RVNL Q2 profit rises 59% as H1 cash flow turns positive
Key highlights
- RVNL’s Q2 FY27 consolidated PAT rose 59.04% sequentially to Rs 253.7 crore.
- H1 FY27 operating cash flow turned positive at Rs 589 crore from negative Rs 1,250 crore in H1 FY26.
- RVNL’s order book was Rs 90,099 crore on September 30, 2026, including Rs 56,816 crore of railway work.
- Consolidated liquidity increased to Rs 10,181 crore on September 30, 2026 from Rs 9,835.36 crore on March 31, 2026.
powered by IRIS

Rail Vikas Nigam Limited reported consolidated profit after tax of Rs 253.7 crore in Q2 FY27, up 59.04% from Q1 FY27, while H1 FY27 operating cash flow turned positive at Rs 589 crore from a negative Rs 1,250 crore a year earlier. The company’s order book stood at Rs 90,099 crore on September 30, 2026.
Know Rail Vikas Nigam inside out
Results, valuation, peers and who's buying, in one view.
How did RVNL’s Q2 FY27 profit change?
RVNL’s consolidated profit after tax, or PAT, rose 59.04% sequentially to Rs 253.7 crore in Q2 FY27 from Rs 159.52 crore in Q1 FY27. Consolidated profit before tax increased 45.59% to Rs 325 crore from Rs 223 crore, while revenue from operations grew 8.79% quarter on quarter to Rs 4,700 crore.
Earnings before interest, tax, depreciation and amortisation, or EBITDA, increased to Rs 294 crore in Q2 FY27 from Rs 190.78 crore in Q1 FY27, and the margin rose to 6.26% from 4.4%. Consolidated PAT was also 10.06% above Rs 230.52 crore in Q2 FY26, while standalone PAT of Rs 214 crore was 37.94% above Q1 FY27 and 9.46% above Q2 FY26.
Standalone EBITDA was Rs 230 crore in Q2 FY27, compared with Rs 171 crore in Q1 FY27, and its margin increased to 4.94% from 3.99%. Revenue from operations per employee also rose to Rs 10.22 crore from Rs 9.6 crore quarter on quarter, which management attributed to improved utilisation of human resources.
What changed in RVNL’s H1 FY27 cash flow?
RVNL recorded positive cash flow from operating activities of Rs 589 crore in H1 FY27, compared with negative Rs 1,250 crore in H1 FY26, a year-on-year turnaround of Rs 1,839 crore. The transcript did not provide a reconciliation identifying the collection, payment or working-capital items behind the movement.
The cash-flow change accompanied consolidated H1 FY27 PAT of Rs 413 crore, up 13.25% from Rs 364 crore in H1 FY26. Consolidated profit before tax increased 6.43% to Rs 548 crore from Rs 515.8 crore, while total comprehensive income rose 19.28% to Rs 417.53 crore.
Consolidated total liquidity reached Rs 10,181 crore on September 30, 2026, compared with Rs 9,835.36 crore on March 31, 2026. Cash and cash equivalents increased to Rs 691 crore from Rs 556 crore over the same period, while H1 FY27 consolidated revenue from operations was Rs 9,022 crore.
Got a follow-up? Ask IRIS
What does RVNL’s Rs 90,099 crore order book contain?
RVNL’s order book was Rs 90,099 crore as of September 30, 2026, with railways accounting for the largest disclosed component at Rs 56,816 crore. H1 FY27 order inflow was Rs 7,132 crore, against management’s full-year target of around Rs 25,000 crore of work orders in addition to the existing order book.
Building works contributed 33.53% of total H1 FY27 revenue from operations, and management said that contribution was 11% higher than in the previous year. Subsidiaries contributed Rs 56.11 crore to consolidated revenue and Rs 6.36 crore to PAT, while RVNL’s share of profit from joint ventures and associates was Rs 36.59 crore.
The project pipeline includes an Rs 6,504 crore NMDC contract, of which Rs 3,869 crore had been received during H1 FY27. RVNL also cited the Rs 13,236 crore BharatNet project, covering 82,607 kilometres of outside-plant infrastructure under the design-build-operate-maintain model, as a major ongoing assignment.
Can RVNL meet its FY27 growth and execution plans?
Management said it expects FY27 revenue to grow by around 10% and bottom-line profit by approximately 8% to 10%. In a later analyst response, management referred to 10% to 15% top-line growth and about 10% bottom-line growth, while maintaining that execution should improve in Q3 and Q4 after monsoon-related disruption in Q2.
For the second half, management said RVNL will seek to increase execution speed, retain margin discipline and convert lowest-bidder positions and letters of award into active projects. It also said it was bidding for railway, highway and international projects, with ongoing overseas work in the Maldives, Saudi Arabia and Rwanda.
The Rs 14,400 crore Vande Bharat sleeper train-set project, including 35-year maintenance, is being executed by Kinet Railway, an RVNL special purpose vehicle. Management said manufacturing was under way at Latur after approval issues were resolved and expected the first prototype between March and June 2027.
RVNL said the 125-kilometre Rishikesh-Karnaprayag Rail Project was 79% complete, with around 97% of tunnel excavation finished. The Rs 37,119 crore project is targeted for completion by December 2029.
Conclusion
RVNL’s Q2 FY27 recovery combined a 59.04% sequential increase in consolidated PAT to Rs 253.7 crore with a Rs 1,839 crore year-on-year improvement in H1 operating cash flow. The Rs 90,099 crore order book, led by Rs 56,816 crore of railway work, provides the stated execution base, while building works accounted for 33.53% of H1 revenue.
The next disclosures to watch are execution and profitability in Q3 and Q4, when management expects higher activity after the monsoon period, and progress towards its target of around Rs 25,000 crore of FY27 work orders. Other scheduled milestones include the Vande Bharat sleeper prototype expected between March and June 2027 and the December 2029 target for the Rishikesh-Karnaprayag project.