RVNL commissions 95-km line after over 300 lost workdays
Key highlights
- RVNL commissioned the 95-km Dallirajahara–Rowghat line in June 2026 at an investment of Rs 1,881 crore.
- Goods traffic and loading on the line began on 17 June 2026.
- RVNL reports more than 300 workdays lost over four years during execution in an LWE-affected area.
- The project includes 16 major bridges, 240 minor bridges, 107 signals and 161 track circuits.
powered by IRIS

RVNL commissioned the Rs 1,881 crore, 95-km Dallirajahara–Rowghat railway line in June 2026, and goods traffic began on 17 June after more than 300 workdays were lost across four years in a Left Wing Extremism (LWE)-affected corridor. RVNL reported 99% physical progress and 97% financial progress.
Know Rail Vikas Nigam inside out
Results, valuation, peers and who's buying, in one view.
What did RVNL commission on the Dallirajahara–Rowghat route?
RVNL commissioned the full 95-km Dallirajahara–Rowghat new line in Chhattisgarh in June 2026. The project carried an investment of Rs 1,881 crore, and its stated operating milestone was the start of goods traffic and loading on 17 June 2026. RVNL identifies Rowghat station as the final stop on the new line.
The disclosed commissioning status distinguishes between freight and passenger operations. RVNL says goods traffic began on 17 June 2026, while passenger approval remained awaited. The stated operational start therefore relates to freight loading rather than a confirmed start date for passenger services on the 95-km route.
How did LWE conditions affect RVNL's construction work?
RVNL says the entire 95-km alignment passed through LWE-affected territory, requiring security arrangements that restricted the construction window. Work was limited to a six-hour daytime shift after daily route sanitisation by the Sashastra Seema Bal (SSB) and Central Reserve Police Force (CRPF). Every truck, crane and rail convoy travelling to the worksite required an armed escort.
RVNL reports more than 300 days lost over four years because of bandhs, general elections and VIP movements. The company also reports sabotage and torched machinery, while security personnel were martyred and labourers were killed in attacks by LWE groups. The presentation does not quantify the cost or schedule effect beyond the lost days and the June 2026 commissioning.
These conditions made daily security clearance and escorted logistics part of the delivery process for the Rs 1,881 crore project. A six-hour workday reduced the time available for field activity, while route sanitisation had to occur before crews could begin work. RVNL nevertheless reported 99% physical progress and 97% financial progress when goods loading began on 17 June 2026.
Got a follow-up? Ask IRIS
What railway infrastructure did RVNL build on the 95-km line?
RVNL built 16 major bridges and 240 minor bridges on the 95-km Dallirajahara–Rowghat line. The 256 bridges in total show that the scope extended beyond a new rail connection through Chhattisgarh. RVNL also records 107 signals and 161 track circuits as part of the line's railway systems.
The company reports 115.4 track kilometres (TKM) of electrified track on the project. Alongside 107 signals and 161 track circuits, this shows that the disclosed scope included electrification and railway systems as well as civil works. RVNL presents these specifications with the Rs 1,881 crore investment rather than providing separate values for civil works, electrification and signalling.
The 16 major and 240 minor bridges are reported alongside the 95-km route length, but RVNL does not disclose individual bridge lengths or equipment suppliers. The presentation also gives no separate completion date for the signalling and electrification elements. Its reported status is that the entire 95-km line was fully commissioned in June 2026.
Why do physical and financial progress differ at commissioning?
RVNL reports a two-percentage-point difference at the disclosed milestone, with physical progress at 99% and financial progress at 97%. At the same time, the presentation describes the 95-km line as fully commissioned and says goods traffic started on 17 June 2026. The operational status and the reported progress measures were therefore not identical.
The presentation does not explain which work items or payments account for the difference between 99% physical and 97% financial progress. It also does not provide a revised final-cost figure beyond the Rs 1,881 crore project investment. The disclosure supports the goods-traffic start and commissioning status, but it does not establish whether all financial-closure steps were complete on 17 June 2026.
Passenger operation is the other unresolved matter in the project disclosure. RVNL says passenger approval was awaited when goods loading began on 17 June 2026. The presentation gives no approval timetable, projected passenger traffic or freight-volume estimate, so the disclosed operating evidence remains centred on the start of goods traffic.
Conclusion
RVNL's June 2026 commissioning of the 95-km Dallirajahara–Rowghat line delivered a Rs 1,881 crore rail project despite a six-hour workday, armed escorts for site logistics and more than 300 lost days over four years. The completed scope includes 256 bridges, 115.4 TKM of electrified track, 107 signals and 161 track circuits, while goods traffic began on 17 June 2026.
The next disclosed item to watch is passenger approval, which remained awaited after the freight start. RVNL also reported 99% physical progress and 97% financial progress at commissioning, leaving a two-percentage-point difference without a stated explanation or separate financial-closure date.