SBI project exposure falls to Rs 76,069 crore in quarter
Key highlights
- SBI’s projects-under-implementation exposure was Rs 76,068.92 crore across 2,049 accounts at September 30, 2026.
- The project balance fell by Rs 3,093.89 crore from Rs 79,162.81 crore at the quarter’s beginning.
- DCCO-extension resolutions covered 372 accounts with Rs 10,457.73 crore outstanding.
- Resolution plans under implementation covered 290 DCCO-extension accounts with Rs 4,929.49 crore outstanding.
powered by IRIS

State Bank of India reported Rs 76,068.92 crore of projects under implementation across 2,049 accounts at September 30, 2026, down from Rs 79,162.81 crore across 2,089 accounts at the quarter’s start. Of the closing balance, Rs 10,457.73 crore in 372 accounts was subject to a resolution process involving an extension of the original or extended DCCO milestone.
Know State Bank of India inside out
Results, valuation, peers and who's buying, in one view.
How much project-finance exposure does SBI have under implementation?
SBI had Rs 76,068.92 crore outstanding in projects under implementation at the end of the quarter ended September 30, 2026. The disclosed balance covered 2,049 accounts and was reported under the Reserve Bank of India’s project-finance disclosure requirements for credit facilities.
The closing exposure was Rs 3,093.89 crore lower than the Rs 79,162.81 crore reported across 2,089 accounts at the beginning of the quarter. The account count declined by 40, reflecting disclosed quarterly sanctions of 71 accounts and 111 accounts that achieved DCCO, or date of commencement of commercial operations.
SBI sanctioned Rs 2,927.68 crore in 71 projects during the quarter, while 111 projects with Rs 6,021.57 crore outstanding achieved DCCO. The Rs 6,021.57 crore that achieved DCCO exceeded new sanctions by Rs 3,093.89 crore, matching the reduction in the reported closing outstanding balance.
How much of SBI’s project exposure involves DCCO extensions?
SBI reported Rs 10,457.73 crore in 372 accounts where a resolution process involving an extension in original or extended DCCO had been invoked at September 30, 2026. This category was part of the Rs 76,068.92 crore closing projects-under-implementation portfolio, rather than a separate portfolio total.
The disclosure separates the 372 accounts by the status of their resolution plans. Resolution plans had been implemented in 77 accounts with Rs 5,460.65 crore outstanding, while 290 accounts carrying Rs 4,929.49 crore were under implementation. Five accounts with Rs 67.59 crore had resolution plans that failed.
The largest number of DCCO-extension cases remained under implementation, at 290 accounts, whereas the largest outstanding amount was in the implemented-plan category, at Rs 5,460.65 crore. Thus, 77 implemented cases carried more outstanding than the 290 cases still under implementation.
What does the DCCO resolution breakdown show?
SBI’s filing shows that Rs 10,390.14 crore of the Rs 10,457.73 crore DCCO-extension resolution exposure was either under an implemented plan or a plan under implementation at September 30, 2026. The remaining Rs 67.59 crore was attached to five accounts where the plan had failed.
An implemented resolution plan does not mean the underlying project has left the projects-under-implementation disclosure, because the Rs 5,460.65 crore remains included in the quarter-end project balance. Similarly, the Rs 4,929.49 crore under implementation remained within the project balance at September 30, 2026.
The filing includes separate rows for cases involving a change in project scope and size, cost overruns associated with DCCO extension, and sanctioned bridge capital facilities, or SBCF. SBI did not report account counts or outstanding amounts in those rows, so no amount can be assigned to these mechanisms from the September 30, 2026 disclosure.
Got a follow-up? Ask IRIS
Are there projects under resolution without a DCCO extension?
SBI disclosed one project account with Rs 50.12 crore outstanding where a resolution process not involving an extension of original or extended DCCO had been invoked at September 30, 2026. The filing classified this one account as having a resolution plan under implementation.
This Rs 50.12 crore category is distinct from the Rs 10,457.73 crore involving DCCO extensions. SBI did not report any account or outstanding amount under the implemented-plan or failed-plan subcategories for the non-DCCO-extension resolution line.
The reporting format also distinguishes the 111 projects that achieved DCCO during the quarter, carrying Rs 6,021.57 crore, from projects where a resolution process had been invoked. Achieving DCCO is a quarterly project-status event, while the Rs 10,457.73 crore figure identifies accounts with a resolution process involving extensions; the filing does not state whether any DCCO-achieved accounts had previously been subject to such a process.
What should readers monitor in SBI’s project-finance disclosure?
The principal unresolved group is the Rs 4,929.49 crore in 290 DCCO-extension cases with resolution plans under implementation at September 30, 2026. Future disclosures can show whether these cases move into implemented plans, leave the projects-under-implementation portfolio after achieving DCCO, or enter the failed-plan category.
Readers can also compare future new sanctions with projects reaching DCCO. In the quarter ended September 30, 2026, Rs 2,927.68 crore of new sanctions was lower than Rs 6,021.57 crore of projects achieving DCCO, producing a Rs 3,093.89 crore reduction in the projects-under-implementation balance.
The five failed-plan accounts carrying Rs 67.59 crore are another disclosed category to track. SBI also reported one non-DCCO-extension resolution account carrying Rs 50.12 crore, under implementation as of September 30, 2026, separate from the 372 DCCO-extension accounts.
Conclusion
SBI’s September 30, 2026 disclosure shows that construction-stage project exposure declined from Rs 79,162.81 crore to Rs 76,068.92 crore as DCCO-achieved exposure of Rs 6,021.57 crore exceeded Rs 2,927.68 crore of new sanctions. At the same time, Rs 10,457.73 crore remained in resolution processes involving extensions to original or extended DCCO.
What to watch next is the outcome of the 290 DCCO-extension resolution plans under implementation, carrying Rs 4,929.49 crore, and the five failed-plan accounts carrying Rs 67.59 crore. Subsequent filings can also show whether new sanctions, DCCO achievements and newly invoked resolution processes change the Rs 76,068.92 crore project-under-implementation balance.