ACME Solar secures 25-year NTPC PPA for 150 MW hybrid
Key highlights
- ACME Solar signed a 150 MW NTPC Hybrid-IV PPA at Rs 3.21 per unit.
- Supply from the 150 MW hybrid project is scheduled to begin on June 30, 2028.
- The NTPC PPA will run for 25 years from the June 30, 2028 supply-start date.
- ACME Solar's under-construction PPA-locked portfolio reached 5,080 MW against 5,380 MW of contracted capacity under construction.
powered by IRIS

ACME Solar Holdings Limited has secured a 25-year power purchase agreement with NTPC Limited for a 150 MW hybrid power project at Rs 3.21 per unit, with supply scheduled to begin on June 30, 2028. The agreement takes ACME Solar's under-construction PPA-locked contracted portfolio to 5,080 MW.
Know ACME Solar Holdings inside out
Results, valuation, peers and who's buying, in one view.
What did ACME Solar agree with NTPC?
ACME Solar agreed to supply power from a 150 MW hybrid project to NTPC under NTPC's Hybrid-IV tranche. The power purchase agreement, or PPA, was executed by ACME Alpha Renewables Private Limited, an ACME Solar subsidiary, and was disclosed on November 18, 2026 as a domestic contract.
The contracted tariff is Rs 3.21 per unit for the 150 MW capacity, and ACME Solar said the Central Electricity Regulatory Commission, or CERC, has adopted the tariff. The filing does not disclose the agreement's total value, annual generation, project cost, expected revenue or financing structure.
The Scheduled Commencement of Supply Date, or SCSD, is June 30, 2028, and the PPA tenure is 25 years from that date. This sets the disclosed supply-start date and contract period, although ACME Solar did not provide construction milestones before the June 2028 SCSD.
Where will ACME Solar build the hybrid project?
ACME Solar said the 150 MW project will span Bhadla in Rajasthan, Jambkhabalia in Gujarat and Mandsaur in Madhya Pradesh. The project combines solar power, wind power and energy-storage solutions across three states rather than using a single generation technology or location.
The project is connected to the Inter-State Transmission System, or ISTS, according to the November 18 announcement. Central Transmission Utility, or CTU, transmission connectivity has been secured for Jambkhabalia and Mandsaur; the disclosure does not separately state CTU connectivity status for Bhadla.
ACME Solar said the solar, wind and storage configuration is designed to provide reliable and dispatchable power throughout the day and meet the offtaker's requirements during peak-demand hours. It did not disclose the capacity split between solar and wind, storage capacity in gigawatt-hours, storage duration or a daily generation profile.
How does the NTPC PPA change ACME Solar's portfolio?
The NTPC agreement raises ACME Solar's under-construction PPA-locked contracted portfolio to 5,080 MW, compared with total under-construction contracted capacity of 5,380 MW. The two disclosed measures differ by 300 MW, indicating that this amount of under-construction contracted capacity is not included in the PPA-locked portfolio figure.
The new 150 MW contract equals about 2.8% of the stated 5,380 MW under-construction contracted capacity and about 3.0% of the 5,080 MW PPA-locked portfolio after the agreement. These are calculations based on ACME Solar's reported capacity figures, not company forecasts.
ACME Solar also reported a diversified contracted portfolio of 8,370 MW across solar, battery energy storage systems, or BESS, firm and dispatchable renewable energy, or FDRE, hybrid and wind solutions. It reported operational capacity of about 3,190 MW and BESS capacity of 5.90 gigawatt-hours.
Got a follow-up? Ask IRIS
What does the Rs 3.21 tariff cover?
The Rs 3.21-per-unit tariff applies to the 150 MW contracted capacity awarded under NTPC's Hybrid-IV tranche. ACME Solar said CERC had already adopted the tariff when it announced the PPA on November 18, 2026.
The filing does not compare Rs 3.21 per unit with tariffs from ACME Solar's earlier PPAs, other NTPC Hybrid-IV awards or other market contracts. It also does not state whether transmission, storage, scheduling or other charges are separately payable under the agreement.
The tariff is linked to a hybrid project combining solar, wind and appropriate energy-storage solutions in Rajasthan, Gujarat and Madhya Pradesh. ACME Solar describes the configuration as designed for dispatchable supply and peak-hour requirements, but does not quantify the peak-period supply hours or the energy available from storage.
What is ACME Solar scheduled to complete by June 2028?
ACME Solar is scheduled to commence supply from the 150 MW ISTS-connected hybrid project on June 30, 2028. The disclosed project footprint covers Bhadla, Jambkhabalia and Mandsaur, with CTU connectivity already secured for the Gujarat and Madhya Pradesh locations.
Nikhil Dhingra, ACME Solar's Joint Managing Director and Chief Executive Officer, said the solar, wind and storage combination would help meet peak-hour demand and support India's clean-energy transition. The announcement does not disclose a construction budget, commissioning sequence, debt plan or generation target for the project.
ACME Solar also stated that its promoter, promoter group and group companies have no interest in NTPC in relation to the agreement. The company classified the 150 MW PPA as not falling within related-party transactions.
Conclusion
The NTPC PPA gives ACME Solar a disclosed 25-year offtake arrangement for 150 MW at Rs 3.21 per unit, with CERC having adopted the tariff. It also lifts the company's under-construction PPA-locked contracted portfolio to 5,080 MW, against total under-construction contracted capacity of 5,380 MW.
The next disclosed milestone is the June 30, 2028 SCSD. Investors can watch for ACME Solar updates on development at Bhadla, Jambkhabalia and Mandsaur, the solar-wind-storage configuration, and any explanation of the 300 MW difference between its under-construction contracted and PPA-locked capacity figures.