Phoenix Mills maps CY2027-30 openings as Kolkata reaches 90% leased
Key highlights
- Phoenix Mills targets CY2030 operations for Thane, Chandigarh and Coimbatore.
- Kolkata mall is 90% leased, versus 70% for the Bengaluru expansion and 50% for Surat.
- Rise mall retail is planned to open in CY2027, while Rise offices are targeted for 2028.
- Phoenix Mills expects about 4 lakh square feet of first-phase Bengaluru offices by CY2030.
powered by IRIS

The Phoenix Mills Limited has mapped retail, office and hotel additions from CY2027 to CY2030, with its Kolkata mall 90% leased before tenant fit-outs planned around Q2. Phoenix Mills targets operations at Thane, Chandigarh and Coimbatore in CY2030, while the Kolkata residential project is expected to start in about two quarters after approval delays.
Know Phoenix Mills inside out
Results, valuation, peers and who's buying, in one view.
When will Phoenix Mills open its next malls?
Phoenix Mills expects the Rise mall retail component to open in CY2027, while the Kolkata mall is expected to start tenant fit-outs around Q2 and launch about six months later. Management also expects the Bengaluru retail expansion to complete by 2027, creating a nearer-term sequence of retail additions before the larger CY2030 projects.
Surat is expected to complete in 2027 and open in 2028, according to management. Phoenix Mills also identified Kolkata, Surat and the Lower Parel expansion as assets likely to come into operations in FY28-FY29, while the Bengaluru expansion is expected to add about 1 lakh to 1.5 lakh square feet.
Phoenix Mills targets CY2030 operations for its Thane, Chandigarh and Coimbatore projects. Management said the CY2030 target allows room for regulatory approvals and for retailers to complete fit-outs, meaning the date is an expectation rather than a fixed commissioning commitment.
How far has Phoenix Mills leased its upcoming malls?
Phoenix Mills has leased 90% of Kolkata, 70% of the Bengaluru expansion, 60% of Rise and 50% of Surat. Kolkata is therefore 40 percentage points ahead of Surat, the lowest disclosed leasing level among these four projects, while management said it has a long pipeline of brands for each centre.
Rise 1 is planned to add about 150 stores, and management said about 50% of its brands will be new to the block. The store mix will combine relocations with new brands, while management expects rentals above Rs 500 per square metre per month for Rise 1, higher than the existing rent for the Palladium complex overall.
The disclosed leasing levels mark progress ahead of opening but do not remove the remaining execution steps. Kolkata requires tenant fit-outs before launch, while Surat has 50% of its space still to be leased based on the call disclosure; Phoenix Mills gave no percentages for Coimbatore, Chandigarh or Thane despite saying leasing was progressing well.
Got a follow-up? Ask IRIS
When will Phoenix Mills add offices and hotels?
Phoenix Mills expects the first phase of its Bengaluru offices, covering about 4 lakh square feet, and the Grand Hyatt Bangalore hotel to become operational by CY2030. Management discussed both projects alongside the CY2030 target for Thane, Chandigarh and Coimbatore, linking retail, office and hospitality development in its longer-dated pipeline.
Rise offices are targeted for completion during 2028, following the planned CY2027 opening of the Rise mall. Management confirmed that the mall would open before the office portion, placing the commercial component about a year after the retail launch target.
For its overall office portfolio, Phoenix Mills said 79% was leased and 54% was rent-generating at the time of the call. Management expects rent-generating occupancy to reach 70% by March and 80% by June or July of the following year, although those figures apply to the overall office portfolio rather than only Bengaluru and Rise.
Why has Phoenix Mills delayed its Kolkata residential launch?
Phoenix Mills expects its Kolkata residential project to start in about two quarters after a redesign to a pure-residential development and a longer approval process. Management said elections and other factors extended the approval timeline beyond its expectations, and said progress could be visible in subsequent investor calls.
An analyst noted that more than three and a half years had passed since the land parcel was acquired, against the one to one-and-a-half-year turnaround the company described as normal from land acquisition to residential launch. Management did not provide a more specific launch date than an expected start in about two quarters.
The residential timetable is separate from the Kolkata mall schedule. Management said incremental land acquired near the Kolkata site would improve the arrival experience and broaden frontage on Diamond Harbour Road, but would not affect mall commencement timelines; the residential approval process remains the unresolved timing factor.
Conclusion
Phoenix Mills has set out a staged pipeline, with Rise retail planned for CY2027, Surat targeted to open in 2028, Rise offices targeted for 2028, and Thane, Chandigarh and Coimbatore expected to operate in CY2030. Kolkata’s 90% leased status is the most advanced disclosed leasing milestone, compared with 70% for the Bengaluru expansion, 60% for Rise and 50% for Surat.
The next milestones are Kolkata tenant fit-outs around Q2 and the expected launch roughly six months later, the CY2027 opening of Rise retail, and the residential project’s anticipated start in about two quarters. Management’s CY2030 targets for Thane, Chandigarh and Coimbatore will depend on regulatory approvals and the time retailers require for fit-outs.