Astra sees QRSAM work late FY28 or FY29, Su-30 orders in 2029
Key highlights
- Astra said main QRSAM execution may begin in late FY28 or FY29 after BEL receives its contract.
- Management said Su-30 radar and electronic-warfare programme orders should be considered for calendar 2029.
- Astra is executing small-quantity QRSAM FOPM orders in Q3 and Q4.
- Astra targets 12 Uttam AAAU radar deliveries by March 2028 and around 25 units in FY29.
powered by IRIS

Astra Microwave Products Limited said main QRSAM execution may begin in the final quarter of FY28 or in FY29, while management said Su-30 radar and electronic-warfare orders should be considered for calendar 2029. The timelines put both anticipated programmes beyond Astra’s immediate execution cycle, despite current QRSAM advance-action work and radar prototype activity.
Know Astra Microwave Products inside out
Results, valuation, peers and who's buying, in one view.
When will Astra begin main QRSAM execution?
Astra said main Quick Reaction Surface-to-Air Missile, or QRSAM, execution will probably start in the last quarter of FY28 or in FY29. Management said Bharat Electronics Limited, or BEL, first needs to receive the main contract, after which Astra expects its own contract to be placed within three to four months.
BEL was described as hopeful of receiving the contract between December and March, but Astra did not provide a confirmed award date. The late-FY28 or FY29 estimate is therefore conditional on BEL’s award and the subsequent placement of Astra’s contract.
Astra is already executing small-quantity orders for the FOPM version of QRSAM in Q3 and Q4. Management distinguished this advance-action work from the main QRSAM programme, which it expects to become an execution opportunity only after the main contract is awarded.
Why does QRSAM depend on BEL’s contract award?
Astra said its main QRSAM contract will follow BEL’s award, with its own contract expected three to four months later. That contracting sequence means Astra’s timeline depends on the prime contractor receiving its order as well as on Astra’s own subcontract placement.
Management said BEL had already taken advance action for the FOPM version, creating the Q3 and Q4 orders now in execution. It did not disclose the value of these orders, and their existence does not indicate that execution of the larger main QRSAM contract has begun.
An analyst referred to an earlier expectation of about Rs 700 crore to Rs 800 crore from QRSAM within a wider prospective order base. Astra did not confirm that value in its response, instead limiting its comments to BEL’s expected award window, the three-to-four-month contract interval and the possible late-FY28 or FY29 execution start.
When could Astra receive Su-30 programme orders?
Astra said calendar 2029 is when investors should look for Su-30 programme orders. Management gave this timing after explaining that Astra is participating in Defence Research and Development Organisation, or DRDO, programmes for both a radar and an electronic-warfare suite.
For the radar programme, Astra said it had delivered hardware for the first prototype of its AAAU radar to DRDO. Firmware and software integration are under way, and management said it hoped DRDO would commission the radar by next year, without specifying a calendar year.
Management said the radar and electronic-warfare suite programmes were on track from Astra’s side. Prototype hardware delivery, however, is separate from a production order, and the call did not disclose a contract value, production volume or order date for either Su-30-related product.
Got a follow-up? Ask IRIS
What supports Astra’s execution before FY29?
Astra identified Q3 and Q4 FOPM QRSAM work, joint-venture execution and Uttam radar deliveries as disclosed activities before the main QRSAM opportunity. These programmes have more defined near-term milestones than the main QRSAM contract or Su-30 orders expected in 2029.
The joint venture had an order book of Rs 900 crore and expected another Rs 1,200 crore to Rs 1,500 crore over the next six to eight months, according to management. It also had visibility for a further Rs 1,500 crore to Rs 2,000 crore over about the next year, supporting management’s stated two-to-three-year order-book visibility.
Management guided the joint venture to execute around Rs 600 crore in the current year and targeted around Rs 1,000 crore in the next year. That implies an increase of around Rs 400 crore in planned annual execution, although both figures remain management targets rather than reported results.
What is Astra’s Uttam radar delivery schedule?
Astra said it is working to deliver 12 Uttam AAAU radar units by March 2028 under the customer schedule. Management said the revised timing followed delay in contract signing and order placement, rather than a supply-chain or Astra execution issue.
The company expects an initial production rate of around 25 units in FY29, followed by 33 to 34 units thereafter. This ramp provides a disclosed production schedule before the 2029 timing management gave for Su-30 orders, although it is a separate radar programme.
Astra also committed to deliver two units to Hindustan Aeronautics Limited, or HAL, by March 2027, while trying to deliver four. Management said the contractual first milestone remains 12 units by March 2028 and that it did not expect HAL’s aircraft-delivery schedule to delay that commitment.
What margin and cash targets has Astra disclosed?
Astra said it is comfortable guiding for an earnings before interest, tax, depreciation and amortisation, or EBITDA, margin of 26% to 28% for the next two to three years. Management said the quarter under discussion had more production orders and a higher EBITDA margin, but retained the same 26% to 28% range as its planning assumption.
Management said operating leverage may emerge because it does not expect its fixed-cost base to rise dramatically. It did not increase its margin guidance, and said any improvement would depend on execution and product mix as programmes including QRSAM move toward later periods.
On cash generation, management targeted free cash flow of Rs 250 crore to Rs 350 crore, compared with more than Rs 300 crore in the previous year. It also said receivables were about 200 days, targeted a cash-conversion cycle of 350 days and aimed to reduce working-capital limits to zero by year-end.
Conclusion
Astra has clarified that the main QRSAM opportunity and Su-30 orders have later timelines than current pipeline discussions may suggest. Main QRSAM execution depends on BEL first receiving its contract and may start only in late FY28 or FY29, while management placed Su-30 radar and electronic-warfare orders in calendar 2029. In the interim, joint-venture execution, FOPM QRSAM activity and Uttam deliveries provide the more specific disclosed operating milestones.
The next event to watch is whether BEL receives the main QRSAM contract in the December-to-March period cited by management, followed by Astra’s expected three-to-four-month contract process. Other disclosed milestones are DRDO’s hoped-for commissioning of the AAAU radar prototype by next year, delivery of 12 Uttam units by March 2028, and the joint venture’s target of around Rs 1,000 crore of execution in the next year.