TD Power Systems targets Q1 2028 fourth-plant readiness
Key highlights
- TD Power Systems targets calendar Q1 2028 readiness for its fourth plant, with June 2028 the stated outer limit.
- The Siemens-linked plant is intended to produce generators ranging from 125 MW to 325 MW.
- TD Power Systems plans to ramp production in calendar 2028 and reach 70%-80% utilisation by FY30.
- TD Power Systems may consider additional capacity below 50 MW or 60 MW in 2029 if customer forecasts materialise.
powered by IRIS

TD Power Systems Limited is targeting calendar Q1 2028 readiness for its Siemens-linked fourth plant, ahead of June 2028, which management called the absolute outer limit, and expects production to ramp to 70%-80% utilisation by FY30 for generators in the 125 megawatt (MW) to 325 MW range.
Know TD Power Systems inside out
Results, valuation, peers and who's buying, in one view.
When will TD Power Systems’ fourth plant be ready?
TD Power Systems is aiming to have its fourth plant ready in calendar Q1 2028. Managing Director Nikhil Kumar described June 2028 as the “absolute outer limit” when asked whether that earlier date remained the project deadline, establishing a management target that is earlier than the stated outer-limit date.
Construction had begun by the time of the call, and a Bhoomi Puja was scheduled for November 19. TD Power Systems had ordered most major equipment, according to Kumar, who said the project would move into full swing after the ceremony and that Siemens forecasts and commitments were proceeding as planned.
The Q1 2028 objective coincides with the period when TD Power Systems expects capacity additions by its original equipment manufacturer, or OEM, customers to start affecting industry volumes. Kumar said customer capacities were expected to come online in 2028 and 2029, while also stating that generator waiting periods had not come down.
What will TD Power Systems make for Siemens?
TD Power Systems plans to produce larger 125 MW to 325 MW generators at the fourth plant for the Siemens gas-turbine group. Kumar clarified that the build-to-print orders already being booked came from the gas-turbine business rather than Siemens’ Transformation of Industry group.
The company has started booking Siemens orders for two-pole generators on a build-to-print basis, but management did not disclose their value, unit volumes or their allocation to the fourth plant. Kumar said the scale of the investment had been discussed in other forums, but no project investment amount was provided on this call.
TD Power Systems is separately investing in its own two-pole-generator design and production capacity for 100 MW machines. Management identified these 100 MW products as a growth area, distinct from the 125 MW to 325 MW generator range specified for the Siemens-linked fourth plant.
The company’s OEM model depends on detailed forecasts for 2027, 2028 and 2029, under which TD Power Systems makes and guarantees capacity available while customers release orders closer to the execution cycle. Kumar corrected an interpretation during the call by saying that discussions for 2029 and 2030 orders were under way, but those orders had not yet been booked.
Got a follow-up? Ask IRIS
How will TD Power Systems ramp production through FY30?
TD Power Systems plans to ramp production during calendar 2028 after the plant is ready and targets 70%-80% utilisation by FY30. Kumar described the intervening period as a capacity or production ramp, rather than giving a date for immediate full-scale operations after commissioning.
An analyst asked whether the longer-gestation 125 MW to 325 MW products would contribute revenue in the fourth quarter of FY29 or mainly in FY30. Management responded with the calendar 2028 production-ramp plan and FY30 utilisation target, without providing a first revenue-recognition quarter for the plant.
The company’s broader demand commentary included Indian steel-sector orders for 40 MW to 100 MW equipment and European demand for grid stabilisation and waste-to-energy projects. Vinay Hegde, head of sales and marketing globally, said these segments were growing, but the call did not disclose their respective order values or their expected use of fourth-plant capacity.
TD Power Systems said certain orders scheduled for FY28, FY29 and FY30 include price-variation clauses linked to raw-material costs. Kumar said pricing was stable and that these formulas would raise or lower selling prices with input costs, but the company gave no fourth-plant margin or revenue forecast.
Does TD Power Systems have enough capacity beyond FY30?
TD Power Systems may consider additional capacity for products below 50 MW or 60 MW in 2029 if customer forecasts materialise. Kumar said management had not decided the size, location or form of any such expansion, making this a potential next step rather than an approved project.
Current investment plans are focused mainly on the larger Siemens-linked project and the company’s 100 MW two-pole-generator programme. For products below 50 MW or 60 MW, TD Power Systems is seeking to raise output through more efficient asset use, automation and technology rather than through an announced new facility.
An analyst cited capital employed of about Rs 820 crore while asking how much more output existing assets could support. Kumar said he did not have a clear answer, although he said the company had achieved improvements in asset utilisation and believed further gains were possible.
TD Power Systems also reported about Rs 2,300 crore of pending orders and initial guidance of Rs 3,435 crore. Neither figure was split between the fourth plant, Siemens orders and existing operations, so the call does not establish how much of the current order position will support the new site’s FY30 utilisation objective.
Conclusion
TD Power Systems has defined the operating schedule for its fourth plant: calendar Q1 2028 is the readiness target, June 2028 is the outer limit and FY30 is the target year for 70%-80% utilisation. The project supports larger 125 MW to 325 MW generators for the Siemens gas-turbine group, while the company separately develops 100 MW two-pole machines and seeks higher output from current assets.
The next milestones are the November 19 Bhoomi Puja, progress on installation of the major equipment already ordered and the release of customer orders nearer to the 2028 and 2029 execution cycle. TD Power Systems has also said it could revisit incremental capacity for products below 50 MW or 60 MW in 2029 if customer forecasts translate into the volumes management expects.