AIA Engineering holds Ghana and China expansion another quarter
Key highlights
- AIA Engineering will keep Ghana and China expansion on hold for one more quarter.
- Management hopes to reconsider geographical expansion by the end of next quarter.
- AIA Engineering sees a directional 25,000-to-30,000-tonne volume opportunity from next year, not formal guidance.
- Freight cost was about 10% of second-quarter sales versus management's normal 7% to 8% range.
powered by IRIS

AIA Engineering will hold its Ghana and China expansion projects for one more quarter and hopes to reconsider reactivation by the end of next quarter, while prioritising conversion trials. The timing is not a commitment: management gave no capital-spending amount, capacity target or project start date for either geography.
Know AIA Engineering inside out
Results, valuation, peers and who's buying, in one view.
Why has AIA Engineering put Ghana and China expansion on hold?
AIA Engineering has kept Ghana and China on hold for one more quarter because management is concentrating its efforts on trials and conversion work. Responding to a question about capital expenditure and capacity expansion in the two countries, Kunal Shah said management had discussed the matter and would maintain the existing position for another quarter. The company described the deferred activity as geographical expansion and disclosed neither a revised investment budget nor planned production capacity.
The decision coincides with management's effort to return to volume growth after a period it expects to remain flat this year. Management said 25,000 to 30,000 tonnes of volume growth looks possible from next year, although it explicitly did not present that range as guidance. AIA Engineering said its broader focus is on mining growth and conversion activity, rather than relying on non-mining demand, which management does not expect to be sufficiently scalable to materially change the outlook.
When could AIA Engineering reconsider the Ghana and China projects?
AIA Engineering hopes to reconsider reactivating geographical expansion by the end of next quarter, but management did not set a fixed approval or construction date. Shah said the company would revisit the position very soon while continuing to hold Ghana and China for one more quarter. The statement leaves open whether a review would lead to an investment approval, a capacity plan or only a further update on the projects.
The possible review will occur as management seeks more confidence in its 25,000-to-30,000-tonne directional volume outlook. Sanjay Majmudar said AIA Engineering hoped to provide more detail in the next quarter or the quarter after that. This indicates that management may assess geographic expansion alongside visibility on demand and trial conversion, rather than against a disclosed financial threshold for Ghana or China.
What trials are taking priority over AIA Engineering's expansion?
AIA Engineering is prioritising conversion trials, including its NGDS solution, a term not expanded in the transcript, and liner-based volumes before restarting geographical expansion. Management said success in NGDS and liner-based volumes should start becoming visible in the second half of the current fiscal year, after which grinding-media volumes should follow. It described the commercial approach as offering a combined package rather than selling grinding media separately.
Management has not attached a firm timetable to trial outcomes. Shah said AIA Engineering had discussed growth through NGDS and trials for the past two years, without the expected recovery yet occurring. He said NGDS could be an addition to the directional 25,000-to-30,000-tonne opportunity, while cautioning that the company would give firmer guidance only when it had greater confidence.
The trial priority also reflects the mechanics of converting a customer. Management said a conversion is not a straightforward commodity replacement because it involves a solution, a measurable outcome, trials, solution engineering and commercial discussions. Shipping reliability and currency considerations can add friction to that process, giving AIA Engineering a reason to focus on customer conversion execution before committing resources to new geographies.
Got a follow-up? Ask IRIS
What operating conditions will shape AIA Engineering's review?
AIA Engineering's review will take place amid freight and shipping uncertainty that management said affects costs and customer confidence. Freight cost was about 10% of sales in the second quarter, compared with management's normal-scenario range of 7% to 8%. Management attributed the higher ratio partly to air freight and elevated sea freight, and said it expected freight to return to the 7%-to-8% range in the current quarter.
Management said the shipping issue extends beyond the cost of freight because long delivery lead times can affect supply reliability for customers. For customers in South America, AIA Engineering said it can place more cargo in containers, maintaining another three months of cargo at sea in addition to about two months of stock on the ground. The measure is intended to reduce the risk that customer operations are interrupted if shipments are delayed.
Mining volumes remain another consideration. Management said a 50% import duty in Mexico affected some volume, while a Chile mine stopped production for almost two months during the quarter, reducing dispatches to that customer. Mexico's peak volume was under 7,000 to 8,000 tonnes a year, and management said the Chile mine had returned to normal traction from the current quarter.
Does AIA Engineering expect growth before restarting expansion?
AIA Engineering sees a possible return to growth from next year, but management has not issued formal volume guidance and says trials remain important. Shah said the company's internal view is that it should return to a growth phase from next year based on current information. Management expects this year to remain flat and described the 25,000-to-30,000-tonne range as directional commentary, not a forecast.
Non-mining operations are not expected to be the main driver of that recovery. An analyst noted that non-mining volume fell 12% year on year and 14% quarter on quarter, which management attributed to timing rather than a structural issue. Management said non-mining could grow during the year but is neither predictable nor expected to be large enough to materially change the company's growth trajectory.
The potential mining recovery is also linked to the resumption of deliveries to the Chile mine and management's view that the impact of Mexico's import duty is already reflected in current numbers. Management called the current position the bottom for its volumes, but did not offer formal guidance. It said the 25,000-to-30,000-tonne outlook should be viewed as an internal planning direction while trial conversions and logistics conditions develop.
Conclusion
AIA Engineering has deferred Ghana and China expansion for one more quarter to concentrate on trials, liner-based volumes and its NGDS solution. The decision aligns with management's stated aim of returning to growth from next year, supported by a directional 25,000-to-30,000-tonne volume opportunity, rather than by a disclosed commitment to new overseas capacity.
The next point to watch is management's hoped-for reconsideration by the end of next quarter, alongside potentially fuller volume commentary in the next quarter or the quarter after that. Progress in second-half NGDS and liner-based volumes, freight moving from about 10% toward the 7%-to-8% range of sales, and shipping reliability will be the disclosed operating markers around that review.