SEAMEC reaches seven diving-support vessels on 1,225-day charter
Key highlights
- SEAMEC added Anant in October 2026, taking its diving-support vessel fleet to seven.
- Anant began an approximately 1,225-day ONGC IMR charter valued at approximately USD 55 million excluding GST.
- SEAMEC agreed to acquire Anant from HAL Offshore Ltd for USD 70 million on 21 July 2026.
- SEAMEC Agastya commenced operations during FY26 after its 2025 procurement.
powered by IRIS

SEAMEC LIMITED reached seven diving-support vessels when SEAMEC Anant began an approximately 1,225-day ONGC inspection, maintenance and repair charter on 21 October 2026, valued at approximately USD 55 million excluding Goods and Services Tax (GST). SEAMEC acquired Anant from HAL Offshore Ltd for USD 70 million and took it over on 14 October 2026.
Know SEAMEC inside out
Results, valuation, peers and who's buying, in one view.
How did SEAMEC reach seven diving-support vessels?
SEAMEC reached seven diving-support vessels, or DSVs, by adding SEAMEC Agastya in 2025 and SEAMEC Anant in October 2026 to five previously listed DSVs. Those five vessels are SEAMEC II, SEAMEC III, SEAMEC Princess, SEAMEC Paladin and SEAMEC Swordfish. The presentation identifies DSVs as core revenue-generating assets for offshore inspection, maintenance and repair, subsea work and remotely operated vehicle deployment.
The acquisitions span more than three decades. SEAMEC II and SEAMEC III were procured in 1993, followed by SEAMEC Princess in 2006, SEAMEC Paladin in 2021, SEAMEC Swordfish in 2023 and SEAMEC Agastya in 2025. Anant was formally taken over at Kakinada at 13:10 hours on 14 October 2026 and was put on hire at 22:00 hours on 21 October 2026.
The seven-vessel count applies to the DSV fleet, not to all of SEAMEC’s marine assets. The presentation separately lists Seamec Diamond as an offshore support vessel, SEAMEC Glorious as a barge and Asian Pearl as a Handymax bulk carrier. Asian Pearl was built in 2003 and procured in 2020, while the offshore fleet serves maintenance, construction and logistics work.
Which vessels are in SEAMEC’s diving-support fleet?
SEAMEC’s disclosed DSV portfolio includes vessels built between 1982 and 2010, with gross-tonnage data available for six of the seven vessels. The Anant transaction page provides the USD 70 million acquisition value and approximately 1,225-day charter tenure, but does not disclose its build year or gross tonnage.
SEAMEC Princess is the largest disclosed DSV at 11,121 gross tonnes, compared with 4,327 gross tonnes for SEAMEC III, the smallest of the six vessels with disclosed tonnage. The newer disclosed assets are Swordfish, built in 2007 and procured in 2023, and Agastya, built in 2010 and procured in 2025. This contrasts with II and III, which were both built in the early 1980s and procured in 1993.
SEAMEC says its DSVs are equipped with dedicated diving facilities, advanced diving equipment and control systems. Their scope includes single-buoy mooring maintenance, removals and installations, platform, riser and pipeline repairs, subsea construction, maintenance operations and deployment of remotely operated vehicles. The presentation cites specialised equipment and certification requirements as barriers to entry for this work.
What are the terms of SEAMEC Anant’s acquisition and charter?
SEAMEC agreed to acquire Anant from HAL Offshore Ltd for USD 70 million and signed an approximately USD 55 million charter with HAL Offshore for approximately 1,225 days of ONGC inspection, maintenance and repair, or IMR, jobs. ONGC is the end client named in the presentation, and the charter value excludes GST.
The delivery schedule changed after the 21 July 2026 memorandum of agreement. On 31 August 2026, two addenda revised the notice-of-readiness date to 15 September 2026 and the cancelling date to 15 October 2026. SEAMEC completed the takeover one day before that cancelling date, then signed the charter and commenced operations seven days later.
The disclosed charter value is lower than the USD 70 million purchase value, but the presentation does not disclose Anant’s financing, operating costs, day rate or expected profitability. It does show that the purchase was paired with specified long-term employment, with the vessel on hire from 21 October 2026.
Got a follow-up? Ask IRIS
How does Anant affect SEAMEC’s near-term deployment plan?
SEAMEC says Anant’s long-term charter, fresh deployment of SEAMEC II and fresh deployment of SEAMEC Glorious support near-term revenue growth. The plan connects Anant’s 21 October 2026 ONGC IMR commencement with deployment activity for an existing DSV and a barge procured in 2021.
Agastya commenced operations during FY26, while Anant commenced operations during October 2026. Based on the seven vessels listed in the presentation, the DSV fleet moved from five vessels before Agastya to six during FY26 and seven after Anant’s October 2026 start. The presentation describes enhanced fleet capability and revenue-generation potential as expected outcomes, not as a numerical revenue forecast.
Other assets have separate operating roles. Seamec Diamond, built in 2011 and procured in 2023, has gross tonnage of 1,922 and supports offshore logistics and platform operations. SEAMEC Glorious, built in 2006 and procured in 2021, has gross tonnage of 8,950; the presentation says its accommodation and project-material role can have seasonal deployment linked to offshore project cycles.
What is SEAMEC’s approach to further fleet expansion?
SEAMEC says it focuses its capital allocation on demand-backed vessel acquisitions, with its balance sheet supporting future expansion opportunities. The Anant transaction follows that stated approach because the presentation records both the USD 70 million acquisition and the approximately USD 55 million, approximately 1,225-day charter for ONGC IMR work.
Management presents Agastya’s FY26 commencement and Anant’s October 2026 commencement as recent fleet additions in its Q2 and H1 FY27 presentation. It also identifies long-term employment for Anant and fresh deployment of II and Glorious as the disclosed near-term drivers, without providing a target for fleet size, revenue or earnings.
SEAMEC operates its bulk-carrier business through wholly owned SEAMEC International FZE and step-down subsidiary SEAMEC Shipping FZC. Asian Pearl, a Handymax vessel with gross tonnage of 27,989, provides dry-bulk transportation exposure, whereas the seven DSVs address offshore maintenance, construction and repair requirements.
Conclusion
SEAMEC’s seven-DSV fleet reflects two recent additions: Agastya began operations during FY26 and Anant entered service on 21 October 2026. Anant combines a USD 70 million acquisition with an approximately USD 55 million, approximately 1,225-day ONGC IMR charter, while the wider fleet includes assets procured from 1993 through 2026.
The next disclosed items to watch are execution of Anant’s charter after its 21 October 2026 on-hire date and the fresh deployments of II and Glorious. Management’s stated plan remains demand-backed acquisitions, but the presentation does not disclose Anant’s day rate, operating cost, financing or expected profitability.