Prostarm adds 1.2 GWh BESS capacity across five sites
Key highlights
- Prostarm expanded to five manufacturing facilities in September 2026.
- Jhajjar has 1.2 GWh of stated single-shift BESS capacity.
- Bakrol combines UPS production with 100 MWh of lithium-ion battery-pack capacity.
- Prostarm reported Rs 1,120.7 crore of total orders in hand in Q2/H1-FY27.
powered by IRIS

Prostarm Info Systems Limited expanded to five manufacturing facilities in September 2026, adding a 1.2 gigawatt-hour, or GWh, single-shift battery energy storage system plant at Jhajjar, Haryana, and a new uninterruptible power supply unit at Bakrol, Gujarat. The company also relocated lithium-battery manufacturing and shifted transformer operations during Q2-FY27.
Know Prostarm Info Systems inside out
Results, valuation, peers and who's buying, in one view.
What manufacturing footprint does Prostarm now operate?
Prostarm says it operates five manufacturing facilities nationwide, although its manufacturing-unit table identifies four geographic locations because Pune contains two separately stated units. The two Pune units make uninterruptible power supply, or UPS, systems, solar hybrid inverters, lift inverters, inverters and other power-solution products, with stated capacities of 17,100 kilovolt-amperes or kilowatts and 60,000 kilovolt-amperes or kilowatts, respectively.
The combined Pune capacity is therefore 77,100 kilovolt-amperes or kilowatts across its two units, located within 36,000 square feet. Outside Pune, Prostarm lists Mahape in Navi Mumbai, Jhajjar in Haryana and Bakrol in Gujarat. Those locations respectively handle servo stabilizers and isolation transformers, battery energy storage systems, or BESS, and UPS systems plus lithium-ion battery packs.
The five-facility structure represents a change from the company’s earlier footprint because the presentation describes a new Jhajjar BESS plant, a new Bakrol UPS unit and the movement of existing operations in Q2-FY27. Prostarm’s manufacturing footprint now spans Maharashtra, Haryana and Gujarat, while its sales and service network includes more than 425 dealers and 23 branch offices.
Jhajjar and Bakrol are the two largest listed sites by area, at 34,000 square feet and 46,558 square feet, respectively. Mahape occupies 7,501 square feet and is the smallest listed manufacturing location, while Pune occupies 36,000 square feet. The presentation does not disclose capital expenditure, commissioning costs, utilisation levels or employee numbers for any of the five facilities.
What did Prostarm add at Jhajjar and Bakrol?
Prostarm established a 1.2 GWh single-shift BESS plant at Jhajjar and a UPS unit at Bakrol in September 2026. The Jhajjar plant is designated for commercial and industrial, or C&I, customers and utility projects. Its 1.2 GWh rating is the largest energy-storage capacity disclosed for a single facility in the presentation.
The Jhajjar site covers 34,000 square feet and is part of Prostarm’s stated BESS growth vertical. The company describes this vertical as BESS assembly and integration, power conversion systems, energy management systems and engineering, procurement and construction, or EPC, work. Its established businesses include power electronics, system integration, solar EPC and value-added services such as rentals, annual maintenance contracts and after-sales support.
Bakrol covers 46,558 square feet and produces UPS systems rated from 1 to 600 kilovolt-amperes as well as lithium-ion battery packs. The facility lists 100 megawatt-hours, or MWh, of lithium-ion battery-pack capacity. Prostarm’s presentation says promoter Vikas Agarwal is responsible for procurement, inventory management and plant operations at Bakrol.
The new BESS capacity follows disclosed order activity. In its 2026 journey update, Prostarm reported a single 3 megawatt UPS order from a solar company and about 33 MWh of BESS orders from two customers. The presentation does not say whether these orders will be manufactured at Jhajjar, nor does it provide a start-up schedule beyond stating that the plant was set up in September 2026.
How did Prostarm reorganise lithium batteries and transformers?
Prostarm relocated its lithium-battery manufacturing plant to Bakrol and transferred servo-stabilizer and isolation-transformer operations to Mahape in Q2-FY27. This realignment places UPS systems and lithium-ion battery packs together at Bakrol, while Mahape is dedicated to servo stabilizers and isolation transformers.
Bakrol’s stated 100 MWh lithium-ion battery-pack capacity matches the 100,000 kilowatt-hour annual capacity that Prostarm disclosed when it expanded its Navi Mumbai lithium-ion facility in 2024. Since 100,000 kilowatt-hours equals 100 MWh, the figures are numerically equivalent, although the presentation does not disclose whether the capacity basis, utilisation or output is unchanged after the relocation.
