Godawari Power and Ispat Limited targets December 2027 CRM
Key highlights
- GPIL plans to commission a 0.7-million-tonne CRM complex in December 2027.
- GPIL had incurred Rs 109 crore on the Rs 1,100 crore CRM project by 30 September 2026.
- GPIL plans Rs 550 crore of debt and Rs 550 crore of internal accruals for the CRM.
- GPIL’s separate Rs 100 crore container line is targeted for March 2028.
powered by IRIS

Godawari Power and Ispat Limited targets December 2027 commissioning of a 0.7-million-tonne cold rolling mill complex in Maharashtra, with planned capital expenditure of Rs 1,100 crore. The company had incurred Rs 109 crore by 30 September 2026, ordered major processing lines and secured bank sanction for Rs 550 crore of debt funding.
Know Godawari Power & Ispat inside out
Results, valuation, peers and who's buying, in one view.
When will GPIL commission its cold rolling mill complex?
GPIL expects to commission its 0.7-million-tonne cold rolling mill, or CRM, complex in December 2027. The presentation describes the project as its entry into value-added steel, while its growth-capex pipeline lists no existing CRM capacity and shows 0.7 million tonnes as both the proposed addition and total capacity after expansion.
The December 2027 target follows several nearer-term projects in GPIL’s disclosed pipeline. Its 100-megawatt solar project and 45-megawatt-hour battery energy storage system, or BESS, project are expected to be completed in December 2026, while the crushing and beneficiation project is targeted for the third quarter of financial year 2027. The 20-gigawatt-hour BESS project is scheduled for the first quarter of financial year 2028, and the container line is due in March 2028.
GPIL’s Rs 1,100 crore CRM investment exceeds the Rs 600 crore spent on its pellet expansion, which lifted pellet capacity by 74% to 4.7 million tonnes. The company says that pellet plant is fully established and expects utilisation of the 4.7-million-tonne facility to reach 75% in financial year 2027. The CRM is therefore a separate move into downstream steel processing rather than another pellet-capacity addition.
Why did GPIL move the CRM project to Maharashtra?
GPIL moved the CRM project from Chhattisgarh to Maharashtra, near Sambhajinagar, to avail state incentives and subsidies and to benefit from proximity to its proposed BESS plant. The company identifies AURIC Bidkin in Maharashtra as the location, linking the site change to industrial-policy support and its planned battery-storage operations.
Maharashtra Industrial Township Limited has issued GPIL an offer letter for 31.45 acres of industrial land at AURIC Bidkin. Separately, the 20-gigawatt-hour BESS project has acquired 112 acres in the AURIC Industrial Area. The common Maharashtra location is the direct project connection disclosed by management.
The CRM project is registered under Production-Linked Incentive, or PLI, 1.1 and PLI 1.2 incentives. GPIL does not disclose the value of those incentives, the subsidy amount or any resulting effect on project economics. Its stated rationale remains access to state support and the location’s proximity to the proposed BESS plant.
How will GPIL fund the Rs 1,100 crore CRM complex?
GPIL plans to fund Rs 550 crore of the CRM cost through debt and the remaining Rs 550 crore through internal accruals. The company says it has received the requisite bank sanction for the debt portion, creating an equal split between planned borrowing and internal funding for the Rs 1,100 crore project.
By 30 September 2026, GPIL had incurred Rs 109 crore on the CRM, leaving Rs 991 crore to be incurred in the growth-capex pipeline. The same table shows Rs 609 crore incurred on the 20-gigawatt-hour BESS project against an approximate Rs 1,400 crore project cost, leaving Rs 791 crore. On these disclosed spending figures, the BESS project had incurred more capex than the CRM by that date.
GPIL has other projects with earlier execution dates and remaining expenditure. It lists Rs 258 crore incurred on the Rs 325 crore crushing and beneficiation project, which is targeted for the third quarter of financial year 2027. The 100-megawatt solar project had incurred Rs 240 crore, with Rs 80 crore remaining and completion expected in December 2026.
Got a follow-up? Ask IRIS
What equipment and products will GPIL’s CRM complex include?
GPIL has placed orders for a pickling line, two continuous galvanising lines, a colour coating line and an acid regeneration plant for the CRM complex. The two galvanising lines are specified as GL/ZAM and ZAM/Alu Silicon/GI configurations in the presentation. These process lines place coating and colour-coating facilities alongside cold rolling within the Rs 1,100 crore project.
GPIL says advance payments have been released for all major process lines and related contracts have been finalised. Detailed engineering and design were completed progressively through April 2026. Those procurement and engineering steps, alongside Rs 109 crore of capex incurred by 30 September 2026, had been completed ahead of the December 2027 commissioning target.
GPIL’s board has separately approved a container manufacturing line alongside the CRM at an additional Rs 100 crore investment, funded through internal accruals. It is expected to be commissioned in March 2028, three months after the CRM target. The capex pipeline specifies annual capacity of 10,000 20-foot containers and 11,200 small cabinets for BESS and marine-container applications.
The Rs 100 crore container-line investment is additional to the CRM’s Rs 1,100 crore budget and is scheduled later than the CRM. It should therefore not be treated as part of the 0.7-million-tonne CRM capacity. GPIL does not disclose projected revenue, utilisation, product pricing or customer arrangements for the CRM complex or the container manufacturing line.
Conclusion
GPIL’s December 2027 CRM plan combines a 0.7-million-tonne, Rs 1,100 crore investment with a move to Maharashtra, where it has an offer for 31.45 acres at AURIC Bidkin and cites state incentives and proximity to its proposed BESS operations. The ordered pickling, galvanising, coating and acid-regeneration lines support management’s stated move into value-added steel, while the separate Rs 100 crore container line adds manufacturing for BESS and marine uses.
The disclosed milestones to watch are the remaining Rs 991 crore of CRM expenditure and the December 2027 commissioning target. GPIL also plans to commission the container line in March 2028, while its 100-megawatt solar project and 45-megawatt-hour BESS project are expected in December 2026 and its 20-gigawatt-hour BESS project is targeted for the first quarter of financial year 2028.