Jain Irrigation targets Rs 300 crore receivables cut by March
Key highlights
- Jain Irrigation targets a Rs 300 crore-plus net reduction in its Rs 800 crore project receivables by March.
- Jain Irrigation had about Rs 1,860 crore of standalone receivables at the September quarter, including Rs 1,200 crore linked to projects and MIP.
- Active projects have fallen to seven or eight from roughly 78, with 15 to 20 projects closed in the previous six months.
- Jain Irrigation expects Rs 60 crore to Rs 70 crore of second-half project revenue and targets a September 2027 project-business exit.
powered by IRIS

Jain Irrigation targets a net reduction of more than Rs 300 crore in its Rs 800 crore project receivables by March, with management saying this should support obligations due by then. The company has reduced active projects to seven or eight from about 78 and expects to exit project business and related recoveries by September 2027.
Know Jain Irrigation Systems inside out
Results, valuation, peers and who's buying, in one view.
How much will Jain Irrigation reduce project receivables by March?
Jain Irrigation expects a net reduction of at least Rs 300 crore in project receivables by March. Management later described the goal as about 40% of the Rs 800 crore project book, or about Rs 320 crore. The measure is net of additional billing, rather than a statement that all cash collected will equal Rs 300 crore.
Management said the Rs 300 crore reduction, together with earnings before interest, tax, depreciation and amortisation, or EBITDA, generation, should be enough for obligations due by March. This was management's assessment rather than a detailed cash-flow forecast, and the call did not disclose the value or timing of individual obligations falling due by that date.
Management indicated that gross billing over the period could be Rs 360 crore to Rs 370 crore, while actual recovery could be higher, resulting in the targeted Rs 300 crore net decline after billing effects. The outcome therefore depends on both collections and residual project billing. Management also said receivables had begun declining in areas where recovery was previously difficult and expected most old legacy receivables to come through over the next few quarters.
What does Jain Irrigation's receivables book include?
Jain Irrigation reported standalone receivables of about Rs 1,860 crore at the September quarter. Of that amount, Rs 800 crore was linked to projects and Rs 400 crore to micro-irrigation projects, or MIP, where government subsidies play a role. Together, those government-linked categories accounted for about Rs 1,200 crore.
The Rs 300 crore-plus target applies to the Rs 800 crore project receivables balance, not to the full Rs 1,200 crore of government-linked project and MIP receivables. Management confirmed that the approximately 40% objective referred to the project book. MIP remains an ongoing business, in which credit continues to revolve as products are supplied and payments are fulfilled.
The remaining Rs 660 crore of the Rs 1,860 crore total consisted of normal retail and institutional receivables, solar-related amounts and exports, according to management. The planned project recovery therefore addresses a defined legacy balance, while collection performance in the other categories remains relevant to the wider working-capital position.
Got a follow-up? Ask IRIS
How close is Jain Irrigation to leaving project business?
Jain Irrigation has reduced active projects to about seven or eight from roughly 78 when it began the process, and management expects project business and related recoveries to become zero by September 2027. It said about 15 to 20 projects had been closed during the previous six months. Physical closure does not immediately eliminate receivables because final settlement with government counterparties takes more time.
Management described a path in which the Rs 800 crore project balance falls by about Rs 300 crore on a net basis by March, leaving about Rs 500 crore before further activity on the remaining projects. The seven or eight ongoing projects are expected to generate some additional revenue over the next 12 months, particularly the Pune project, where management said a substantial amount of work remains.
For the second half, management estimated project revenue of Rs 60 crore to Rs 70 crore, including the Pune project, after about Rs 14 crore of project revenue in the first half. Most other projects have little remaining revenue, except nominal billing that can arise during final closure and settlement. The expected second-half revenue is therefore concentrated in the limited projects still being executed.
Will collections cover Jain Irrigation's near-term obligations?
Management said the planned Rs 300 crore reduction in project receivables should be sufficient for March obligations when combined with EBITDA generation. The mechanism is that collection reduces the receivables balance and releases cash, while operating earnings add another source of cash generation. Management did not provide an EBITDA target or a complete March cash-flow bridge during the call.
Jain Irrigation said it had achieved good conversion of EBITDA into cash during the quarter and reduced its working-capital cycle, although management added that some challenges remained and some were beyond the company's control. It expects positive performance in the second half and further working-capital-cycle reduction over roughly the next 12 months as capacity utilisation increases.
Management said better collections should serve two purposes: repayment of obligations falling due and creation of liquidity for growth in the next fiscal year. It expects the balance sheet to look better as the company moves into financial year 2028, conditional on continued receivables reduction and operating progress. That expectation includes project collections but also relies on the ongoing MIP credit cycle and other receivable categories.
Conclusion
Jain Irrigation's disclosed plan combines a financial target with an operating exit. By March, management aims to reduce the Rs 800 crore project receivables balance by more than Rs 300 crore on a net basis, while the number of active projects has already fallen from about 78 to seven or eight. The strategy is intended to generate cash for near-term obligations while reducing the legacy project exposure.
The next milestones are the March net-reduction target and the Rs 60 crore to Rs 70 crore of estimated second-half project revenue, including the Pune project. Management's stated target is for project business and related recoveries to reach zero by September 2027, although government settlements can continue after physical closure. Progress on the residual project balance and the MIP collection cycle will determine whether that timetable is met.