Om Infra's ₹2,083.35 crore order book is 52% in Uttar Pradesh
Key highlights
- Om Infra reported ₹2,083.35 crore of work in hand across 16 projects on 30 September 2026.
- Uttar Pradesh represented ₹1,076.23 crore, or 51.7%, of Om Infra’s work balance.
- Om Infra disclosed ₹1,051 crore of L1 projects at Sirpur and Andheri, with LOIs awaited soon.
- Management guides for FY27 revenue of ₹600-700 crore and expects ₹1,500 crore of order inflow.
powered by IRIS

Om Infra Ltd had ₹2,083.35 crore of work in hand across 16 ongoing projects on 30 September 2026, with Uttar Pradesh contributing ₹1,076.23 crore, or 51.7%. The company also disclosed ₹1,051 crore of L1 projects awaiting letters of intent and management’s FY27 revenue guidance of ₹600-700 crore.
Know Om Infra inside out
Results, valuation, peers and who's buying, in one view.
How concentrated is Om Infra’s order book by state?
Uttar Pradesh is Om Infra’s largest geographic exposure, accounting for ₹1,076.23 crore of work in hand, compared with ₹442.35 crore in Rajasthan and ₹248.22 crore in Jammu and Kashmir. Uttar Pradesh’s 51.7% share is more than twice Rajasthan’s 21.2% share, making execution in that state central to the ₹2,083.35 crore work balance reported on 30 September 2026.
The remaining ₹1,007.12 crore, or 48.3%, is distributed across the eight other locations shown in the presentation. Rajasthan and J&K together account for ₹690.57 crore, or 33.1%, while Punjab, Maharashtra, Tamil Nadu, Arun-3, Manipur and Uttarakhand together represent ₹316.55 crore. The portfolio therefore extends beyond Uttar Pradesh, but its state distribution is not even.
Which projects make up Om Infra’s work in hand?
The Amroha, Unnao, Raibarely and Sambhal package is Om Infra’s largest individual project at ₹445.14 crore, and includes 10 years of operations and maintenance, or O&M. The next largest listed assignments are the HCC-OMIL joint-venture Nokha project in Rajasthan at ₹248.88 crore, the Kawar project in J&K at ₹248.22 crore, and the OMIL-JWIL joint-venture Rampur project in Uttar Pradesh at ₹220.42 crore.
Uttar Pradesh’s ₹1,076.23 crore total comprises five listed entries: the ₹445.14 crore Amroha, Unnao, Raibarely and Sambhal package; the ₹220.42 crore Rampur project; the ₹162.53 crore Amroha project; ₹136.00 crore of Rampur O&M work; and the ₹112.14 crore Shajapur project. Rajasthan’s ₹442.35 crore total consists of the ₹248.88 crore Nokha project, ₹153.12 crore Khajuwala project and ₹40.35 crore Isarda project.
At the smaller end of the 16-project portfolio, Om Infra reports ₹20.44 crore for Tapovan in Uttarakhand, ₹31.14 crore for Imphal Barrage in Manipur and ₹13.77 crore for the Kunda project through Patel Engineering in Tamil Nadu. The two Kunda entries total ₹59.61 crore, while the Arun-3 Nepal project for SJVNL has ₹55.46 crore of work balance.
Got a follow-up? Ask IRIS
What could increase Om Infra’s work in hand?
Om Infra disclosed that it is L1, or lowest bidder, for the Sirpur and Andheri projects valued at ₹1,051 crore, with letters of intent, or LOIs, awaited soon. This ₹1,051 crore is not included in the reported ₹2,083.35 crore work balance, and therefore remains a potential addition rather than part of the 16 ongoing projects as of 30 September 2026.
Management expects FY27 order inflow of ₹1,500 crore and identifies hydro mechanical projects, pumped storage and water infrastructure as target areas. Its stated strategy includes bidding for projects from NHPC, SECI and state power utilities, forming joint ventures with global turbine and electro-mechanical players, and pursuing long-term design-build-finance-operate-transfer, or DBFOT, and public-private partnership annuity models.
Management has separately targeted monetisation of non-core assets and arbitration awards of about ₹1,200 crore or more over the next two to three years. This target is distinct from the ₹1,500 crore order-inflow expectation and the ₹1,051 crore of L1 projects, as it relates to asset and arbitration-award monetisation rather than new construction orders.
How does Om Infra’s FY27 guidance relate to execution?
Management guides for FY27 revenue of ₹600-700 crore and an EBITDA margin of 10-11%, while Om Infra reported consolidated revenue from operations of ₹264.3024 crore in H1 FY27. That revenue was 15.9% higher than ₹228.1359 crore in H1 FY26, providing the reported first-half comparison against the company’s full-year guidance range.
EBITDA, or earnings before interest, tax, depreciation and amortisation, was ₹21.9911 crore in H1 FY27, up 72.3% from ₹12.7613 crore in H1 FY26. Om Infra defines EBITDA in the presentation as profit before tax plus finance costs plus depreciation and amortisation, and calculates EBITDA margin on total income, which includes revenue from operations and other income.
The consolidated EBITDA margin rose by 269 basis points to 8.12% in H1 FY27 from 5.43% a year earlier, but remained below management’s 10-11% FY27 guidance range. Profit before tax increased to ₹9.3818 crore from ₹1.1456 crore, while profit after tax declined to ₹0.6038 crore from ₹6.0215 crore; the presentation notes a temporary real-estate segment loss due to execution of low-price sale deeds.
Conclusion
Om Infra’s disclosed work balance provides ₹2,083.35 crore of identified projects across 16 assignments, but ₹1,076.23 crore of that balance is in Uttar Pradesh. The ₹445.14 crore Amroha, Unnao, Raibarely and Sambhal package is the largest individual project, while Rajasthan’s ₹442.35 crore and J&K’s ₹248.22 crore are the next-largest geographic pools.
The next disclosed developments to watch are LOIs for the ₹1,051 crore Sirpur and Andheri projects, progress against management’s ₹1,500 crore FY27 order-inflow expectation, and delivery against ₹600-700 crore of FY27 revenue guidance. Management’s target to monetise about ₹1,200 crore or more of non-core assets and arbitration awards over the next two to three years is another disclosed milestone.