MMP Solar Commissioning Slips to January-February on Approvals
Key highlights
- MMP expects its approximately 7-megawatt solar park to be commissioned in January-February 2027, after missing the Q3 FY27 target.
- The Rs 30 crore solar project is almost ready, with all major equipment in place, but regulatory approvals are pending.
- Management estimates the solar facility could reduce MMP's power cost by Rs 3 to Rs 3.50 per unit.
- MMP reported H1 FY27 EBITDA of Rs 40.3 crore, and EBITDA margin increased to 8.3% from 7.13% a year earlier.
powered by IRIS

MMP Industries Limited (MMP) now expects its nearly complete 7-megawatt group captive solar park to be commissioned in January-February 2027 rather than Q3 FY27, because regulatory approvals remain pending. Management said the Rs 30 crore project has all major equipment in place and could reduce power costs by Rs 3 to Rs 3.50 per unit after it starts.
Know MMP Industries inside out
Results, valuation, peers and who's buying, in one view.
Why is MMP's solar park delayed?
MMP said pending regulatory approvals have delayed commissioning of the approximately 7-megawatt group captive solar park beyond its original Q3 FY27 target. Managing Director Arun Bhandari gave the revised January-February expectation on the November 3, 2026 earnings call, while describing the project as almost ready at site.
The disclosed constraint is regulatory rather than a shortfall in construction or equipment. MMP said all major equipment is in place for the Rs 30 crore project, and the call did not identify a change in capacity, investment, financing or site readiness. It also did not name the regulator or regulators from which approvals are awaited.
The timetable change moves commissioning beyond the quarter ending December 2026. Management did not provide a specific date within January-February 2027, so the revised schedule remains an expectation contingent on completion of the approval process.
When will MMP's 7-megawatt solar park begin operating?
MMP expects the solar park to begin operating sometime in January-February 2027, subject to the pending regulatory clearances. This is later than the original Q3 FY27 commissioning target, which management had set for the period ending December 2026.
The group captive classification indicates that the facility is intended to help meet MMP's electricity requirements rather than being presented as a standalone power-sales operation. However, management did not disclose which MMP facilities will receive the power, the proportion of their electricity needs covered, or the expected annual generation from the 7-megawatt park.
The solar initiative sits within a wider set of cost and capacity projects. MMP said its 18,000-metric-tonnes-per-annum aluminium wire-rod facility was at an advanced stage of construction and machinery installation, with commercial production targeted for early Q4 FY27, while its 6,000-metric-tonnes-per-annum low-tension power-cable expansion at Umred had trials targeted for Q4 FY28.
How much does MMP expect to save on power costs?
MMP estimates that the solar project could save about Rs 3 to Rs 3.50 per unit compared with its existing power cost. Director Mayank Bhandari gave that range in response to a question about annual savings, while noting that actual generation was not yet known because the project had not started operating.
Management did not disclose expected annual units generated, the amount of captive consumption, annual rupee savings or a payback period for the Rs 30 crore investment. As a result, the company has provided a unit-cost estimate but not enough information to calculate the facility's yearly financial benefit.
MMP also did not quantify the effect on earnings before interest, tax, depreciation and amortisation, or EBITDA. When asked about the EBITDA-margin impact, Chief Financial Officer Sharad Khandelwal said it would be difficult to answer, meaning any margin benefit remains unquantified until generation and usage data are available.
Got a follow-up? Ask IRIS
What does the solar delay mean for MMP's FY27 results?
The delay means that MMP's intended solar-led reduction in power cost will start later than its original Q3 FY27 plan, if approvals permit commissioning in January-February 2027. Management said the project should reduce power costs and support long-term margin improvement, but it did not change any FY27 revenue, EBITDA or profit outlook because of the revised schedule.
The park made no contribution to the first half ended September 30, 2026. MMP reported H1 FY27 total income of Rs 485.7 crore, up 31% from Rs 371.9 crore in H1 FY26, while EBITDA increased 52% to Rs 40.3 crore and EBITDA margin rose to 8.3% from 7.13%.
Quarterly results show why management has treated solar as a future cost initiative rather than an explanation for current margins. Q2 FY27 EBITDA margin was 7.65%, down from 9.01% in Q1 FY27, primarily because of inventory-valuation losses; management quantified Q2 inventory-related losses at about Rs 2.5 crore and said two early-stage subsidiaries recorded combined EBITDA losses of about Rs 1.5 crore.
MMP also cited a greater share of lower-margin foil sales in Q2 FY27. In contrast, the aluminium powders segment reported H1 FY27 revenue of Rs 315 crore, up 41% year on year, and aluminium foil revenue increased 38% to Rs 135 crore, while conductors and cables revenue fell 32% to Rs 33 crore amid monsoon-related slower project execution.
What should investors watch before MMP starts solar generation?
The immediate milestone is receipt of the regulatory approvals that management said were pending on November 3, 2026. With major equipment already installed at the 7-megawatt site, a commissioning update would determine whether MMP meets its January-February 2027 expectation or faces a further shift.
After commissioning, the relevant operating measures will be generated units, captive-power usage and the actual reduction in MMP's power cost against the stated Rs 3 to Rs 3.50-per-unit estimate. MMP has not disclosed annual generation or an EBITDA-margin calculation, so these data would be needed to measure the financial outcome of the Rs 30 crore investment.
A further consideration is execution across MMP's newer businesses. Management expects initial low-tension cable sales from its Bhandara facility to gain momentum from Q4 FY27, subject to approvals, while it said polymer-insulator capacity could reach optimum utilisation from H2 FY28 and targets an 18% to 20% EBITDA margin for that business as it scales.
Conclusion
MMP's revised solar timetable leaves the project physically close to completion but administratively unfinished. The 7-megawatt captive facility is designed to lower the company's electricity cost by an estimated Rs 3 to Rs 3.50 per unit, yet the annual savings and margin effect cannot be established from the disclosed information because expected generation and captive use have not been quantified.
The next item to watch is whether MMP receives the outstanding approvals and commissions the Rs 30 crore facility within the January-February 2027 window outlined by management. Subsequent disclosures on generation, consumption and realised power costs will show whether the project delivers the savings mechanism management has identified.