TEIPL ends 15% PB North West penalty from 8 September 2026
Key highlights
- TEIPL avoided a 15% PB North West penalty from 8 September 2026 after both CHP streams became operational.
- PB North West produced 5.62 lakh tonnes of coal and dispatched 6.52 lakh tonnes in Q2FY27.
- TEIPL's H1FY27 revenue rose 43% year on year to Rs 4,608.2 crore.
- TEIPL's H1FY27 EBITDA rose 85% year on year to Rs 883.6 crore, with a 19.18% margin.
powered by IRIS

Thriveni Earthmovers and Infra Private Limited, referred to as TEIPL, avoided a 15% penalty at PB North West from 8 September 2026 after operationalising both Coal Handling Plant streams; its H1FY27 EBITDA increased 85% year on year to Rs 883.6 crore.
Know Lloyds Metals & Energy inside out
Results, valuation, peers and who's buying, in one view.
How did TEIPL end the PB North West penalty?
TEIPL ended the 15% penalty by commissioning and operationalising both streams of the Coal Handling Plant, or CHP, at PB North West, with the avoidance effective from 8 September 2026. The presentation identifies the CHP commissioning as the reason the penalty was avoided, rather than as a planned or partly completed activity.
The CHP milestone was reported alongside the completed rehabilitation and resettlement of three major villages, Sirma, Basaria and Nawadih. PB North West also recorded Q2FY27 coal production of 5.62 lakh tonnes and overburden, or OB, removal of 20.09 lakh cubic metres, showing reported mine activity during the quarter in which the site update was provided.
What did TEIPL produce and dispatch at PB North West in Q2FY27?
TEIPL produced 5.62 lakh tonnes of coal, crushed 6.69 lakh tonnes and dispatched 6.52 lakh tonnes at PB North West in Q2FY27. The operation also removed 20.09 lakh cubic metres of OB, which is reported separately from coal volumes in the presentation.
Crushing exceeded dispatch by 0.17 lakh tonnes in Q2FY27, while dispatch exceeded production by 0.90 lakh tonnes. These are separate stages of the coal-handling chain, and the presentation reports each metric independently rather than giving a single operating-volume measure.
PB North West formed part of TEIPL's Indian coal operations, which reported 18.82 million cubic metres including OB in Q2FY27, compared with 16.87 million cubic metres in Q2FY26. At the separately reported PB West operation, Q2FY27 coal production was 34.4 lakh tonnes, coal crushing was 37.2 lakh tonnes and coal dispatch was 38.1 lakh tonnes, all above PB North West's reported volumes.
How did TEIPL's H1FY27 financial performance change?
TEIPL reported H1FY27 revenue from operations of Rs 4,608.2 crore and EBITDA of Rs 883.6 crore, compared with Rs 3,229.5 crore and Rs 478.8 crore in H1FY26. Revenue increased 43% year on year, while EBITDA increased 85%, and the EBITDA margin rose to 19.18% from 14.82%.
TEIPL's H1FY27 cash profit after tax increased 116% year on year to Rs 558.2 crore, while its cash profit margin rose to 12.11% from 8.01%. As of 30 September 2026, TEIPL reported net debt including redeemable preference shares of Rs 4,841.6 crore and net worth of Rs 2,735.3 crore.
Got a follow-up? Ask IRIS
Why was TEIPL's Q2FY27 EBITDA below Q1FY27?
TEIPL's Q2FY27 revenue was Rs 1,936.4 crore, down 29% from Rs 2,671.9 crore in Q1FY27, and EBITDA was Rs 225.6 crore, down 66% from Rs 658.1 crore. The Q2FY27 EBITDA margin was 11.65%, compared with 24.63% in Q1FY27 and 13.22% in Q2FY26.
Year on year, TEIPL's Q2FY27 revenue increased 22% from Rs 1,590.8 crore, while EBITDA increased 7% from Rs 210.3 crore. Total expenses rose 24% year on year to Rs 1,710.8 crore, and cash profit after tax increased 47% to Rs 111.4 crore; the cash profit margin increased by 97 basis points to 5.75%.
Reported operating activity was also lower sequentially in two disclosed measures. Iron ore volume including banded haematite quartzite, or BHQ, was 11.22 million tonnes in Q2FY27 versus 19.09 million tonnes in Q1FY27, while Indian coal activity including OB was 18.82 million cubic metres versus 26.02 million cubic metres.
What other operating developments did TEIPL report?
TEIPL said full-scale mining had commenced at Western Hill in Gadchiroli, where dispatch over the last two quarters was 11.02 million tonnes and cumulative dispatch reached 13.48 million tonnes. It also said the FY27 equipment mobilisation plan was completed on schedule, including 14 mobile crushers and 26 heavy earthmoving machinery units for BHQ crushing.
At Gadchiroli, TEIPL reported 88 electric equipment units operating at the mines and another 20 at the railway siding. A 100-tonne diesel dumper had been converted to liquefied natural gas-hybrid operation, while mobilisation and assembly remained in progress for 10 EH5000 ultra-class dump trucks, one R 996 excavator and two EX 2500 excavators.
In Odisha, TEIPL said production at DCJ commenced in October 2026. Operations at Tata Joda West Iron Ore Mines, Vijay-II Iron Ore Mines, and Tata Tiringpah and Bamebari Manganese Mines were expected to commence shortly, while Geomysore's approved mining plan covers 1.5 million tonnes per annum each of opencast and underground mining and 1.5 million tonnes per annum of processing capacity.
Conclusion
TEIPL reported a completed PB North West handling and rehabilitation milestone alongside quarterly production of 5.62 lakh tonnes and dispatch of 6.52 lakh tonnes. The half-year financial comparison showed EBITDA growth outpacing revenue growth, with the margin rising 436 basis points to 19.18%, although the Q2FY27 margin was below both Q1FY27 and Q2FY26 levels.
The next disclosed execution points are the expected start of operations at four Odisha mines and the ongoing assembly of 10 EH5000 dump trucks and three excavators in Gadchiroli. The presentation also leaves future PB North West operating volumes unresolved after both CHP streams became operational from 8 September 2026.