Lemon Tree targets FY30 opening for its 21-floor Bandra hotel
Key highlights
- Lemon Tree targets an FY30 opening for a 21-floor Bandra hotel.
- Lemon Tree expects to begin Bandra excavation within 2-3 weeks.
- Lemon Tree outlined a roughly 33-month development sequence for Bandra.
- Lemon Tree said potential CAPEX could reach about Rs 3,000 crore over 3.5 years if acquisitions proceed.
powered by IRIS

Lemon Tree is targeting an FY30 opening for its 21-floor Bandra hotel, with excavation expected to start within 2-3 weeks and management outlining a development sequence of about 33 months. The plan depends on approval of architectural drawings, although Lemon Tree said excavation can proceed while those drawings are under review.
Know Lemon Tree Hotels inside out
Results, valuation, peers and who's buying, in one view.
When will Lemon Tree's Bandra hotel open?
Lemon Tree is targeting an FY30 opening for the Bandra hotel, based on a roughly three-year development path from FY27 to FY30. Management said it began designing the hotel about six months before the call, when it became sufficiently confident the acquisition would close. The design is complete, and the selected architect is preparing drawings for approval. The property already has approval for excavation, which management expected to begin within 2-3 weeks.
The first construction milestone is to emerge from the basement within 3-5 months. Lemon Tree said it would submit drawings at the same time as excavation starts, an approach it said is possible in Mumbai. Once the basement is complete and drawings are approved, management expects to start the superstructure. The hotel is planned at 21 floors, and management said the shell could be completed in about 20 months.
Management also described the overall schedule as six months, plus 21 months, plus six months, or about 33 months. That framework supports the FY30 target but is not a fixed completion date. The acquisition itself took about one year because it involved a complex buyout with roughly 19 owners and a housing society, rather than a transaction with one counterparty.
What could delay Lemon Tree's Bandra hotel?
Approvals are the main disclosed risk to Lemon Tree's FY30 target because management said real-estate development includes factors outside its control. The company expects excavation to proceed while drawings are submitted, but those drawings need to be fully approved before the superstructure can begin. Management estimated that it could be out of the basement and have approvals in place within 3-5 months, subject to the approval process.
Mumbai's monsoon is another practical constraint in the construction sequence. Management said developers typically try to avoid monsoon conditions for excavation, just as its Delhi projects must account for Graded Response Action Plan, or GRAP, restrictions in winter. These factors do not alter the FY30 target in management's plan, but they explain why the company did not give an unconditional assurance on the opening year.
Management specifically cautioned investors not to hold it to the projected schedule if a government authority takes an additional six months. It said it would be transparent about any delay and its cause. The 33-month outline includes construction and interiors, but approvals can extend the timeline beyond the six-month allowance management used in its estimate.
Got a follow-up? Ask IRIS
How much has Lemon Tree spent on Bandra and other projects?
Lemon Tree said it had spent about Rs 200 crore across the Bombay buyout, project work and renovation capital expenditure at the time of the call. Management separately described the Bombay acquisition outlay as Rs 120 crore plus Rs 9 crore, and said another Rs 50 crore to Rs 70 crore had been spent in Shimla and Shillong. It had not started major expenditure in Varanasi or Nehru Place.
The Rs 3,000 crore figure is conditional rather than a formal annual capital-expenditure commitment. When asked about FY28 and FY29 spending, management said the total could reach roughly Rs 3,000 crore over the next 3.5 years if it completes acquisitions and new projects under consideration. The ultimate funding requirement therefore depends on transactions still undergoing due diligence, rather than only on the Bandra development.
Renovation is another component of cash deployment. Management said about 60%-65% of renovation spending is operating expenditure, or OPEX, with the balance treated as capital expenditure, or CAPEX, when it covers equipment replacement or major hotel assets. It indicated renovation CAPEX of about Rs 40 crore for the year and said investors should assess free cash generation after both project CAPEX and spending on existing hotels.
How does Bandra fit Lemon Tree's expansion plan?
Lemon Tree's Bandra development forms part of a wider plan combining acquisitions, brownfield assets and greenfield construction. Management said it remained hopeful of identifying 2,500 rooms between operational brownfield and greenfield assets within the next 9-12 months, by the time of a planned Fleur listing. It also said it was hopeful those 2,500 rooms could be operational by FY30-FY31, while noting that legal, technical, soil and financial diligence can lengthen transaction timelines.
The Bandra project illustrates the difference between acquired assets and new construction. Management said acquisitions can have a direct and immediate effect on Fleur's earnings before interest, tax, depreciation and amortisation, or EBITDA, whereas a 21-floor development requires excavation, structural work, interiors and approvals. It also said Warburg Pincus's Rs 960 crore investment is available on call for acquisitions or developments, but Lemon Tree would draw the funds only when it can deploy them.
Elsewhere, Lemon Tree discussed an Omaxe arrangement covering about 4,000 rooms across 10 projects, with land already owned by Omaxe. Management said all but the Greater Noida property would take 3-4 years, and fee income should be assumed to begin only after four years. Those projects will use the Lemon Tree brand, showing that the group has owned, acquired, managed and franchise-linked routes to expansion with different funding and revenue timings.
Conclusion
Lemon Tree has set out a defined route to an FY30 opening for its 21-floor Bandra hotel: excavation within 2-3 weeks, basement completion and expected approvals in 3-5 months, followed by structural construction and interiors within a roughly 33-month framework. The project sits alongside about Rs 200 crore already spent across the Bombay transaction, projects and renovation CAPEX, rather than representing an isolated investment.
The next milestones are the start of excavation, progress out of the basement and approval of architectural drawings. Investors should also watch whether Lemon Tree completes acquisitions under review, because management said that outcome could lift total spending to about Rs 3,000 crore over the next 3.5 years and affect the timing of its wider 2,500-room expansion plan.