Park Hotels targets 2030 opening for Rs 150 crore Vizag hotel
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Park Hotels plans to spend Rs 150 crore on a 100-room ultra-luxury beach hotel in Visakhapatnam.
- Park Hotels targets a second-half 2030 opening after saying construction could start within 7 to 10 days of November 17, 2026.
- The Andhra Pradesh MoU could provide Rs 10 crore to Rs 20 crore or more in savings through a capital subsidy and SGST refunds.
- Park Hotels expects about Rs 100 crore of second-half FY27 capital expenditure, including initial spending on Vizag and the Juhu hotel.
powered by IRIS

Apeejay Surrendra Park Hotels Limited plans to open a Rs 150 crore, 100-room ultra-luxury beach hotel in Visakhapatnam in the second half of 2030. Park Hotels said on November 17, 2026 that all permissions were in place, construction was due to start within 7 to 10 days, and Andhra Pradesh incentives could save Rs 10 crore to Rs 20 crore or more.
Know Apeejay Surrendra Park Hotels inside out
Results, valuation, peers and who's buying, in one view.
What is Park Hotels building in Visakhapatnam?
Park Hotels is building a 100-room ultra-luxury hotel at the site of its existing Visakhapatnam property for Rs 150 crore. Management said every room will face the beach and include a balcony, with facilities it described as world-class. The project accounts for the 100 owned keys under development in Vizag.
The new development is beside Park Hotels' existing 65-room Visakhapatnam hotel, which management said opened in 1968 as Andhra Pradesh's first five-star hotel. The 100-room addition will therefore exceed the existing hotel's room count by 35 keys, or about 54%, at a site where Park Hotels already operates.
When will Park Hotels start construction and open the Vizag hotel?
Park Hotels expects construction to begin within 7 to 10 days of its November 17, 2026 earnings call and targets an opening around the same period in the second half of 2030. Management said it had secured all permissions and paid the Greater Visakhapatnam Municipal Corporation, or GVMC, fees that represented the final approval needed to start work.
Vizag is one of more than 400 owned keys under development at the end of the first half of FY27. The wider pipeline includes about 220 keys in Kolkata, about 80 keys in Juhu, Mumbai, and 100 keys in Vizag, showing that Vizag represents about one-quarter of the disclosed owned-key pipeline.
The opening date remains a management target rather than a completed-project milestone. Atul Khosla, Park Hotels' Senior Vice President, said the second half of FY27 would include initial capital expenditure for Vizag, while the larger project is scheduled to open in 2030.
How could Andhra Pradesh incentives reduce Park Hotels' Vizag cost?
Park Hotels said its memorandum of understanding with the Andhra Pradesh government could deliver Rs 10 crore to Rs 20 crore or more of savings over the project's five-year period. Management identified two mechanisms: a capital subsidy and a State Goods and Services Tax, or SGST, refund.
The company said the capital subsidy is capped at Rs 10 crore for hotels with project costs above Rs 100 crore. The Rs 150 crore Vizag project exceeds that threshold, while the SGST refund could run for five to seven years and add to the eventual benefit.
Park Hotels did not disclose a final approved subsidy amount or revise its Rs 150 crore project-cost estimate. The stated saving range is therefore management's expectation under the MoU, dependent on the application of the capital-subsidy and SGST-refund provisions.
Got a follow-up? Ask IRIS
How does the Vizag project fit Park Hotels' capital plan?
Park Hotels expects about Rs 100 crore of capital expenditure in the second half of FY27, including spending on the Juhu hotel and the initial Vizag outlay. Khosla said overall capital expenditure for FY28, covering Vizag, Juhu and operating requirements, would be about Rs 150 crore to Rs 200 crore.
Apartment sales from Park Hotels' EM Bypass mixed-use project are expected to fund that development and other capital expenditure. Management said nearly 100% of launched inventory in the 69-service-apartment project was sold at an average Rs 19,500 per square foot, and it expects Rs 325 crore as its share of sales over three years, of which Rs 38.5 crore had been received.
The capital programme follows acquisitions that lifted gross borrowings from Rs 150 crore to Rs 300 crore. Management attributed the increase partly to Rs 188 crore paid for about a 90% stake in Zillion Hotels in Juhu and about Rs 21 crore for Purity at Vembanad Lake, while saying it held about Rs 100 crore of mutual-fund investments.
Park Hotels had 43 hotels and 2,729 keys at the end of H1 FY27 and aims to reach 100 hotels and 7,500 keys by FY31. Management plans to add 57 hotels with 4,771 keys over six years, principally through managed properties, while the 100-key Vizag project remains an owned development.
Conclusion
The Vizag project adds a larger second hotel to a Park Hotels location that has operated since 1968. The Rs 150 crore investment combines 100 beach-facing rooms with a possible Rs 10 crore to Rs 20 crore or more in government-linked savings, though the company has not disclosed the final incentive award or a revised net development cost.
The next disclosed markers are the start of work after the GVMC approval, initial spending within the Rs 100 crore second-half FY27 capital-expenditure plan, and progress toward the second-half 2030 opening target. Park Hotels' delivery of the capital subsidy and five-to-seven-year SGST refund will determine whether the savings range outlined by management is realised.