INDO-MIM reports zero IGT cancellations amid capacity demand
Key highlights
- INDO-MIM said it had recorded zero cancellations in its industrial gas turbines segment.
- Management said IGT demand could remain elevated for the next 10 to 15 years, based on gas-turbine generation requirements.
- INDO-MIM currently makes about 1,200 aerospace components and targets at least 400 additions in the current year.
- The Vietnam electronic-components operation is expected to begin generating revenue in fiscal 2028.
powered by IRIS

INDO-MIM reported zero cancellations in its industrial gas turbines, or IGT, segment during its earnings call, despite an analyst raising a reported GE-linked cancellation involving a few gigawatts. Management said customers were instead pulling in programmes and discussing further component packages after initial technical capability had been demonstrated.
Know Indo-MIM inside out
Results, valuation, peers and who's buying, in one view.
Has INDO-MIM seen any IGT order cancellations?
No, INDO-MIM said it had faced zero cancellations in the IGT segment up to the earnings call. The response followed an analyst’s question on whether a reported SoftBank cancellation from GE could affect INDO-MIM’s exposure to industrial gas turbines, and Krishna Chivukula Jr. clarified that the company had seen “zero cancellations.”
Management did not identify a customer, programme value, order-book amount or delivery schedule for its IGT business. It said its own experience involved demand for aerofoils, casings and housings, rather than confirming conditions at GE or commenting on any specific supplier contract. The zero-cancellation statement therefore applies to INDO-MIM’s IGT segment, not to the wider gas-turbine supply chain.
Why does INDO-MIM expect IGT demand to continue?
INDO-MIM expects IGT demand to continue because original equipment manufacturers, or OEMs, need qualified capacity as gas-turbine generation requirements rise. Management said IGT could be “booming” for the next 10 to 15 years, while also making clear that this was its market outlook rather than revenue guidance or a disclosed order-book forecast.
The demand mechanism described by management is technical qualification. IGT components require specialised technical capability and significant quality systems, according to management, and OEMs that need capacity are willing to work with suppliers able to meet those requirements. Once INDO-MIM demonstrates capability on an initial programme, customers are generally willing to begin discussions on the next component package.
Management contrasted IGT with aerospace, where programmes take longer to mature but may have significant potential over the next 10 years because of expected engine sales to Southeast Asia. IGT was presented as a capacity-led opportunity tied to electricity-generation needs, while aerospace was described as having a longer product-development and qualification cycle.
Is INDO-MIM reliant on GE for IGT work?
No, INDO-MIM said GE is not the only participant in the industrial gas-turbine market and referred to orders from other OEMs. Krishna Chivukula cited South Korean and American companies, while naming ProEnergy as an example of another market participant. The company did not disclose revenue, order value or customer concentration for any of these relationships.
Management said GE is more vertically integrated than some peers and is relatively self-sufficient in parts of its supply chain, aside from areas including aircraft-engine parts and hot-zone components. INDO-MIM’s stated strategy is to build penetration across OEMs in both aerospace and IGT, and management said its presence in these markets had matured over the past two or three years as it ran programmes.
The company did not quantify what share of IGT revenue comes from GE, ProEnergy, South Korean customers, American customers or other OEMs. That leaves the exact level of customer diversification undisclosed, even though management’s comments indicate it views the addressable IGT market as broader than one manufacturer.
Got a follow-up? Ask IRIS
What capabilities and investment support INDO-MIM’s IGT work?
INDO-MIM said its IGT position depends on producing technically demanding components and maintaining the required quality systems. Management specifically identified aerofoils, casings and housings as standard IGT components with strong demand, and said active product development was under way across the group. It did not disclose the number of IGT programmes, output volumes or qualification stages.
Capital expenditure in the current financial year is expected to focus on secondary operations, including machining required to finish parts, rather than on primary processes. Management said it had sufficient capacity in metal injection moulding, or MIM, and casting, while significant programmes developing during the year would require investment for ramps in Q2 and Q4.
Management also said aerospace machining and IGT typically require higher raw-material holdings. It attributed inventory partly to minimum order quantities and lumpy purchases in casting and machining, where the company may need to buy an entire heat of material and consume it over time. INDO-MIM is targeting lower inventory by the end of the current year, but disclosed no inventory-days target.
What does INDO-MIM’s wider programme pipeline show?
INDO-MIM’s wider aerospace pipeline shows an effort to add parts alongside IGT work. The company said it currently produces about 1,200 aerospace components and had previously indicated a target to add at least 400 components in the current year. Management said it was on the way toward that target but did not disclose how many additional components had entered production.
A newly signed Safran Aircraft Engines contract was described as long term, but INDO-MIM did not disclose its value. Management said European OEMs were making room for military-related programmes amid higher defence spending and had significant work to source overseas in civilian aerospace and drones. It added that future Safran opportunities first depend on executing the existing contract and product development.
Outside aerospace and IGT, INDO-MIM expects its Vietnam electronic-component manufacturing operation to begin generating revenue in fiscal 2028. Management said development work in Vietnam would ultimately support business in India. The Vietnam plan is separate from the IGT outlook, but it shows that the company’s disclosed growth initiatives extend across electronic components, aerospace, drones and gas turbines.
Conclusion
INDO-MIM’s direct read-through on the reported GE-linked concern is that it had experienced zero cancellations in its own IGT segment at the time of the call. Management described customers pulling in programmes, demand for components including aerofoils and casings, and discussions on follow-on packages once a supplier has demonstrated technical capability.
The next developments to watch are execution on programmes expected to ramp in Q2 and Q4, progress on the target to reduce inventory by the end of the current year, and movement toward adding at least 400 aerospace components. Management also expects the Vietnam electronic-components operation to start revenue generation in fiscal 2028, while it has not provided an IGT revenue target or order-book figure.