phases to meet NALCO's power needs.
The board approval followed communication from the Ministry of Coal regarding approval from the Department of Investment and Public Asset Management. NLC India's filing also referred to compliance with applicable DIPAM guidelines and the need for relevant statutory and administrative approvals.
The incorporation is therefore a corporate-structure milestone rather than evidence that construction has begun. The disclosed information establishes the company that is intended to undertake the project, while project execution will depend on the approvals and arrangements specified in the companies' disclosures.
What does the incorporation mean for NLC India and NALCO?
The incorporation gives NLC India and NALCO a jointly owned vehicle to pursue the captive power project with defined 50:50 ownership. For NALCO, the venture is linked to securing power for a planned increase in aluminium smelting capacity at Angul.
For NLC India, the venture creates an equal partnership in a proposed thermal generation project with captive demand identified by NALCO. The disclosed plan also provides for NALCO to be the intended offtaker of the plant's generation under a proposed long-term power purchase agreement.
The announcement may keep both companies in investor focus because it connects their operations through a large proposed power project. However, the disclosure does not provide project cost, financing details, a construction schedule, commissioning dates or expected financial contribution from the venture.
The development also illustrates how captive generation remains relevant to energy-intensive industrial projects. For an aluminium producer, a dedicated power arrangement can be central to planning production expansion, while the eventual operating and financial implications will depend on the project moving through approvals, execution and commissioning.
Conclusion
NLC India has incorporated a 50:50 joint venture with NALCO to develop a 1,080 MW thermal captive power plant at Angul. The incorporation creates the formal project vehicle for four proposed 270 MW units, with the plant intended to support NALCO's planned 0.5 MTPA aluminium smelter expansion.
The next disclosures to watch are the status of statutory and administrative approvals, the proposed 25-year power purchase agreement, project cost and financing arrangements, and the development schedule. These details will determine how and when the incorporated joint venture moves from a corporate entity to project execution.