e2E Rail order book reaches Rs 1,200 crore on government work
Key highlights
- e2E Rail reported an approximately Rs 1,200 crore order book, including GST and L1s, as of 11 November 2026.
- e2E Rail's executable order book was Rs 994 crore, comprising Rs 870 crore of B2G work and Rs 124 crore of B2B work.
- e2E Rail received Rs 724.04 crore of FY27 year-to-date orders across 12 B2G and seven B2B awards.
- e2E Rail said B2G ticket sizes have shifted from Rs 20-60 crore earlier to Rs 50-500 crore now.
powered by IRIS

e2E Rail reported an order book of about Rs 1,200 crore, including Goods and Services Tax (GST) and L1s, on 11 November 2026, while its executable order book stood at Rs 994 crore. Government business accounted for Rs 870 crore of executable work, and e2E Rail said its government contract sizes had shifted from Rs 20-60 crore to Rs 50-500 crore.
Know E to E Transportation Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
What is e2E Rail's current order book?
e2E Rail's current order book was about Rs 1,200 crore as of 11 November 2026, including GST and L1s. Its executable order book, which excludes GST and L1s, was Rs 994 crore, distinguishing the work available for execution from the broader reported order-book measure.
The executable total was weighted towards business-to-government (B2G) contracts, which accounted for Rs 870 crore, while business-to-business (B2B) work accounted for Rs 124 crore. The government component was therefore substantially larger than private-sector work within the Rs 994 crore executable book, although the presentation did not provide execution dates for individual orders.
How much business has e2E Rail secured in FY27 year to date?
e2E Rail reported Rs 724.04 crore of orders received in financial year 2027 (FY27) year to date, including GST and L1s. The total comprised 12 B2G orders worth Rs 568.80 crore and seven B2B orders worth Rs 155.24 crore, or 19 orders in all.
B2G awards contributed more value and more orders than B2B awards in FY27 year to date: Rs 568.80 crore from 12 government orders compared with Rs 155.24 crore from seven private-sector orders. That mix is consistent with the Rs 870 crore B2G share of the executable order book, although the two measures cover different disclosed order-book views.
The presentation also identifies the Rs 724.04 crore figure as “illustrative secured orders” in its category analysis. That table divides the secured-order total among capacity expansion, Mission Raftar, private siding and signalling categories, rather than treating it as a replacement for the Rs 994 crore executable order book.
Which categories make up e2E Rail's secured orders?
e2E Rail's largest disclosed secured-order category was capacity expansion at Rs 183.4 crore, or 25.33% of the Rs 724.04 crore illustrative secured-order total. Mission Raftar followed at Rs 179.2 crore, or 24.75%, leaving a Rs 4.2 crore gap between the two largest categories.
Private siding contributed Rs 155.24 crore, representing 21.44% of the illustrated secured-order total. Signalling work totalled Rs 206.2 crore across Rs 97.5 crore of signalling for new lines and Rs 108.7 crore of signalling upgrades, placing it ahead of private siding when the two signalling categories are combined.
Got a follow-up? Ask IRIS
How has e2E Rail's government contract size changed?
e2E Rail said its earlier average B2G order value was Rs 20-60 crore, compared with Rs 50-500 crore now. The current range begins at a higher value than the former range and extends far beyond its previous Rs 60 crore upper end.
The company cited its Kalahasti project order, worth more than Rs 200 crore, as an example of the shift to larger B2G tickets. This disclosure concerns contract-size mix and does not specify the project’s revenue-recognition schedule or establish that every future B2G award will exceed Rs 200 crore.
The shift is set against Rs 568.80 crore of B2G orders across 12 FY27 year-to-date awards. That award value records orders received, while the Rs 50-500 crore range describes the order sizes e2E Rail says it is now pursuing in the B2G market.
What pipeline does e2E Rail have for the next six months?
e2E Rail reported a current pipeline of Rs 3,423.1 crore, comprising Rs 664.4 crore of result-awaited bids, Rs 173.7 crore of high-probability bids and Rs 2,585 crore of third-quarter and fourth-quarter bids. The result-awaited component covered 10 bids, while the high-probability group comprised three B2G bids and one B2B bid.
Management presented visibility of more than Rs 1,000 crore over the next six months using a 30% bid-conversion ratio. This is management's pipeline-based scenario rather than a secured-order figure: FY27 year-to-date secured orders were Rs 724.04 crore, while the full current pipeline was Rs 3,423.1 crore.
The company identified Automatic Block Signalling, signalling upgrades, private siding, and new lines, doubling and third-line projects as participation areas. These areas correspond with the Rs 183.4 crore capacity-expansion category, Rs 206.2 crore of combined signalling categories and Rs 155.24 crore of private-siding orders in the illustrated FY27 secured-order mix.
Conclusion
e2E Rail's 11 November 2026 disclosure shows Rs 994 crore of executable orders within an approximately Rs 1,200 crore reported order book, with Rs 870 crore assigned to B2G and Rs 124 crore to B2B. Its Rs 724.04 crore of FY27 year-to-date awards were spread across five categories, led by Rs 183.4 crore of capacity expansion and Rs 179.2 crore of Mission Raftar work.
The next point to watch is whether the Rs 3,423.1 crore pipeline converts into orders, particularly the Rs 664.4 crore of result-awaited bids and Rs 2,585 crore of third-quarter and fourth-quarter bids. Management's more than Rs 1,000 crore six-month visibility assumes a 30% bid-conversion ratio, while the stated Rs 50-500 crore B2G ticket range provides a benchmark for the size of future awards.