Mahape now has stated capacity of 24,000 kilowatt-hours for servo stabilizers and 14,400 kilowatt-hours for isolation transformers. The source presents these as separate product capacities rather than a combined manufacturing measure. Promoter Sonu Ram Agarwal is identified as Business Head for Servo and Transformer, while the presentation does not provide output, order backlog or utilisation data for Mahape.
The reorganisation also separates BESS assembly at Jhajjar from lithium-ion battery-pack manufacturing at Bakrol. Jhajjar’s 1.2 GWh BESS capacity equals 1,200 MWh, making it 12 times Bakrol’s stated 100 MWh lithium-ion battery-pack capacity on a numerical energy-capacity basis. The two figures cover different products and the presentation does not state that they are directly comparable measures of annual production.
Got a follow-up? Ask IRIS
How does the expanded footprint fit Prostarm’s business mix?
Prostarm reported H1-FY27 revenue of Rs 196.1 crore, with third-party power-solution products contributing 51%, manufactured power-solution products 27% and BESS EPC 18%. BESS EPC was therefore the third-largest reported segment in the half year, behind third-party and manufactured power-solution products.
Solar EPC contributed 2% of H1-FY27 revenue, while value-added services and system integration each contributed 1%. The segment mix shows that the company’s new BESS vertical was already a reported revenue category before the September 2026 manufacturing additions, although the presentation does not quantify revenue from the Jhajjar site itself.
Revenue increased by Rs 35.2 crore from FY25 to FY26, while earnings before interest, tax, depreciation and amortisation, or EBITDA, margin declined by 0.98 percentage points to 12.00%. H1-FY27 EBITDA margin was 8.06%, but the presentation does not provide H1-FY26 revenue or margin, preventing a like-for-like half-year comparison.
Prostarm reported total orders in hand of Rs 1,120.7 crore in its Q2/H1-FY27 snapshot. Its H1-FY27 zone-wise revenue was concentrated in the West Zone at 74%, followed by the North Zone at 18%, South Zone at 5%, Central Zone at 2% and East Zone at 1%. The source does not forecast how Jhajjar or Bakrol could change this regional revenue distribution.
What BESS activity supports Prostarm’s manufacturing expansion?
Prostarm’s disclosed BESS activity includes a first BESS EPC order from Adani Electricity in 2025 for 11 megawatts and 22 MWh. The company also disclosed letters of award for a Bihar State Power Generation Co. project structured as build-own-operate-transfer, or BOOT, at 30 megawatts and 120 MWh, and a Karnataka Power Transmission Corporation Ltd. project structured as build-own-operate, or BOO, at 150 megawatts and 300 MWh.
The 300 MWh Karnataka letter of award is larger than the 120 MWh Bihar project and the 22 MWh Adani Electricity order. Together, these three disclosed projects total 442 MWh, excluding the about 33 MWh of orders from two customers reported in the 2026 journey update. The presentation does not provide execution dates, contract values, revenue recognition schedules or manufacturing allocation for these projects.
Management characterises BESS as a new high-growth vertical built on the same foundation as Prostarm’s power-electronics, system-integration, solar EPC and services businesses. That is management’s strategic positioning, not a revenue forecast. The presentation identifies C&I and utility customers, existing developer projects and BESS assembly and integration as the operating channels for the vertical.
The 1.2 GWh single-shift Jhajjar facility gives Prostarm a stated manufacturing base for this BESS strategy, while Bakrol supplies UPS systems and lithium-ion battery packs. However, the source leaves unresolved how the company will divide capacity between customer types, what proportion of the Rs 1,120.7 crore order book relates to BESS, and when capacity utilisation will be disclosed.
Conclusion
Prostarm’s September 2026 changes create a five-facility manufacturing structure led by a 1.2 GWh single-shift BESS plant at Jhajjar and a Bakrol site that combines UPS systems with 100 MWh of lithium-ion battery-pack capacity. The reorganisation also moves lithium-battery production to Bakrol and concentrates servo-stabilizer and isolation-transformer operations at Mahape, while Pune retains two production units.
What to watch next is execution against the Jhajjar capacity and the BESS projects already disclosed, including the 300 MWh Karnataka letter of award and about 33 MWh of 2026 customer orders. Prostarm has disclosed Rs 1,120.7 crore of total orders in hand, but it has not provided plant-utilisation targets, facility-level revenue targets, capital spending or commissioning milestones for Jhajjar and Bakrol.