RVNL shifts to competitive bidding across eight sectors
Key highlights
- RVNL identifies the 2021–22 Indore Metro award as its first competitive-bidding project.
- RVNL lists 8 infrastructure verticals, compared with its pre-2021 pure-railway focus.
- RVNL’s overseas map identifies 4 countries across 2 continents.
- RVNL’s Rs 13,236 crore BharatNet order was 15% complete in FY26.
powered by IRIS

In its post-2021 model, Rail Vikas Nigam Limited has shifted from Ministry of Railways-nominated domestic railway work to competitive bidding across eight infrastructure verticals and a stated presence in four overseas countries. The Indore Metro award in 2021–22 was RVNL’s first bidding project, followed by work in sectors including ports, solar, highways and communications.
Know Rail Vikas Nigam inside out
Results, valuation, peers and who's buying, in one view.
How has RVNL's business model changed since 2021?
RVNL says its post-2021 model uses competitive open bidding, diversified sectors and global deployment, replacing a pre-2021 structure based on Ministry of Railways nominations, pure railway infrastructure and domestic operations. The company identifies the Indore Metro award in 2021–22 as its first project won through bidding, marking the change in its source of business.
The stated shift developed through later milestones. In 2022–23, RVNL won the Maldives UTF Harbour project, described as its first international foray, and entered BharatNet digital infrastructure. In 2024–25, the company added solar and renewables, hydro and irrigation, power transmission, rolling-stock manufacturing, highways and ports. RVNL was elevated to Navratna central public sector enterprise status in 2023–24, and Saleem Ahmad became chairman and managing director in December 2025.
Which sectors form RVNL's current infrastructure platform?
RVNL lists eight verticals: railways, urban transport, highways, ports, energy and sustainability, hydro and irrigation, manufacturing and logistics, and communications. Railways covers doubling capacity, new construction, gauge conversion, stations, electrification and signalling. Urban transport includes metro and suburban transport, buildings and station redevelopment, while highways includes bridges, tunnels, stations, hybrid annuity model projects and build-operate-transfer projects.
The newer non-rail categories have distinct stated scopes. Ports includes harbours and port connectivity; energy and sustainability includes solar, battery storage, carbon reduction and railway electrification; and hydro and irrigation covers hydropower and irrigation. Manufacturing and logistics includes rolling stock, workshops and multi-modal logistics parks, while communications includes telecom, BharatNet and fibre-optic networks. The presentation does not provide revenue or order-book values for each of the eight verticals.
BharatNet is RVNL’s largest disclosed non-railway order at Rs 13,236 crore. Awarded by Bharat Sanchar Nigam Limited in FY25, it covers 8,206 kilometres of optical fibre for the Middle Mile network in Uttar Pradesh East and West, and physical progress was 15% in FY26. The project has a 10-year operations and maintenance commitment. Separately, the Vande Bharat sleeper programme has a total value of Rs 14,400 crore for 120 trainsets at Latur through Kinet Railway Solutions Ltd, with RVNL’s stated share at Rs 8,640 crore.
Got a follow-up? Ask IRIS
Where has RVNL expanded outside India?
RVNL’s overseas map identifies four countries across two continents: Maldives, Uzbekistan, Rwanda and Oman. The Maldives UTF Harbour covers port and marine works and is identified as RVNL’s first overseas project. Uzbekistan includes the 250-megawatt Nur Bukhara solar photovoltaic project delivered through a joint-venture entity, while Rwanda represents the power-transmission segment and Oman hosts RVNL Infra Middle East.
The company’s overseas structure includes Rail Vikas Nigam LLC in Uzbekistan and RVNL Middle East Contracting in Dubai. RVNL also lists Rail Vikas Nigam Co. Ltd in Saudi Arabia and says its 49% equity joint venture with Jakson Green is establishing solar grids, including 250 megawatts in Uzbekistan and 450 megawatts at Tabarjal, Saudi Arabia. These arrangements show that the company is using subsidiaries and joint ventures alongside project execution.
RVNL also disclosed portfolio rationalisation. Its board approved closure of RVNL Infra South Africa on 25 July 2026 and of the Kyrgyzindustry-RVNL joint venture in Central Asia on 25 May 2026. The presentation’s identified overseas sectors are ports, solar and transmission, rather than rail projects alone, although it does not disclose financial contributions from those countries or sectors.
What supports RVNL's competitive bidding strategy?
RVNL says it executes five stages in-house: concept, design and estimate, contracting, execution and commissioning. The company says design and estimate work uses delegated authority to sanction estimates within prescribed limits. Its contracting procedures are described as compliant with multilateral funding requirements, while concurrent project management is intended to avoid dependency on zonal railways for drawing approvals.
The corporate platform comprises nine subsidiaries and 10 joint ventures, according to the presentation. Chennai and Bengaluru multi-modal logistics park ventures are intended to create integrated freight hubs, while Masakani Paradeep Road Vikas and Sabbavaram Sheelanagar Road Development support road-sector activity. RVNL also cites 158 delivered mega-projects and 14 consecutive years of an “Excellent” rating from the Department of Public Enterprises as operating credentials.
The presentation reports higher consolidated financial metrics in Q2FY27 than in Q1FY27, but does not attribute the change specifically to diversification or overseas work. Revenue from operations increased 9% quarter on quarter to Rs 4,700.96 crore, from Rs 4,321.23 crore. Earnings before interest, tax, depreciation and amortisation rose 54% to Rs 294.41 crore, profit after tax increased 59% to Rs 253.71 crore, and profit-after-tax margin rose by 171 basis points to 5.40%.
Conclusion
RVNL’s presentation describes a change from domestic railway work obtained through Ministry of Railways nominations before 2021 to competitive bidding across eight sectors. The diversification is evidenced by the Rs 13,236 crore BharatNet order, the Rs 14,400 crore Vande Bharat sleeper programme, port work in the Maldives and solar activity including the 250-megawatt Uzbekistan project.
What to watch next is delivery against disclosed milestones. The first Vande Bharat sleeper prototype is due by December 2026, while the Rs 37,000 crore Rishikesh–Karnaprayag rail link was 79% complete and due in December 2028. BharatNet was 15% complete in FY26, and its 10-year maintenance commitment, alongside Vande Bharat’s 35-year commitment, provides the disclosed test of whether newer project awards create longer-duration operations and maintenance activity.