TRSL targets up to 25,000 wheel supplies in FY27 ramp-up
Key highlights
- TRSL expects 20,000 to 25,000 forged-wheel supplies from its joint venture in FY27.
- TRSL's Chennai plant has produced 300 trial wheels that are under Indian Railways inspection.
- The project targets annual capacity of 228,000 forged wheels and has an estimated cost of Rs 2,181 crore.
- Both partners had infused Rs 532.65 crore of equity in the joint venture as of September 30, 2026.
powered by IRIS

Titagarh Rail Systems Limited expects its 49%-owned rail-wheel joint venture to supply about 20,000 to 25,000 forged wheels in FY27, following trial production at Chennai and Indian Railways' inspection of 300 trial wheels. TRSL plans partial production of 2,000 to 3,000 wheels a month from November or December 2026.
Know Titagarh Rail Systems inside out
Results, valuation, peers and who's buying, in one view.
What is TRSL doing at its Chennai wheel plant?
TRSL's joint venture with Ramkrishna Forgings Limited has started trial production at its Chennai, Tamil Nadu plant, where it has produced 300 forged wheels. Those 300 wheels are under inspection by Indian Railways, and TRSL said approval is expected shortly, without giving a date for the inspection decision.
The TRSL-Ramkrishna Forgings consortium has received a Letter of Acceptance, or LOA, to manufacture and supply forged wheels for Indian Railways. TRSL said commercial production will commence shortly, but the presentation distinguishes this expected next step from the current trial-production stage and does not disclose the LOA's value or wheel quantity.
The 300 trial wheels are a defined operational checkpoint before the venture's planned FY27 supply ramp. The presentation does not set out Indian Railways' inspection criteria, whether further trial batches may be needed, or a re-testing process, so the stated November or December 2026 production timing remains the company's disclosed plan rather than a reported commercial-production date.
How will TRSL ramp wheel supplies in FY27?
TRSL expects partial production of 2,000 to 3,000 wheels a month from November or December 2026 and a rise to 4,000 to 5,000 wheels a month in Q4 FY27. It forecasts supply of approximately 20,000 to 25,000 wheels for the full FY27 period.
The monthly range is planned to rise by 2,000 wheels at each end of the range, from 2,000 to 4,000 at the low end and from 3,000 to 5,000 at the high end. This is a staged ramp, not a full-capacity launch, and TRSL has not disclosed monthly production targets after Q4 FY27.
TRSL describes the FY27 figure as wheels expected to be supplied, rather than only manufactured. The source does not disclose a per-wheel price, FY27 revenue, the order's total wheel requirement or the share of output that may be held as inventory, limiting conclusions on the financial contribution of the 20,000 to 25,000-wheel target.
Got a follow-up? Ask IRIS
How large is TRSL's rail-wheel investment and capacity?
TRSL's joint venture plans a plant capable of producing 228,000 forged wheels a year, which the company describes as Asia's second-largest manufacturing plant in India. The capacity is a long-term design measure, compared with the 20,000 to 25,000 wheels expected to be supplied during the FY27 ramp.
The project is estimated to cost about Rs 2,181 crore across two phases and is being funded through a mix of debt and equity. Both partners had infused total equity of Rs 532.65 crore into the joint venture as of September 30, 2026; the presentation does not provide the debt amount, financing drawdown or funding schedule for the remaining project cost.
The FY27 target is below the 228,000-wheel annual capacity because TRSL expects only partial production from November or December 2026 before increasing output in Q4 FY27. The presentation does not give a date for reaching the plant's annual design capacity, nor does it identify production volumes for FY28 or later periods.
What is TRSL's stake and what remains unresolved?
TRSL holds a 49% stake in Ramkrishna Titagarh Rail Wheels Limited, its joint venture with Ramkrishna Forgings Limited. The Rs 532.65 crore equity figure is the combined infusion by both parties as of September 30, 2026, and the source does not break the amount down by shareholder.
The consortium's LOA for forged wheels from Indian Railways is the disclosed commercial basis for the Chennai project. However, the presentation does not state the award value, contract duration, contracted quantity or delivery schedule beyond TRSL's FY27 expectation of approximately 20,000 to 25,000 wheels supplied.
The rail-wheel venture is separate from TRSL's other disclosed joint venture with Bharat Heavy Electricals Limited, which was agreed on September 15, 2026 for maintenance of 80 Vande Bharat sleeper trainsets over 35 years. That maintenance venture is to have 50:50 ownership, unlike TRSL's 49% stake in the rail-wheel venture, and the two projects should not be combined.
Conclusion
TRSL has moved the Rs 2,181 crore rail-wheel project into trial production, with 300 forged wheels under Indian Railways inspection and an FY27 supply target of about 20,000 to 25,000 wheels. The expected ramp from 2,000 to 3,000 wheels a month to 4,000 to 5,000 in Q4 FY27 is materially below the plant's 228,000-wheel annual design capacity.
The next disclosed milestones are Indian Railways' approval of the 300 trial wheels, commercial production shortly thereafter, and partial production from November or December 2026. Investors can also watch whether output reaches the 4,000 to 5,000-wheel monthly range in Q4 FY27, while the timing of full capacity and remaining debt and equity funding remains undisclosed.